How long do roof deck permits take in San Francisco's North Beach neighborhood?

In the North Beach neighborhood of San Francisco, only 2 roof deck permits filed from October 2025 through September 2026 have been issued, too few for a reliable figure. Only 2 of the permits filed from October 2023 through September 2024 have reached final sign-off, too few for a reliable figure.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long roof deck permits take in San Francisco's North BeachneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offFewer than 5 permits in every quarter of the last 10 years: no median to draw.Source: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/north-beach/roof-deck · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 20262 issuedunder 55 issued5
Permit issued to final sign-offOctober 2023 through September 20242 finishedunder 56 finished344

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 32 days to issue and 250 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q34200too recent
2025-Q32220too recent
2025-Q22110too recent
2025-Q11000too recent
2024-Q42220too recent
2024-Q32110yes
2024-Q21100yes
2024-Q11110yes
2023-Q42200yes
2023-Q33220yes
2023-Q23330yes
2023-Q11110yes
2022-Q31101yes
2021-Q41000yes
2021-Q34313yes
2021-Q21001yes
2021-Q12220yes
2020-Q42211yes
2020-Q31110yes
2020-Q13210yes
2019-Q33221yes
2019-Q23220yes
2019-Q11110yes
2018-Q43100yes
2018-Q34440yes
2018-Q22110yes
2018-Q14330yes
2017-Q34440yes
2017-Q22210yes
2016-Q43211yes
2016-Q34330yes
2016-Q22211yes
2016-Q15321yes
2015-Q42211yes
2015-Q33311yes
2015-Q24321yes
2015-Q13110yes
2014-Q43220yes
2014-Q32211yes
2014-Q22220yes
2014-Q12220yes
2013-Q35431yes
2013-Q22000yes
2013-Q12110yes
2012-Q41110yes
2012-Q31110yes
2012-Q11100yes
2011-Q44440yes
2011-Q31110yes
2011-Q11110yes
2010-Q41101yes
2010-Q32210yes
2010-Q11100yes
2009-Q42110yes
2009-Q21110yes
2009-Q11110yes
2008-Q410913574682725411yes
2008-Q36617434731yes
2008-Q2973123662311,4721yes
2007-Q4559981852181,2250yes
2007-Q32220yes
2007-Q22220yes
2007-Q11110yes
2006-Q42210yes
2006-Q31100yes
2005-Q41110yes
2005-Q33320yes
2005-Q21110yes
2005-Q11110yes
2004-Q41110yes
2004-Q31110yes
2004-Q21110yes
2004-Q11100yes
2003-Q43321yes
2003-Q11110yes
2002-Q42210yes
2002-Q21110yes
2001-Q41110yes
2001-Q31001yes
2000-Q12200yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

21 of the 185 roof deck permits filed since 2000 (11%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's North Beach neighborhood

Shown apart, with their own page here: bathroom remodel (1,585 filed, 1,119 finished; contractors); kitchen remodel (1,580 filed, 1,137 finished; contractors); stairs (630 filed, 414 finished; contractors); deck (271 filed, 194 finished; contractors); roof deck (185 filed, 114 finished; contractors). Other types: 11,297 permits. All permits in San Francisco's North Beach neighborhood

Nearby neighborhoods

Chinatown, Russian Hill, Nob Hill; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.