How long do kitchen remodel permits take in San Francisco's North Beach neighborhood?

In the North Beach neighborhood of San Francisco, of the 44 kitchen remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 2 days, up from 1 day a year earlier. Of the 24 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 206 days of being issued, down from 239 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long kitchen remodel permits take in San Francisco's NorthBeach neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/north-beach/kitchen · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202644 issued245 issued1
Permit issued to final sign-offOctober 2023 through September 202424 finished20645 finished239

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 176 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q3960520too recent
2026-Q2242332740too recent
2026-Q110903861381520too recent
2025-Q46606820too recent
2025-Q31313388111082970too recent
2025-Q21080145941200too recent
2025-Q19911071112290too recent
2024-Q41615623740too recent
2024-Q31212021072665090yes
2024-Q210100852074090yes
2024-Q1880562103770yes
2023-Q488231616603020yes
2023-Q31414046131545040yes
2023-Q21313828112874462yes
2023-Q1990191974410yes
2022-Q41716022122002573yes
2022-Q31414020102615474yes
2022-Q21717011391895228yes
2022-Q11212057112466071yes
2021-Q41614038132336072yes
2021-Q31715036111372585yes
2021-Q21313024122567561yes
2021-Q120200175143991,2454yes
2020-Q41414092121824330yes
2020-Q315135111131896091yes
2020-Q25502851051780yes
2020-Q116150285143078911yes
2019-Q42725022192776714yes
2019-Q32623033211781,2092yes
2019-Q2141306691841,0303yes
2019-Q1171604215974962yes
2018-Q499050751454893yes
2018-Q329251258211491,2101yes
2018-Q22826063231807763yes
2018-Q11413042111908922yes
2017-Q41312019891696323yes
2017-Q32623075191154262yes
2017-Q2221902318813001yes
2017-Q1171702316904091yes
2016-Q41515011131792670yes
2016-Q326241541161603905yes
2016-Q22121036181943682yes
2016-Q12221060171906443yes
2015-Q4161603891753166yes
2015-Q327270246181148576yes
2015-Q2151505121663982yes
2015-Q1202002161004764yes
2014-Q416160360101831,9105yes
2014-Q321210222162064045yes
2014-Q2141407133124721yes
2014-Q122220121892141yes
2013-Q4262602224924782yes
2013-Q332320328852324yes
2013-Q22524018191103643yes
2013-Q1252503421826181yes
2012-Q415150214611260yes
2012-Q31616031214502582yes
2012-Q2212003618582651yes
2012-Q12424046221243530yes
2011-Q414140891976052yes
2011-Q319170205142294550yes
2011-Q21313024121563720yes
2011-Q199058632190yes
2010-Q41614032121322662yes
2010-Q36604021yes
2010-Q2121106172784253yes
2010-Q12118237172032841yes
2009-Q41917052101573800yes
2009-Q31818012121102641yes
2009-Q21919022161292261yes
2009-Q110903361422963yes
2008-Q4990542yes
2008-Q3191613051464224yes
2008-Q2121204182423950yes
2008-Q1161606122073942yes
2007-Q42020012171583172yes
2007-Q3990151903550yes
2007-Q212120091473721yes
2007-Q199031182155590yes
2006-Q499047961103510yes
2006-Q3131304392944431yes
2006-Q216160082895433yes
2006-Q1161600131745370yes
2005-Q4660040yes
2005-Q3171706101042170yes
2005-Q21413006902721yes
2005-Q112100071543191yes
2004-Q413130026yes
2004-Q31616086131142641yes
2004-Q25508240yes
2004-Q11212007912082yes
2003-Q42220yes
2003-Q31212009551701yes
2003-Q215150011991902yes
2003-Q113130061352581yes
2002-Q414140012602640yes
2002-Q377006902820yes
2002-Q2770030yes
2002-Q1770072453480yes
2001-Q48801971452290yes
2001-Q3660052312710yes
2001-Q29803361361740yes
2001-Q1550020yes
2000-Q4660030yes
2000-Q38801540yes
2000-Q213130091402350yes
2000-Q19901640yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

156 of the 1,580 kitchen remodel permits filed since 2000 (10%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's North Beach neighborhood

Shown apart, with their own page here: bathroom remodel (1,585 filed, 1,119 finished; contractors); kitchen remodel (1,580 filed, 1,137 finished; contractors); stairs (630 filed, 414 finished; contractors); deck (271 filed, 194 finished; contractors); roof deck (185 filed, 114 finished; contractors). Other types: 11,297 permits. All permits in San Francisco's North Beach neighborhood

Nearby neighborhoods

Chinatown, Russian Hill, Nob Hill; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.