Permit GraphSan Francisco building permits since 2000

Block 0206, lot 008

500 Sansome St

The 200 most recent permits filed for this property.

CompletedIn progressNever finaledExpired or cancelled
FiledOutcomeAddressContractorWork described on the permitDeclared cost
May 20, 2026In progress
issued Jul 2026
500 Sansome StCentric Construction Inc6/f suite 600 - t.i buildout of an (e) office space. scope include new open office space, enclosed office space, employeee kitchenette and storage. new office space will utilize (e) men's and women's restrooms on 6/f.$1,300,000
Oct 15, 2025Completed
final sign-off Oct 2025
500 Sansome StBilcor Inc1st floor & mezz: relocate 9 wall mount horn strobes and install 2 wall mount strobes. ref to 202503263112$2,664
Aug 29, 2025Completed
final sign-off Dec 2025
500 Sansome StC B F Inc#100: new lighting, branch circuiting.provide new power and signal. ref pa#202503263112$440,000
Jul 30, 2025Completed
final sign-off Sep 2025
500 Sansome StAct Now Fire Inspectionti: on existing vacant office space fire sprinkler relocation. ref# 202503263112$8,000
May 30, 2025Completed
final sign-off Dec 2025
500 Sansome StCentric Construction Inc1st floor: deferred structural for pa #202503263112
Mar 26, 2025Completed
final sign-off Dec 2025
500 Sansome StCentric Construction Inc1/fl and mezzanine- ti including dmeo and construction of non structual partitions ceilings, finishes and ffe. (n) restrooms and breakroom. deferred mep$4,360,000
Nov 10, 2023Completed
final sign-off Jan 2025
500 Sansome StBilcor Inc(1) flush mount control relay. arch ref#: 202102043991$666
May 12, 2021Completed
final sign-off Sep 2021
500 Sansome StR L H Fire Protection Incti/upgrade of existing fire sprinkler system 1 relocated pendent sprinkler 2 relocated upright sprinklers 1 additional upright sprinkler ref. # 2020-1120-9425$1,500
Feb 4, 2021Completed
final sign-off Jan 2024
500 Sansome StCentric Construction Incdemolition of (e) front door, glazing & finishes per plan.construction of (n) front doors and glaszing at (e) opening.construction of new structural supports as needed for (n) construction.$30,000
Nov 20, 2020Completed
final sign-off Dec 2021
500 Sansome StCentric Construction Incdemo and removal of (e) walls and (1) run of stairs within stairwell 1. construction of (n) walls, stairs and landing to accomodate (n) layout within stairwell 1.$150,000
Jul 17, 2020Never finaled
issued Sep 2020, no final
500 Sansome StBilcor Incfire life safety. install(3) wall mount strobes, (7) wall mount horn stobes, (6) duct detectors and (6) control relay modules. reference t.i. #2020-0228-5671$14,520
Jun 12, 2020Never finaled
filed Jun 2020, never issued
500 Sansome StR L H Fire Protection Incste. #402 - t.i. fire sprinkler: relocate 49 heads, add 16 heads, remove 11 sprinkler heads. ref ti pa202002285671. maher n/a.$19,000
Feb 28, 2020Never finaled
issued Mar 2020, no final
500 Sansome StCentric Construction Incste. #402 - demo of (e) non-load bearing partitions, doors & lighting; construction of (n) non-load bearing partitions, doors, finishing & lighting.$605,646
Sep 25, 2018Never finaled
issued Oct 2018, no final
500 Sansome StHathaway Dinwiddie Co.partial tenant improvement for single full floor tenant. enclose small office space, install presentation rails. replace ceiling tiles and finishe upgrades in selected rooms. minor elec to install av screen and back lit panel in 2 rooms will be design build under sep permit. no structural scope. no$5,000
Nov 22, 2017Completed
final sign-off Dec 2017
500 Sansome StR L H Fire Protection Incfire sprinkler relocate 2, add 10, delete 3 pendent sprinklers. relocate 4, delete 1 upright sprinkler 4th fl ti 201710171389$6,500
Nov 21, 2017Completed
final sign-off Jan 2018
500 Sansome StBilcor Incsuite 410: f/a t.i.: insatll 3 celing mount hron strones,, 1 ceiling mount strobe, 1 wall mount horn/strobe. wall mount strobe, 2 duct detectors w/ sampling tube, 2 control relay mods, ref t.i. 201710171389. maher n/a.$5,000
Oct 17, 2017Completed
final sign-off Jan 2018
500 Sansome StCentric Construction Incsuite 410, construction of new non load bearin partitions, doors paint, lighting, finishes maher not req$350,000
Mar 27, 2017Completed
final sign-off Apr 2017
500 Sansome StTurner Construction Coref 201702149331 electrical permit maher not req$150,000
Mar 21, 2017Completed
final sign-off Apr 2017
500 Sansome StIngram Fire Protection Increlocate 4 head fire sprinklers. ref pa 2017-0214-9331$4,100
Mar 20, 2017Completed
final sign-off Apr 2017
500 Sansome StBilcor Incsuite #370: fire alarm t.i. to relocate 1 wall mount horn strobe. ref app#201702149331$1,000
Mar 2, 2017Completed
final sign-off Apr 2017
500 Sansome StBilcor Incfire alarm tenant improvement install (1) ceiling mount horn strobe ref pa 2017-0201-8375. maher na$500
Feb 22, 2017Completed
final sign-off Mar 2017
500 Sansome StR L H Fire Protection Inc5th flr, suite 510: fire sprinkler permit. relocate 18 and add 1. ref ti 2017-0201-8375 maher na$5,500
Feb 14, 2017Completed
final sign-off Apr 2017
500 Sansome StTurner Construction Co3rd fl suite 370 partial remodel of the 3rd fl walls. ceilings, new non load bearing walls, doors, ceiling etc. mep sprinklers, fire protection and signs under seperate permits. maher not req$80,000
Feb 1, 2017Completed
final sign-off Apr 2017
500 Sansome StCentric Construction Inc5th floor: demo of extg non-load bearing partitions, doors, lighting, & finishes. construction of new non-load bearing partitions, doors, paint, new lighting and finishes. n/a for maher. alarm/sprinkler deferred.$200,000
Oct 11, 2016Completed
final sign-off Nov 2016
500 Sansome StBilcor Inc4th floor: fire alarm t.i. install 1 small detector with base. ref app# 201507141392. n/a for maher$400
Jun 23, 2016Completed
final sign-off Aug 2016
500 Sansome StBilcor Incsuite 350: fire alarm ti install (4) ceiling mount horn-strobes, install (1) ceiling mount strove, install (6) duct detectors, install (6) control relay modules. ref ti 2016-0405-3980$6,800
May 12, 2016Never finaled
issued May 2016, no final
500 Sansome StBilcor Inc3rd floor - install 4 horn/strobes, 1 strobe, 6 duct detectors, & 6 control relays. ref pa #201604053980. n/a maher ordinance$5,500
May 3, 2016Completed
final sign-off Jun 2016
500 Sansome StR L H Fire Protection Incfire sprinkler permit, relocate 30, add 3 and delete 15 pendent sprinklers, install 55 new uprights and delete 3 uprights on the 3/f. t.i. pa#201604053980. n/a ordinance #155-13$34,900
Apr 5, 2016Never finaled
issued Apr 2016, no final
500 Sansome StCentric Construction Incste 350, demo of (e) non-load bearing partitions, doors, lighting & mechanical system; construction of (n) non-load bearing partitions, doors & paint, (n) lighting & (n) mechanical system. maher na$648,490
Mar 4, 2016Completed
final sign-off Jun 2016
500 Sansome StJohnson Controls Fire1st & basement: relocate (e) facu from 1st flr to basement, provide & install new (1) smoke detector above facu and (1) remote annunciation in the lobby; maher n/a$25,000
Aug 25, 2015Completed
final sign-off Sep 2015
500 Sansome StR L H Fire Protection Inc4th floor suite 450 fire sprinkler for tenant improvement - 72 heads. reference pa #201507141392. n/a maher ordinance$18,910
Aug 19, 2015Completed
final sign-off Jan 2016
500 Sansome StBilcor Incsuite #450: fire alarm t.i. install 5 ceiling mount horn-strobes, 5 ceiling mount strobes, 5 control relays, and 5 duct detectors. ref. appl. 2015.0714.1392. maher n/a.$8,000
Jul 14, 2015Never finaled
issued Jul 2015, no final
500 Sansome StCentric Construction Inc4th floor suite 450 - demo of (e) non-load bearing partitions, doors & lighting. construction of (n) non-load bearing partitions, doors & paint & lighting. n/a maher ordinance$605,646
May 19, 2015Completed
final sign-off Jun 2015
500 Sansome StBilcor Incunit #615: fire alarm t.i. install 3 ceiling mount horn-strobes. install 1 ceiling mount strobe. maher na$1,600
Apr 20, 2015Completed
final sign-off May 2015
500 Sansome StR L H Fire Protection Inc6th flr: fire sprinkle ti - relocate 8 and add/modify 11, total 19 heads. ref 2015 0311 0547 maher - not req'd$8,990
Mar 11, 2015Never finaled
issued Mar 2015, no final
500 Sansome StCentric Construction Incdemo of (e) non-load bearing partitions, doors, (e) out of commission, mech duct. construction of (n) non load bearing partitions, doors, paint maher - not req'd$341,935
Feb 23, 2015Completed
final sign-off Mar 2015
500 Sansome StBilcor Incste. 500: fire alarm tenant improvement: install 6 ceiling mount horn strobes. install 5 duct detectors with built in relay. parent ti permit: 2014-1202-2783 maher - not req'd$4,400
Feb 12, 2015Completed
final sign-off Mar 2015
500 Sansome StR L H Fire Protection Incfire sprinkler ti 5th fl suite 500. add 38 pendents and relocate 2 upright. 40 heads total (also, removing 25 uprights) ref 201412022783 maher not req$11,960
Feb 9, 2015Completed
final sign-off Jul 2015
500 Sansome StBilcor Incfire alarm t.i. in basement - relocate 1 ceiling mount horn-strobe, install 2 smoke detectors with base. n/a ordinance #155-13$1,200
Dec 26, 2014Completed
final sign-off Aug 2015
500 Sansome StCentric Construction Incbasement:construction of new non-load bearing partitions, doors and carpet. there is no electrical work or mechanical work on this permit. n/a for the maher.$27,740
Dec 15, 2014Never finaled
issued Dec 2014, no final
500 Sansome StBilcor Inc#300- fire alarm tenant improvement, install 9 ceiling mount horn-strobes, install 4 duct detectors. t.i. pa# 201410290219. n/a ordinance #155-13.$5,200
Dec 4, 2014Completed
final sign-off Mar 2015
500 Sansome StR L H Fire Protection Incbasement & 1st flr: fire sprinkler permit, add 16 upright sprinklers in the basement, t.i. 201302260933, relocate 3 and add 1 pendant on the 1st flr t.i. 20141010810; maher n/a$10,280
Dec 2, 2014Completed
final sign-off May 2015
500 Sansome StCentric Construction Incconstruction of (n) non-load bearing partitions, doors, side lights, ceiling, paint, carpet, lightight & electrical work. all work in suite 500, 5th floor. f/a and sprinklers under separate permit.$1,172,000
Dec 1, 2014Completed
final sign-off Jan 2015
500 Sansome StR L H Fire Protection Incfire sprinkler relocate 33, add 3, delete 7 pendents. relocte 1, add 4, delete 3 uprights on 3rd fl.$20,560
Oct 29, 2014Never finaled
issued Nov 2014, no final
500 Sansome StCentric Construction Inc3rd floor - demolition of (e) non load bearing partitions, doors, ceilings, carpet and lighting. construction of new non-load bearing partiions, doors, sidelights, ceiling, paint, carpet, lighting and power. sprinklers, fire alarm sep. permits maher n/a.$801,000
Oct 10, 2014Never finaled
issued Oct 2014, no final
500 Sansome StCentric Construction Inc1st flr: demolition of (e) signage, construction of (n)n non-load bearing ceilings & lights; maher n/a$84,003
Sep 30, 2014Completed
final sign-off Sep 2014
500 Sansome StBilcor Incas built revision to pa#: 2014-0813-3742
Aug 15, 2014Never finaled
issued Aug 2014, no final
500 Sansome StCentric Construction Incsuite 750 - demolition of (e) non-load bearing partitions + doors. construction of (n) non-load bearing partitions, door, paint. compliance with maher ordinance 155-13 not required.$37,330
Aug 14, 2014Completed
final sign-off Sep 2014
500 Sansome StR L H Fire Protection Inc2nd floor fire sprinkler permit - relcoate 32 pendents & 6 upright sprinklers, add 73 pendents & 1 upright. ref t.i. #2014.0612.8262. n/a maher ordinance$56,540
Aug 13, 2014Completed
final sign-off Oct 2014
500 Sansome StBilcor Incinstall 11 ceiling mount horn strobes, install 7 duct detectors with built in control relay$7,200
Jul 9, 2014Never finaled
issued Jul 2014, no final
500 Sansome StBilcor Incremove and replace 5 booster panels, ti #201309096337 and 201207124658.; maher n/a; (fire lite fcps -24f56)$2,000
Jun 12, 2014Completed
final sign-off Nov 2014
500 Sansome StCentric Construction Inc2nd flr, ste 200: construction of new non-load bearing partitions, ceiling, paint, carpet & lighting; compliance with ord 155-13 not required, fire alarm/sprinkler under seperate permit.$1,105,000
Jun 5, 2014Never finaled
issued Jun 2014, no final
500 Sansome StBilcor Incinstall: 1 booster panel, 1 ceiling mount strobe, 6 ceiling mount horn-strobes, 2 wall mount strobes, 2 wall mount horn-strobes, 3 smode detectors with base, 2 duct detectors with relay control, 2 relay control modules, 1 signal module. ref pa# 2014-0328-1887.$8,000
May 16, 2014Completed
final sign-off Aug 2014
500 Sansome StAnderson, Rowe & Buckley, Inc.2nd floor:fire sprinkler t.i. relocate 30 heads and adding 16 heads. total 46. n/a for the maher ordinance #155-13. t.i. 201403281887$24,272
Mar 28, 2014Completed
final sign-off Aug 2014
500 Sansome StCentric Construction Inc2nd fl: demo e non load bearing partitions, ceiling, lights. new non load bearing partitions, ceiling, paint, carpet, lighting. 2nd fl 220: demo e non load bearing partitons, ceiling, lights. new non load bearing partitions, ceiling, paint, carpet, lighting. 5th fl demo e non load bearing partitons,$375,000
Mar 28, 2014Completed
final sign-off Sep 2014
500 Sansome StCentric Construction Inc(rooftop): construction of new stairs and new raised walkways at e equipment platforms$55,000
Dec 17, 2013Never finaled
issued Dec 2013, no final
500 Sansome Ststreet space
Dec 16, 2013Completed
final sign-off Jan 2014
500 Sansome StJohnson Controls Firerenovation of existing fire alarm system. add 1 smoke detector, 30 h0rn strobes, 7 strobes, 15 duct detectors. ti 1st fl and mezzanine$14,000
Dec 12, 2013Completed
final sign-off Jan 2014
500 Sansome StPotter Fire Protection2nd fl. install fire sprinkler system on the 2nd floor. total 118 sprinklers.$45,000
Nov 25, 2013Completed
final sign-off Jul 2014
500 Sansome StR L H Fire Protection Incfire sprinklers: remove 36 sprinklers and piping from stairwell #2 on all floors. relocate 1 upright$5,000
Nov 8, 2013Completed
final sign-off Jul 2014
500 Sansome StR L H Fire Protection Incfire sprinkler permit:install 44 pendents and 10 uprights on floors on 3-7 floors. relocate 4 pendents on 8th floor. t.i. app#201309096337 and 201207124658 and for 8th floor 201302140246.$29,812
Nov 1, 2013Completed
final sign-off Sep 2014
500 Sansome StJohnson Controls Fire1st floor to 7th floor: fire alarm t.i. add 4 control zam, 25 smoke sensors, 13 duct detectors, 6 door holders, 3 strobes, 29 horn/strobes, relocated 1 (e) smoke, 1 horn/strobe, 1 pull station to new location. remove 4 (e) smoke sensors.$14,000
Oct 31, 2013Completed
final sign-off Dec 2013
500 Sansome StPotter Fire Protectionrelocate 30 fire sprinkler on the 5th floor. ref app#201307010869$13,000
Oct 28, 2013Completed
final sign-off Jan 2014
500 Sansome StPotter Fire Protection1st floor and mezz:install a fire sprinkler system on the 1st floor. bldg app#201308124076$70,000
Oct 23, 2013Completed
final sign-off Jan 2014
500 Sansome StCentric Construction Incdemo of extg non-load bearing partitions. construction of new non-load bearing partitions, paint, and carpet. sprinkers separate permit ste 350$75,000
Oct 1, 2013Completed
final sign-off Apr 2014
500 Sansome StCentric Construction Inc1st floor and mezz:project consists of mechanical and electrical interior t. i. architectural improvements under prior approval app#201308124076.extent of work is limitted to 1st floor and mezzanine. no change in bldg height or floor area. bldg is fully accessible.$565,000
Sep 10, 2013Completed
final sign-off Nov 2013
500 Sansome StR L H Fire Protection Inc4th floor fire sprinkler t.i. - 38 fire sprinkler heads. ref pa #201307010872$9,532
Sep 9, 2013Completed
final sign-off Sep 2014
500 Sansome StCentric Construction Inc7th floor corridor: demo of extg non load bearing partitions, ceiling and lights. construction of new non-load bearing partitions, ceilings, paint, carpet and lighting.$60,000
Aug 12, 2013Completed
final sign-off Apr 2014
500 Sansome StCentric Construction Inc1st floor & mezz - interior tenant improvement including new partitions, ceilings, finishes, new stair & guardrail. mep deferred.$1,122,600
Aug 9, 2013Never finaled
issued Aug 2013, no final
500 Sansome StSimplexgrinnell Lp.revision to 201304124377. adding 12 duct smoke detectors. reference approved mechanical 2013.0809.3912$7,000
Aug 9, 2013Never finaled
issued Aug 2013, no final
500 Sansome StCentric Construction Increplacement of 1st fl/mezzanine windows and front entry. new window to match e frames in finish and color. new windows have spandrel at floor level as it currently does$200,000
Aug 9, 2013Completed
final sign-off Apr 2014
500 Sansome StCentric Construction Inchvac equipment and ducts; ref. 201302140246; 1 new fire smoke damper, smoke detector, required in air handlers, fire alarm separate permit$162,000
Aug 2, 2013Never finaled
issued Aug 2013, no final
500 Sansome Ststreet space
Jul 30, 2013Completed
final sign-off Jul 2014
500 Sansome StSimplexgrinnell Lp.fire alarm ti for 1st fl through roof and mezzaninie 10 duct detectors$10,000
Jul 30, 2013Completed
final sign-off Jun 2014
500 Sansome StSimplexgrinnell Lp.fire alarm ti new elevator power on roof. add 1 new smoke sensor 5 heat sensors, 4 control zam, 2 supervised iam. reference ti 2013.0523.7736$8,000
Jul 25, 2013Completed
final sign-off Jun 2014
500 Sansome StSimplexgrinnell Lp.3rd floor:fire alarm t.i- add 9 new horn/strobe, 5th strobes, 5 smoke detectors, 7 duct detectors with 7 remote test station, 2 door holders. remove and cover extg 1 horn/strobe, relocate extg horn/strobe to new location. t.i. #201305177209$14,000
Jul 23, 2013Never finaled
issued Jul 2013, no final
500 Sansome StPotter Fire Protection3rd floor - relocate 33 add 1 fire sprinklers. ref pa #2013.05.17.7209$13,500
Jul 22, 2013Completed
final sign-off Aug 2013
500 Sansome StSimplexgrinnell Lp.all floors-add 9 smoke detectors on each floor for new risers$9,000
Jul 3, 2013Never finaled
issued Jul 2013, no final
500 Sansome Ststreet space
Jul 1, 2013Completed
final sign-off Sep 2014
500 Sansome StCentric Construction Inc5th floor-corridor-demo of (e) non load bearing partitions, ceiling & lights. construct of new non load bearing partitions, ceiling, paint, carpet & lighting. suite #501/502/503-demo of (e) non load bearing partitions. construct new non load bearing partitions, doors, sidelghts, ceiling, carpet, pa$375,000
Jul 1, 2013Completed
final sign-off Aug 2014
500 Sansome StCentric Construction Inc4th floor-corridor-demo of (e) non load bearing partitions, ceiling & lights. constr. new non load bearing partitions, ceiling, paint, carpet & lighting. suite #402/450-demo of (e) non load bearing partitions. construct new non load bearing partitions, doors, sidelghts, ceiling, carpet, paint, li$370,000
May 24, 2013Never finaled
issued May 2013, no final
500 Sansome Ststreet space
May 23, 2013Never finaled
issued Oct 2013, no final
500 Sansome StCentric Construction Incdemolition of (e) elevator shaft at penthouse. construction of new elevator shaft & hoistway beam at penthouse. construction of new mechanical units & support & new rated fresh air shaft$250,000
May 20, 2013Completed
final sign-off Apr 2014
500 Sansome StSimplexgrinnell Lp.fire alarm t.i. rest room renovation to mezz, 2nd, 3rd, 4th,5th, 6th, 7th, 8th floors. 16 strobes, 8 duct detectors with relay.$9,800
May 17, 2013Completed
final sign-off Aug 2014
500 Sansome StCentric Construction Inc3rd floor-corridor area-demo of (e) non load bearing partitions, ceiling & lights. construction of new non load bearing partitions, ceiling, paint, carpet & lighting. 3rd fl-demo of (e) non load bearing partitions, construction of new non load bearing partitions, new carpet, paint & lighting & power$350,000
May 13, 2013Completed
final sign-off Aug 2013
500 Sansome StR L H Fire Protection Inc8th floor fire sprinkler permit - relocate 138 pendents & 14 uprights. ref pa #2013.02.14.0246$78,128
May 6, 2013Never finaled
issued May 2013, no final
500 Sansome Ststreet space
Apr 30, 2013Completed
final sign-off Jul 2014
500 Sansome StCentric Construction Inc8th floor:signage at one conference room stating max. occupant load per attached sf bldg code ab-005, local equivalency for alternative design. an automatic fire protection system is installed throughout the bldg.$500
Apr 26, 2013Completed
final sign-off Apr 2014
500 Sansome StCentric Construction Incdemolition of (e) non load bearing walls & stairs, construction of (n) wall, doors, stairs, construction of (n) concrete slab, structural support. add (n) elevator smoke door.$35,000
Apr 18, 2013Never finaled
issued Apr 2013, no final
500 Sansome Ststreet space
Apr 12, 2013Never finaled
issued Apr 2013, no final
500 Sansome StSimplexgrinnell Lp.8th floor - addioitn new (1) nac panel, 1 signal zam, 2 smoke sensors, 24 horn/strobes, 3 strobes, 2 relay base, remvoe exisitng 9 horn/strobes. t.i. #2013.02.14.0246$11,000
Mar 29, 2013Never finaled
issued Mar 2013, no final
500 Sansome Ststreet space and mta
Mar 27, 2013Completed
final sign-off Jul 2014
500 Sansome StR L H Fire Protection Incbasement level-relocate (e) ssu & ssp sprinklers. replace (e) semi-recessed to concealed heads in the t-bar & gyp board ceilings. total of 53 sprinklers$8,500
Mar 27, 2013Completed
final sign-off Jun 2014
500 Sansome StSimplexgrinnell Lp.basement & 1st floor-fire alarm alteration-2 power supplies, 12 smokes, 10 duct detectors, 2 relays, 16 horn/strobes, 14 strobes, relocate 2 (e) power supplies. relocate 9 (e) devices, remove 3 (e) devices. ti pa# 2012-1207-5743$18,000
Mar 1, 2013Completed
final sign-off Apr 2014
500 Sansome StCentric Construction Increvision to pa #201111169069 of revised detail 15/s5.1 & 11/s5.1
Feb 26, 2013Never finaled
issued Mar 2013, no final
500 Sansome StCentric Construction Incbsmt-rev.to pa #201212075743 storage b06 & 07 changed to bike storage,conf. rm b11 changed into 2 offices, corridor b28- 2 doors removed & 2 doors relocated, addition of rm b04 for bike storage & corridor b31 path of travel revised, addition of mech. sys.-maintain elevator lobbies- sp-ls sep.permit$150,000
Feb 19, 2013Completed
final sign-off Jul 2014
500 Sansome StCentric Construction Incnew mech equipment on roof, new structural platform on roof. new exhaust throughout the bldg.$700,000
Feb 14, 2013Completed
final sign-off May 2014
500 Sansome StCentric Construction Inc8th floor-interior t.i. including partitions, ceilings & finishes w/ interior courtyard "bridge" spanning 16'-0". structural drawings & calcs attached. design build mech, elect, fire protection filed under separate permit.$485,000
Jan 18, 2013Completed
final sign-off May 2013
500 Sansome StR L H Fire Protection Incfire sprinkler permit. add 1 and relocate 6 uprights in the electrical rooms on floors 3-8. ti. pa# 201208016219$3,500
Jan 16, 2013Never finaled
issued Jan 2013, no final
500 Sansome Ststreet space permit
Jan 9, 2013Completed
final sign-off Sep 2013
500 Sansome StR L H Fire Protection Incinstall a new sprinkler system in 1st floor- new electrical room, bathrooms and corridor,28 heads. install a new 4" riser and connect to (e) on the 2nd floor and existing standpipe that feeds upper flrs t.i. # 201209250608,201206253332. see pre-app letter 1-29-2012$15,000
Dec 21, 2012Completed
final sign-off Dec 2014
500 Sansome StCentric Construction Increvision to pa#2012-06-25-3332 (1st floor & basement) electrical room, exit corridor, restroom & basement elevator lobby layout changes.
Dec 7, 2012Never finaled
issued Jan 2013, no final
500 Sansome StCentric Construction Incbasement level-construction of new non load bearing partitions, doors, side lights, ceiling & soffits. new carpet, paint, lighting & power. construction of 1 ada shower room & 1 non ada shower room-sprinklers and fire alrm separate permit- new corridors and elevator doors, hvac under separate permit$850,000
Nov 26, 2012Never finaled
issued Nov 2012, no final
500 Sansome Ststreet space
Nov 26, 2012Never finaled
issued Nov 2012, no final
500 Sansome Ststreet space
Nov 14, 2012Completed
final sign-off Aug 2014
500 Sansome StR L H Fire Protection Incnew basement fire sprinkler system, with 131 heads, new piping, new fdc piping and two areas calculated. new seismic calculations-$65,500
Oct 16, 2012Completed
final sign-off Jun 2015
500 Sansome St1st thru 8th floors-new restoom exhaust throughout the building. (restrooms under seperate permits)$75,000
Sep 25, 2012Completed
final sign-off Jun 2014
500 Sansome StCentric Construction Incconsturction of new accessible bathrooms and drinking fountains at vacant first floor and mezzanine$75,000
Aug 17, 2012Never finaled
issued Aug 2012, no final
500 Sansome Ststreet space
Aug 7, 2012Never finaled
issued Aug 2012, no final
500 Sansome Ststreet space with meters
Aug 1, 2012Completed
final sign-off Jun 2015
500 Sansome StCentric Construction Incall floors: barrier removal & replacement of elevator. 3rd-8th floors: phase 2 of a 2 phase voluntary seismic strengthening. phase 1 pa# 2011/11/16/9069.$2,000,000
Jul 12, 2012Completed
final sign-off Jun 2014
500 Sansome St2nd/3rd/4th/5th/6th floors-removal of (e) bathrooms, non load bearing walls. construction of new accessible bathrooms & drinking fountains- mep, sprinklers and fire alarm separate permit$500,000
Jul 2, 2012Completed
final sign-off Jun 2014
500 Sansome StCentric Construction Inc7th floor: removal of existing bathrooms. construction of new accessible bathrooms & drinking fountains. 8th floor: removal of existing non-load bearing walls at vacant suite. removal of existing bathrooms. construction of new accessible bathrooms & drinking fountains.$300,000
Jun 25, 2012Completed
final sign-off Dec 2014
500 Sansome StCentric Construction Inc1st fl & bsmt - construction of new transformer room, new exit passageway, stairs & accessible restrooms. removal of (e) non load bearing walls, exit passageway & non complying stairs & ramps.$500,000
Jun 5, 2012Completed
final sign-off Sep 2013
500 Sansome StR L H Fire Protection Incbasement-demo (e) 8" main & re-connect to 4" from pump room$4,000
May 18, 2012Never finaled
issued May 2012, no final
500 Sansome StSimplexgrinnell Lp.all floors: demo (e) fire alarm terminal cabinet riser in the elect. room near the main elevator. relocate (e) power supply and relays to new location in the elect. room near the freight elevator.$8,000
Apr 2, 2012Expired or cancelled
withdrawn Apr 2012
500 Sansome Stbarrier removal of non ada elevator including slab demolition and walls. new concrete walls and steel beams will be constructed. phase 1 of voluntary seismic upgrade in basement, first floor, mezzanine and 2nd floor. includes shear walls and collector beams.$1,960,000
Feb 9, 2012Completed
final sign-off Oct 2012
500 Sansome StCentric Construction Incdemo of non structural interior improvements in basement per ab17$35,000
Dec 30, 2011Completed
final sign-off Jan 2012
500 Sansome StSimplex Grinnell7th floor-fire alarm system tenant improvement-4 horn/strobes, demo 2 smokes & 1 relay$5,000
Dec 27, 2011Completed
final sign-off Feb 2012
500 Sansome StR L H Fire Protection Incste #750 fire sprinkerl only: relocate 9 heads, add 3 (upright), toatl 12 heads.$6,000
Dec 21, 2011Completed
final sign-off Mar 2012
500 Sansome StInnovative Mechanical Incsuite #750-mechanical, re-route duct work, install 4 vav boxes, registers & thermostats$42,000
Dec 9, 2011Completed
final sign-off Mar 2012
500 Sansome StCentric Construction Incsuite #750-remove & replace doors at suite & restrooms, enlarge suite entry, install non load bearing partitions, doors, side lights, ceiling & soffits. new paint, lighting & power/data$276,562
Nov 16, 2011Completed
final sign-off Aug 2014
500 Sansome StCentric Construction Incvoluntary seismic strengthening in basement, 1st, mezz, and 2nd floor in accordance with ch 16 & 34 of the 2010 sfbc & elevator e02 upgrade replacement w/ new elevator & controls. also enlarge 2 hr elevator shaft. assessibility compliance exempt per sfbc ab-o17 for vacant bldg. at these floors.$500,000
Nov 10, 2011Completed
final sign-off Nov 2011
500 Sansome StSimplex Grinnellfire alarm tenant improvement on #200. new devices include one new nac extender panel, six new horn/strobe and 6 new strobes.$8,700
Nov 3, 2011Completed
final sign-off May 2012
500 Sansome StR L H Fire Protection Inc#200 - fire sprinkelr permit - relocate 33 & add 2 upgrights, relocate 1 pendent.$18,000
Oct 25, 2011Completed
final sign-off Mar 2012
500 Sansome StCentric Construction Inc2nd floor-demo non load bearinf interior office walls, install new soffits, double entry doors, carpets & paint. new electrical supply for new work stations. no changes to (e) mechanical & plumbing$75,000
Sep 21, 2011Never finaled
issued Sep 2011, no final
500 Sansome Ststreet space & mta parking meter
Aug 24, 2011Never finaled
issued Aug 2011, no final
500 Sansome StCentric Construction Incdemolition of all interior non structural improvents inthe following spaces: all tenant space on floors 1, mezzanine, floor 2, suite 325, suite 500 and suite 615 per ab 17$200,000
Nov 18, 2009Completed
final sign-off Nov 2009
500 Sansome StAnderson, Rowe & Buckley, Inc.umbrella permit - no work. compliance letter for high rise sprinkler ordinance # 377-93
Oct 9, 2009Completed
final sign-off Nov 2009
500 Sansome StR L H Fire Protection Incadd sprinklers to make it a full sprinkler bldg. base-2hd,4th-8hd, 5th-1hd, 6th-5 hd, 7th 15hd, 8th-1 hd, roof-03 hd, total 35 heads$5,000
Sep 15, 2009Completed
final sign-off Dec 2009
500 Sansome StPeacock Construction Inc3rd floor lighting, t-24, ref pa #200908124654.$3,000
Sep 14, 2009Never finaled
issued Sep 2009, no final
500 Sansome StR L H Fire Protection Inct/i upgrade to existing sprinkler system. add 212 new pendent heads and add 31 uprights to first floor and mezannine.$51,000
Aug 31, 2009Completed
final sign-off Mar 2010
500 Sansome StAyoob & Peery Plumbing Co Inc3rd fl - relocate fire sprinkler heads per tenant improvements (2-relocate). pid #200993181.$800
Aug 12, 2009Completed
final sign-off Dec 2009
500 Sansome StPeacock Construction Incremove and replace existing doors with rated doors, add soffits at elevator lobby. replace light fixtures with new, apply new finishes to lobby and corridor walls, change ceiling tiles to new- sprinklers and removal of hose rack separate permit$85,000
Jun 25, 2009Completed
final sign-off Jul 2009
500 Sansome StSimplex Grinnellinstall 5 wall mounted strobes and 4 wall mounted horn strobes on the 3rd floor.$5,000
Jun 9, 2009Completed
final sign-off Jul 2009
500 Sansome StAyoob & Peery Plumbing Co Inc3rd floor relocate & remove fire sprinkelrs per teant improvement, (7 relocate & 2 remove)$1,050
May 28, 2009Completed
final sign-off Jul 2009
500 Sansome StPeacock Construction Inc3rd floor suite 301 - demo of existing on-bearing partitions, build back non-bearing partitions to meet new office configuration. sprinkler, life safety, mech, elec under separate permit.$125,000
Jan 12, 2009Never finaled
issued Jan 2009, no final
500 Sansome StR L H Fire Protection Inc2nd floor. relocate 144 sprnklr heads from upright to pendent.$28,500
Dec 1, 2008Never finaled
issued Dec 2008, no final
500 Sansome StR L H Fire Protection Inctenant improvements. upgrade sprinkler system. add 146 pendents sprinklers to 3rd floor.$30,000
Oct 29, 2008Completed
final sign-off Nov 2008
500 Sansome StPeacock Construction Increnew pa# 2007/06/01/2773 to obtain final inspection.
Jul 9, 2008Never finaled
issued Jul 2008, no final
500 Sansome Stnon structural demo at g/f & mezzanine level partitions, demo of existing g/f restroom note, space is pending improvements and floors are no be occupied.$89,000
Jul 9, 2008Completed
final sign-off Nov 2008
500 Sansome StSimplex Grinnelltake out 2 duct detectors/revision to app 200802285881$500
Jul 3, 2008Completed
final sign-off Aug 2008
500 Sansome StDinyari Construction Inc.reroofing.$106,350
Jun 6, 2008Completed
final sign-off Jul 2008
500 Sansome StR L H Fire Protection Inc6th floor - renew 200706194374 and 200707247623 for final inspection.
Feb 28, 2008Completed
final sign-off Nov 2008
500 Sansome StSimplex Grinnellfire alarm ti to 6th floor corridor only includes addition of (3) horn strobes, (1) strobe and (2) duct detectors.$5,800
Feb 20, 2008Completed
final sign-off Nov 2008
500 Sansome StAyoob & Peery Plumbing Co Incti for sprinkler system on the 6th floor. relocate 12 heads$2,200
Dec 19, 2007Completed
final sign-off Apr 2008
500 Sansome StSimplex Grinnellrelocate (e) horn/strobes to new location. add 1 new strobe to 5th floor suite # 502 only.$2,800
Dec 18, 2007Completed
final sign-off Apr 2008
500 Sansome Strevision to pa# 2007.11.14.8068. drinking fountain was not as originally drawn. correction to reflect the current configuration with the upgrade of the vinyl flooring. works on the 5th fl.$1,000
Nov 14, 2007Completed
final sign-off Apr 2008
500 Sansome Stt/i fifth floor-create two conference rooms and open workstation space. sprinklers,mech,elect. under sep app$35,000
Nov 6, 2007Expired or cancelled
expired Jun 2009
500 Sansome StSimplex Grinnellfire alarm modification: 6th floor add 1 horn/strobe,2 strobes,2 duct det. ,relocate 2 existing strobes$8,500
Sep 24, 2007Completed
final sign-off Jul 2008
500 Sansome StAllied Heating & Air Conditioningdemolish (e) air handler on 6th fl. install (n) airhandler and connect to the (e)chilled water. install (n) steam to hot water heat exchanger. install (n) ductwork and piping, see pa# 2007.06.01.2773 for 6th fl upgrades.$145,000
Aug 10, 2007Never finaled
issued Aug 2007, no final
500 Sansome StAllied Heating & Air Conditioningisntall 13 new vav boxes new distribution ductwork and new diffusers ref ap #200706042883 work on 6th floor$42,500
Jul 24, 2007Expired or cancelled
expired Jul 2008
500 Sansome StSimplex Grinnellwork on the 6th floor, 1 smoke, 6 strobes, 5 horn strobes, 1 door holder (1 set)$7,000
Jul 17, 2007Never finaled
issued Jul 2007, no final
500 Sansome StCalifornia Roof Managementreroofing$10,000
Jun 19, 2007Expired or cancelled
expired Jul 2008
500 Sansome StR L H Fire Protection Inc6th floor-t.i. upgrade of fire sprinkelr system; relocate 9 sprinkler heads.$4,386
Jun 4, 2007Completed
final sign-off Jul 2008
500 Sansome StDfi Construction Companyoti-1, 500 sansome llc, 6th fl, el, me, ls, sp.$145,400
Jun 1, 2007Never finaled
issued Jun 2007, no final
500 Sansome Stnew hvac mech. room, upgrades to 6th floor tenant cooridor and elevator lobby including wall and ceiling finishes new lounge at property line wall. m/e to fire sprnklr filed under seperate permit. fsd seperate permit. lighting under seperate permit$120,000
Dec 11, 2006Completed
final sign-off Mar 2007
500 Sansome StCommercial Interior Builders Incoti-2 m and j wilko 2nd fl sp$6,000
Nov 30, 2006Completed
final sign-off Mar 2007
500 Sansome StCommercial Interior Builders Incoti-1 2nd fl-sp.$25,000
Feb 14, 2006Completed
final sign-off Apr 2006
500 Sansome StSimplex Grinnelladdition of 1 nac power supply, 7 smoke det., 3 duct det., 1 control mod., 1 signal mod., 16 horn / strobes, 3 strobes, 2 door holders. all work to be done on 5th floor.$7,000
Jan 19, 2006Completed
final sign-off Apr 2006
500 Sansome StDpw Inc.relocate 18 pendents for new ceiling , relocate 18 upright for new wall and add 1 new head for new improvement on 7th floor$9,000
Dec 28, 2005Completed
final sign-off Mar 2006
500 Sansome StCommercial Interior Builders Incoti-2 bsmnt sp$3,500
Dec 12, 2005Completed
final sign-off Apr 2006
500 Sansome StPrincipal Builders Inc.oti-2 7th floor el me$400,000
Nov 2, 2005Never finaled
issued Nov 2005, no final
500 Sansome StCommercial Interior Builders Incoti-3 7th floor el, me$9,000
Oct 31, 2005Completed
final sign-off Apr 2006
500 Sansome StPrincipal Builders Inc.oti-1 7/f el me ls sp$200,000
Oct 27, 2005Expired or cancelled
expired May 2006
500 Sansome StC B F Inclife safety system modifications @500 sansome street 7/f corridor & lobby. f & i 3 horn/strobes, 1 smoke decetors, 1 strobes, dual sync.modules.$2,500
Oct 26, 2005Completed
final sign-off Mar 2006
500 Sansome StCommercial Interior Builders Incoti-1 bfl el mels sp$9,926
Oct 12, 2005Never finaled
issued Oct 2005, no final
500 Sansome StCommercial Interior Builders Incoti-2 7th floor sp$31,000
Aug 22, 2005Never finaled
issued Aug 2005, no final
500 Sansome StCommercial Interior Builders Incot1-1 7th floor el, me, l/s, sp$60,229
Aug 22, 2005Completed
final sign-off Oct 2005
500 Sansome StCommercial Interior Builders Incoti-1 4th floor$5,800
Jul 13, 2005Never finaled
issued Jul 2005, no final
500 Sansome Ststreetspace
Jul 22, 2004Completed
final sign-off Feb 2005
500 Sansome StC B F Inclife safety system modification 500 sansome st floors 1-8 and bsmt, install simplex smoke det for co$18,000
Jun 25, 2004Completed
final sign-off Feb 2005
500 Sansome StCommercial Interior Builders Incoti-1 7/f el me ls sp$198,777
Apr 22, 2004Completed
final sign-off Jun 2004
500 Sansome StCommercial Interior Builders Incoti-2 4th floor, sp$2,765
Mar 25, 2004Completed
final sign-off Jun 2004
500 Sansome StCommercial Interior Builders Incoti-1 4th floor, el, l/s, me, sp$30,000
Mar 22, 2004Completed
final sign-off Jul 2004
500 Sansome StCommercial Interior Builders Incoti-2 4th fl -sp$2,670
Mar 16, 2004Expired or cancelled
withdrawn Jul 2004
500 Sansome Stoti-1, 7th floor/ el, me, ls, sp$160,300
Feb 20, 2004Expired or cancelled
expired Dec 2005
500 Sansome StCommercial Interior Builders Incoti-1 4th fl el, me, ls, sp$39,200
Feb 18, 2004Completed
final sign-off Dec 2004
500 Sansome StBcci Construction Companyfire sprinkler work on the 8th fl$12,000
Feb 12, 2004Completed
final sign-off Dec 2004
500 Sansome StBcci Construction Companyupgrade restroom & breakroom for accessability -provide new finishes @ reception & counter in servi$100,000
Jan 13, 2004Expired or cancelled
expired Dec 2005
500 Sansome StC B F Incremew fpr foma; 3rd 9114921 8th and 9120319 - 8th 9200053 8th
Jan 13, 2004Completed
final sign-off Jun 2004
500 Sansome StC B F Increnew for final 9716832, 9716833, 4th floors & 9405916- 3rd floor
Jan 12, 2004Expired or cancelled
expired Dec 2005
500 Sansome StC B F Increnew for final inspection : 9313146-3rd fl, 9314883- 3rd fl, & 9404844- 3rd floor.
Jan 12, 2004Completed
final sign-off Apr 2004
500 Sansome StC B F Increnew for final 8204920, 8413172, 9133145 (3rd flr)
Jul 29, 2003Expired or cancelled
expired Dec 2005
500 Sansome StCommercial Interior Builders Incoti-1 rev. #1 6th floor, ls, sp$1,843
Jul 15, 2003Expired or cancelled
expired Dec 2005
500 Sansome StCommercial Interior Builders Incoti-2 6th flfoor l/s$5,000
Jul 11, 2003Completed
final sign-off Sep 2003
500 Sansome StPotter Fire Protectioninstall 22 fire sprinkler from existing main & grand lines. remove 3/4" pipe and replace w/ 1".$4,750
Jun 23, 2003Expired or cancelled
expired Dec 2005
500 Sansome StCommercial Interior Builders Incoti-1 6th floor, ls, sp$25,000
May 21, 2003Completed
final sign-off Jul 2003
500 Sansome StCommercial Interior Builders Incoti-3 4/f sp$15,000
May 19, 2003Completed
final sign-off Jul 2003
500 Sansome StCommercial Interior Builders Incoti-2 4th fl-ls$4,000
May 8, 2003Completed
final sign-off Sep 2003
500 Sansome Stinfill of existing windows with 3 hour rated walls from interior side only. 5th, 6th, 7th, and 8th$30,000
May 8, 2003Completed
final sign-off Jul 2003
500 Sansome StCommercial Interior Builders Incoti-1 4th floor el,,l/s, sp$90,000
Feb 21, 2003Completed
final sign-off Feb 2003
500 Sansome StC B F Incto renew app#2002/09/23/7185,9714286,9714289 for final inspection.
Jan 21, 2003Completed
final sign-off Mar 2003
500 Sansome StCommercial Interior Builders Incoti-2 5th floor, ls$3,500
Jan 17, 2003Completed
final sign-off Mar 2003
500 Sansome StCommercial Interior Builders Incoti-3 5th floor el ls #502$5,000
Jan 13, 2003Completed
final sign-off Mar 2003
500 Sansome StCommercial Interior Builders Incoti-2, 5th floor, sp$950
Dec 23, 2002Completed
final sign-off Mar 2003
500 Sansome StCommercial Interior Builders Incoti-1, 5th floor, ste 502, el, ls$20,000
Dec 23, 2002Completed
final sign-off Mar 2003
500 Sansome StCommercial Interior Builders Incoti-1, 5th floor, ste 501, el, ls$20,000
Sep 23, 2002Completed
final sign-off Nov 2002
500 Sansome StC B F Increnew permits 9802854 for final inspection.$5,000
Sep 23, 2002Expired or cancelled
expired Jun 2003
500 Sansome StC B F Increnew permits 9714286 & 9714289 for final inspection.$5,000