13 permits since 2000 (architect on 13 permits): 10 completed, 1 in progress, 1 never finaled, 1 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jul 1, 2026 | Completed final sign-off Aug 2026 | 478 Post St | T P Windows Inc/United Glass & Aluminum | remove 5-foot section of hollow, clay tile wall between two tenant spaces each with their own exits so as to create a common opening. refer to p/a 2026-0206-5495.Details
remove 5-foot section of hollow, clay tile wall between two tenant spaces each with their own exits so as to create a common opening. refer to p/a 2026-0206-5495. | $12,500 |
| May 21, 2026 | In progress filed May 2026, not yet issued | 1111 Gough St | remodel of (3) existing restrooms.Details
remodel of (3) existing restrooms. | $1,500,000 | |
| Nov 14, 2025 | Completed final sign-off Jul 2026 | 2350 Turk Bl | Cahill Contractors Llc. | ref 202503041492 and 202510248069 to install production rigging equipment at usf theaterDetails
ref 202503041492 and 202510248069 to install production rigging equipment at usf theater | $200,000 |
| Apr 11, 2025 | Completed final sign-off Jul 2026 | 2350 Turk Bl | Cahill Contractors Llc. | renovation of (e) theater includng installation of new cat- walk over (e) stageDetails
renovation of (e) theater includng installation of new cat- walk over (e) stage | $950,000 |
| Nov 4, 2024 | Completed final sign-off Aug 2025 | 1111 Gough St | Field Construction Inc. | ti to include interior barrier removal and code upgrades including (n) lift platform, stair hand and guardrails.Details
ti to include interior barrier removal and code upgrades including (n) lift platform, stair hand and guardrails. | $170,000 |
| Apr 21, 2023 | Expired or cancelled cancelled Jan 2026 | 2555 17th Av | priest's bldg: replacement in-kind approx 53 windows units to match extg rehab units, all windows to rear & side elevations.Details
priest's bldg: replacement in-kind approx 53 windows units to match extg rehab units, all windows to rear & side elevations. | $100,000 | |
| Mar 20, 2023 | Completed final sign-off Feb 2024 | 2350 Turk Bl | Skyline Construction | theater/school of education building: life safety & accessibility upgrades. including new platform lift & exit doors.Details
theater/school of education building: life safety & accessibility upgrades. including new platform lift & exit doors. | $73,000 |
| Sep 30, 2022 | Never finaled issued Oct 2022, no final | 1 Steuart Ln | Black Mountain Development | unit #2001: demo of non-structural partitions, new interior lighting, new interior partitions, installation of new finishes, plumbing fixtures, and new cabinetry. no structural work.Details
unit #2001: demo of non-structural partitions, new interior lighting, new interior partitions, installation of new finishes, plumbing fixtures, and new cabinetry. no structural work. | $80,000 |
| Mar 21, 2022 | Completed final sign-off Mar 2024 | 940 Laguna Honda Bl | voluntary structural seismic upgrade. accessibility code upgradesDetails
voluntary structural seismic upgrade. accessibility code upgrades | $2,000,000 | |
| Oct 25, 2021 | Completed final sign-off Feb 2025 | 330 Parker Av | Malcolm International Llc | voluntary structural remedial work to private elevated roadway/via duct in-kind. all work to be performed out doorsDetails
voluntary structural remedial work to private elevated roadway/via duct in-kind. all work to be performed out doors | $3,000,000 |
| May 21, 2021 | Completed final sign-off Nov 2025 | 2335 Golden Gate Av | Cahill Contractors Llc. | construct (n) approx 15,600 sf addition, 45-ft basketball practice facility on the usf lower campus. 1 full basketball court, 2 partial shooting/drills courts, coaches' offices, conf rms, restrms, & storage room.Details
construct (n) approx 15,600 sf addition, 45-ft basketball practice facility on the usf lower campus. 1 full basketball court, 2 partial shooting/drills courts, coaches' offices, conf rms, restrms, & storage room. | $15,000,000 |
| Apr 23, 2021 | Completed final sign-off Apr 2023 | 201 Folsom St | Aaron Gordon Construction Inc | unit 38d: interior renovation. new interior lighting. new cabinets, no structural work. no change of use.Details
unit 38d: interior renovation. new interior lighting. new cabinets, no structural work. no change of use. | $20,000 |
| Jul 16, 2020 | Completed final sign-off Jul 2023 | 50 Thomas More Wy | installation of a new platform lift system assocated with accessibility path of travel upgrdaes deferred under structural seismic upgrade pa201905079955, other works include installation of new casework.Details
installation of a new platform lift system assocated with accessibility path of travel upgrdaes deferred under structural seismic upgrade pa201905079955, other works include installation of new casework. | $150,000 |