- Dec 2004 to Aug 2024
19 permits since 2000 (architect on 19 permits): 12 completed, 2 in progress, 1 never finaled, 4 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Aug 20, 2024 | In progress filed Aug 2024, not yet issued | 645 Chestnut St | to comply with abe ord 51-16 abe 201912109598 replace threshold w/new max 1/2" high; new sidewalk less than 1/2" lower than floor, provide door lever: provide power door operator to keep existing pair of 30" doors (11b-404.3.1: doorways shall provideDetails
to comply with abe ord 51-16 abe 201912109598 replace threshold w/new max 1/2" high; new sidewalk less than 1/2" lower than floor, provide door lever: provide power door operator to keep existing pair of 30" doors (11b-404.3.1: doorways shall provide | $11,225 | |
| Apr 26, 2024 | In progress filed Apr 2024, not yet issued | 2448 San Bruno Av | abe# 201812283582- response to entrance and accessibility parking upgrades (new accessible van parking) new retaining wall 42"high above accessible van parking space, etc. new pour in place bollards (n) power door operator to serve main entry door to (e) laundromat. actuator paddles inside & outsideDetails
abe# 201812283582- response to entrance and accessibility parking upgrades (new accessible van parking) new retaining wall 42"high above accessible van parking space, etc. new pour in place bollards (n) power door operator to serve main entry door to (e) laundromat. actuator paddles inside & outside | $46,860 | |
| Aug 22, 2023 | Expired or cancelled withdrawn May 2026 | 4083 24th St | abe 201908125993. make modifications to provide an accessible business entrance per ordinance 51-16. provide new curb and concrete sidewalk that aligens with building entry.Details
abe 201908125993. make modifications to provide an accessible business entrance per ordinance 51-16. provide new curb and concrete sidewalk that aligens with building entry. | $6,000 | |
| Jul 18, 2023 | Completed final sign-off Dec 2023 | 1201 Ortega St | Build Group Inc. | scope includes removal of moisture damaged (e) floor slab on grade to edge of walls in 2 rooms (class #117 & multi purpose room #129) on the 1st fl; installation of (n) concrete slab over 15-mil x-treeme wood below slab vapor barrier membrane. provide polished concrete finish in both roomsDetails
scope includes removal of moisture damaged (e) floor slab on grade to edge of walls in 2 rooms (class #117 & multi purpose room #129) on the 1st fl; installation of (n) concrete slab over 15-mil x-treeme wood below slab vapor barrier membrane. provide polished concrete finish in both rooms | $63,000 |
| Dec 14, 2022 | Never finaled filed Dec 2022, never issued | 2444 San Bruno Av | project is solely for accessibility upgrades per ord 51-16. within an (e) exterior door frame a new accessible door & entrance will be built, with some minor changes to interior walls & moving 4 dryers. a new accessible van parking space will be built within the (e) parking lot. abe #201812283582.Details
project is solely for accessibility upgrades per ord 51-16. within an (e) exterior door frame a new accessible door & entrance will be built, with some minor changes to interior walls & moving 4 dryers. a new accessible van parking space will be built within the (e) parking lot. abe #201812283582. | $507,980 | |
| Jul 15, 2022 | Expired or cancelled cancelled Feb 2025 | 274 Brannan St | Mc Millan Electric | basement and gr floors, structural reinforcement for 2 openings at basement level, gr level. structural reiforcemnt at existing slab for future conduit runsDetails
basement and gr floors, structural reinforcement for 2 openings at basement level, gr level. structural reiforcemnt at existing slab for future conduit runs | $20,000 |
| Feb 11, 2020 | Completed final sign-off Mar 2021 | 1930 Fillmore St | Occidental Express | to comply with abe ord 51-16 install power door openerDetails
to comply with abe ord 51-16 install power door opener | $6,000 |
| Oct 16, 2019 | Completed final sign-off Jul 2021 | 2115 Irving St | to comply with accessible business entrance program per ordinance 51-16.business entrancesDetails
to comply with accessible business entrance program per ordinance 51-16.business entrances | $2,500 | |
| Sep 13, 2019 | Completed final sign-off Aug 2020 | 3250 Geary Bl | Bai Construction | provide accessible toilet roomDetails
provide accessible toilet room | $31,684 |
| Aug 30, 2019 | Completed final sign-off Aug 2020 | 3250 Geary Bl | Bai Construction | accessibility upgrades only. including compliance with abe ord. 51-61 andDetails
accessibility upgrades only. including compliance with abe ord. 51-61 and | $7,856 |
| Aug 30, 2019 | Expired or cancelled cancelled Jan 2026 | 799 Valencia St | barier removal only in compliance with ordinance #51-16 at commercial tenant space. 791 and 799 valencia stDetails
barier removal only in compliance with ordinance #51-16 at commercial tenant space. 791 and 799 valencia st | $8,000 | |
| Apr 9, 2019 | Completed final sign-off Dec 2019 | 1331 Harrison St | Sgdm Llc | change of use from garment shop to "e" occupancy day care under 30 children.Details
change of use from garment shop to "e" occupancy day care under 30 children. | $130,000 |
| May 3, 2017 | Completed final sign-off Aug 2017 | 1 Embarcadero Center | Swinerton Builders | tenant improvement retail space lobby lvel 2310 sf no facade work, no ext modifications includes new kitchenette, new toilet rm maher not reqDetails
tenant improvement retail space lobby lvel 2310 sf no facade work, no ext modifications includes new kitchenette, new toilet rm maher not req | $230,000 |
| Jun 12, 2009 | Completed final sign-off Oct 2009 | 437 Sutter St | General Contracting Services Inc. | a minor remodel of existing store room. located on the 2nd. floor. (e) restroom will remain. the remaining space will be divided w/ (n) wall configuration to divide a (n) stock area from the main space. (if needed electrical or hvac will be on a separate permit).Details
a minor remodel of existing store room. located on the 2nd. floor. (e) restroom will remain. the remaining space will be divided w/ (n) wall configuration to divide a (n) stock area from the main space. (if needed electrical or hvac will be on a separate permit). | $45,000 |
| Jun 8, 2006 | Completed final sign-off Feb 2007 | 1400 Geary Bl | level b, demo all drop ceiling (a-o2) new ceiling throughout new computer room ceiling suspended form steel joists(structural calcs)Details
level b, demo all drop ceiling (a-o2) new ceiling throughout new computer room ceiling suspended form steel joists(structural calcs) | $101,250 | |
| May 5, 2006 | Completed final sign-off Sep 2007 | 953 De Haro St | Spacesaver Designs Inc. | replace 35 street facing windows sashes with replica. 30 non-street facing exterior and interior window sashes replaced with fiberglass sash & frame. replace 1 steel door & 1 wood french door. replace hardware for 6 doors.paint/patch windows & doors. non street facing replacement windows.Details
replace 35 street facing windows sashes with replica. 30 non-street facing exterior and interior window sashes replaced with fiberglass sash & frame. replace 1 steel door & 1 wood french door. replace hardware for 6 doors.paint/patch windows & doors. non street facing replacement windows. | $96,000 |
| Mar 21, 2005 | Expired or cancelled expired Feb 2007 | 1400 Geary Bl | furr out walls, new soffits w/cove hights, gilded barrel vault ceiling in elevator lobby.Details
furr out walls, new soffits w/cove hights, gilded barrel vault ceiling in elevator lobby. | $101,250 | |
| Dec 6, 2004 | Completed final sign-off May 2005 | 1700 California St | oti-1, 2nd floor, el, me, sp.Details
oti-1, 2nd floor, el, me, sp. | $30,000 | |
| Dec 6, 2004 | Completed final sign-off May 2005 | 1700 California St | oti-2, 2nd floor, el, me.Details
oti-2, 2nd floor, el, me. | $20,000 |