62 permits since 2000 (architect on 59 permits, designer on 3 permits, authorized agent-others on 2 permits): 38 completed, 3 in progress, 13 never finaled, 8 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Aug 20, 2025 | In progress filed Aug 2025, not yet issued | 2500 Pacific Av | voluntary structural strenghthening of (e) building foundation, including new hand dug piers and grade beams.Details
voluntary structural strenghthening of (e) building foundation, including new hand dug piers and grade beams. | $100,000 | |
| Sep 16, 2024 | In progress issued Feb 2025 | 330 Linden St | Axelson Builders Inc | installation of (n) storefront opening entry & egress doors on linden st side of 425-427 hayes st throughout building. (n) interior ramp to provide ada compliance structural scope includes storefront opening interior steps. (n) slab on grade & columns. existing sam flores mural on linden stDetails
installation of (n) storefront opening entry & egress doors on linden st side of 425-427 hayes st throughout building. (n) interior ramp to provide ada compliance structural scope includes storefront opening interior steps. (n) slab on grade & columns. existing sam flores mural on linden st | $400,000 |
| Aug 6, 2024 | Completed final sign-off Sep 2026 | 418 Larkin St | One Hat One Hand Llc | replacement of exterior mounted security gates with new gates. no interior work. all work on exterior of restaurants. no work related to residential use.Details
replacement of exterior mounted security gates with new gates. no interior work. all work on exterior of restaurants. no work related to residential use. | $60,000 |
| Jan 26, 2024 | Completed final sign-off Sep 2024 | 166 Eddy St | Axelson Builders Inc | renovation of storefront for accessible entrance and renovation of entry areaDetails
renovation of storefront for accessible entrance and renovation of entry area | $87,600 |
| Oct 17, 2023 | In progress issued Jan 2024 | 425 Hayes St | Axelson Builders Inc | upgrade (e) unisex restroom to be accessible. add sanitorial closet w/mop sink.Details
upgrade (e) unisex restroom to be accessible. add sanitorial closet w/mop sink. | $22,500 |
| Sep 5, 2023 | Never finaled filed Sep 2023, never issued | 432 Octavia St | 1-ground electric single face community bulletin board.Details
1-ground electric single face community bulletin board. | $3,500 | |
| Sep 28, 2021 | Never finaled filed Sep 2021, never issued | 432 Octavia St | to erect a type v-b, 2-story, mixed retail, storage and community events building. w/o basement.Details
to erect a type v-b, 2-story, mixed retail, storage and community events building. w/o basement. | $80,000 | |
| Dec 20, 2019 | Expired or cancelled cancelled Jan 2026 | 1125 Mariposa St | existing building contains a coffee roastery & coffee bar, roasting operations are to continue & coffee bar will be expanded to include new seating & new training lab for employees & wholesale clientele, coffee bar training lab will include (n) cabinets, counters and equipt, ele & plumbing work onlyDetails
existing building contains a coffee roastery & coffee bar, roasting operations are to continue & coffee bar will be expanded to include new seating & new training lab for employees & wholesale clientele, coffee bar training lab will include (n) cabinets, counters and equipt, ele & plumbing work only | $147,000 | |
| Jul 3, 2018 | Completed final sign-off Nov 2019 | 538 28th St | Pete Moffat Construction Inc | interior remodel, inc kichen. all interior finishes. no exterior structural or mechanical work. sprinkler work on separate permit.Details
interior remodel, inc kichen. all interior finishes. no exterior structural or mechanical work. sprinkler work on separate permit. | $1,000,000 |
| Feb 8, 2018 | Completed final sign-off Jun 2019 | 688 Mission St | Cookline Construction Inc | construction of a bona-fide restaurant in the location of an (e) restaruant, replacing (e) door, re-orientation of (e) glazing.Details
construction of a bona-fide restaurant in the location of an (e) restaruant, replacing (e) door, re-orientation of (e) glazing. | $180,000 |
| Aug 8, 2016 | Never finaled issued Aug 2016, no final | 1111 08th St | construction of gates, fence and striping for parking area.Details
construction of gates, fence and striping for parking area. | $20,000 | |
| Jul 29, 2016 | Never finaled issued Jul 2016, no final | 1111 08th St | alter site to original pa#: 2014/07/31/2724-s. addition of accessary off street parking area & altered container layout.Details
alter site to original pa#: 2014/07/31/2724-s. addition of accessary off street parking area & altered container layout. | $5,000 | |
| May 25, 2016 | Never finaled issued Sep 2016, no final | 1000 Evans Av | Erm-West, Inc. | remediation grading/excavaion/backfill & shoreline restoration. installation of park features including electrial & plumbing.Details
remediation grading/excavaion/backfill & shoreline restoration. installation of park features including electrial & plumbing. | $7,000,000 |
| Oct 27, 2015 | Completed final sign-off Nov 2015 | 2665 Mission St | change of occupancy from a-1 to a-2 per fire department request, ref. 201406259448. no change to (e) exits, no occupant load change.Details
change of occupancy from a-1 to a-2 per fire department request, ref. 201406259448. no change to (e) exits, no occupant load change. | ||
| Nov 4, 2014 | Completed final sign-off May 2016 | 1300 Haight St | Bradford Construction | change of use from laundry to coffee shop/cafe-no cooking. (e) cabinets / counters to be demo, new flooring, fixtures, lighting, counters, seating,(2) ada restrooms, storage, plumbing. replace windows in (e) openings.Details
change of use from laundry to coffee shop/cafe-no cooking. (e) cabinets / counters to be demo, new flooring, fixtures, lighting, counters, seating,(2) ada restrooms, storage, plumbing. replace windows in (e) openings. | $150,000 |
| Aug 29, 2014 | Completed final sign-off Apr 2015 | 1111 08th St | installation of exterior debris chuteDetails
installation of exterior debris chute | $6,000 | |
| Aug 11, 2014 | Expired or cancelled withdrawn Feb 2016 | 1111 08th St | minor demo non load bearing interior; demo/fix wall scarsDetails
minor demo non load bearing interior; demo/fix wall scars | $4,500 | |
| Aug 4, 2014 | Expired or cancelled cancelled Jan 2020 | 432 Octavia St | intensification of exterior community space to include: movie screening, personal service (outdoor exercise classes), accessory limited live performances, community meetings, farmers markets, lectures, holiday craft fairs.Details
intensification of exterior community space to include: movie screening, personal service (outdoor exercise classes), accessory limited live performances, community meetings, farmers markets, lectures, holiday craft fairs. | ||
| Jul 25, 2014 | Completed final sign-off Apr 2015 | 1111 08th St | addition of new exterior lights with light stanshings and perimeter electrical site work.Details
addition of new exterior lights with light stanshings and perimeter electrical site work. | $45,000 | |
| May 28, 2014 | Expired or cancelled cancelled Jan 2026 | 1140 07th St | revision to 201403191137 add a0.2 accessible path of travelDetails
revision to 201403191137 add a0.2 accessible path of travel | ||
| May 28, 2014 | Never finaled issued Jun 2014, no final | 1111 08th St | new egresss doors in existing storefront glass. accessible rame and stair to meet grade. new exterior doors with stair to meet gradeDetails
new egresss doors in existing storefront glass. accessible rame and stair to meet grade. new exterior doors with stair to meet grade | $42,000 | |
| Apr 15, 2014 | Completed final sign-off Oct 2014 | 145 Delmar St | Altmann & Associates, Inc | at grade, single story horizontal addition of living space to rear of house.Details
at grade, single story horizontal addition of living space to rear of house. | $20,000 |
| Jan 24, 2014 | Completed final sign-off Oct 2014 | 145 Delmar St | Altmann & Associates, Inc | excavation of crawlspace and renovation of basement to add new bathroom, laundry room, bedroom, multipurpose room and deck.Details
excavation of crawlspace and renovation of basement to add new bathroom, laundry room, bedroom, multipurpose room and deck. | $90,000 |
| Dec 20, 2013 | Completed final sign-off Mar 2014 | 409 Bryant St | D.P. Stearns | revision to appl #2013.09.20.7409 - scope includes new lighting & sheetrock at property line walls in the area of remodel.Details
revision to appl #2013.09.20.7409 - scope includes new lighting & sheetrock at property line walls in the area of remodel. | $7,000 |
| Aug 28, 2013 | Expired or cancelled cancelled Jan 2020 | 3417 18th St | change of use from m to b (restaurant) in reference to pa #2012.10.31.3197.Details
change of use from m to b (restaurant) in reference to pa #2012.10.31.3197. | ||
| Aug 27, 2013 | Never finaled issued Sep 2013, no final | 3417 18th St | Insight Construction Partners Inc | revision to app#201307252801. permit for mechanical ventilation of ada bathroom approved under seperate permit.Details
revision to app#201307252801. permit for mechanical ventilation of ada bathroom approved under seperate permit. | $200 |
| Aug 16, 2013 | Completed final sign-off Oct 2014 | 145 Delmar St | Altmann & Associates, Inc | application of local equivolency for 2 second floor property line fire rated windows per ab-009Details
application of local equivolency for 2 second floor property line fire rated windows per ab-009 | $5,000 |
| Jul 17, 2013 | Completed final sign-off Oct 2014 | 145 Delmar St | Altmann & Associates, Inc | interior residential remodel of 2 doors + structural upgrades new winodws _ doors @ rear yard facade. one new bathroom on second floor. new stair between basement & main level. mep work.Details
interior residential remodel of 2 doors + structural upgrades new winodws _ doors @ rear yard facade. one new bathroom on second floor. new stair between basement & main level. mep work. | $475,000 |
| Jun 27, 2013 | Expired or cancelled cancelled Feb 2020 | 101 Hyde St | erect (n) 8-story multi-residential & retail building.Details
erect (n) 8-story multi-residential & retail building. | $17,000,000 | |
| Jan 30, 2013 | Completed final sign-off May 2013 | 264 Clipper St | Insight Construction Partners Inc | new internal stair connection from upper unit to garage vestibule.Details
new internal stair connection from upper unit to garage vestibule. | $10,000 |
| Nov 14, 2012 | Completed final sign-off Jul 2013 | 215 Leidesdorff St | Wci-Gc Inc | construction of non bearing partition walls and hard lid ceilings. new lighting, title 24 calcs includedDetails
construction of non bearing partition walls and hard lid ceilings. new lighting, title 24 calcs included | $50,000 |
| Nov 14, 2012 | Completed final sign-off Oct 2013 | 3929 26th St | A L Martin Construction | bathroom, kitchen & laundry room interior remodel-structural modifications including the removal of a interior wall, the replacemnet of windows & the addition of a door at the back (garden elevation) of the houseDetails
bathroom, kitchen & laundry room interior remodel-structural modifications including the removal of a interior wall, the replacemnet of windows & the addition of a door at the back (garden elevation) of the house | $50,000 |
| Nov 8, 2012 | Completed final sign-off Jul 2013 | 560 Sacramento St | Wci-Gc Inc | construction of non bearing paritions walls and hard lid ceilings in 600 sf of existing office space. new lighting. reconfigured kitchen. upgrade restroom to ada compliance.Details
construction of non bearing paritions walls and hard lid ceilings in 600 sf of existing office space. new lighting. reconfigured kitchen. upgrade restroom to ada compliance. | $100,000 |
| Oct 31, 2012 | Completed final sign-off Sep 2013 | 3417 18th St | Insight Construction Partners Inc | installation of (n) exterior garage door , (n) cabinetry, lighting, electrical, & plumbing associated with proposed use as coffee shop. sprinkelr work if required under separate permit.Details
installation of (n) exterior garage door , (n) cabinetry, lighting, electrical, & plumbing associated with proposed use as coffee shop. sprinkelr work if required under separate permit. | $40,000 |
| Jul 5, 2012 | Completed final sign-off Feb 2013 | 489 Hayes St | to erect 3 story retail and storage building.Details
to erect 3 story retail and storage building. | $200,000 | |
| Feb 16, 2012 | Completed final sign-off Sep 2012 | 1125 Mariposa St | Alsterlind Construction Inc. | revision to appl #2010.06.03.3738 - reduction of scope. construction of ada compliant restroom. new plumbing fixtures & coffee roaster. construction of pony wall for plumbing & stair from loading dock.Details
revision to appl #2010.06.03.3738 - reduction of scope. construction of ada compliant restroom. new plumbing fixtures & coffee roaster. construction of pony wall for plumbing & stair from loading dock. | $95,000 |
| Mar 14, 2011 | Completed final sign-off Sep 2011 | 548 Shotwell St | Steve Dudum Construction | new full bathroom (shower, sink & toilet) with lighting on the 1st floor.Details
new full bathroom (shower, sink & toilet) with lighting on the 1st floor. | $4,500 |
| Feb 24, 2011 | Completed final sign-off Jun 2011 | 74 Langton St | S J L Construction*** Pls See 959755**** | office ti on the 1st and 2nd floor. new accessible entry, new accessible bathroom and shower, relocation of partition walls and lighting changesDetails
office ti on the 1st and 2nd floor. new accessible entry, new accessible bathroom and shower, relocation of partition walls and lighting changes | $120,000 |
| Dec 22, 2010 | Completed final sign-off Sep 2011 | 548 Shotwell St | new radiant heating & domestic hot water, partial kitchen remodel, master bath remodel, some lighting changes.Details
new radiant heating & domestic hot water, partial kitchen remodel, master bath remodel, some lighting changes. | $125,000 | |
| Dec 22, 2010 | Completed final sign-off Jun 2011 | 74 Langton St | S J L Construction*** Pls See 959755**** | remove kit cabs & counters, carpet & linoleum & wood floor (finished wood), one set doors, remove built-in entry desk, sheetrock from exposed beams (per ab-017).Details
remove kit cabs & counters, carpet & linoleum & wood floor (finished wood), one set doors, remove built-in entry desk, sheetrock from exposed beams (per ab-017). | $10,000 |
| Oct 27, 2010 | Completed final sign-off May 2012 | 321 12th Av | Insight Construction Partners Inc | horizontal rear yard addition on all levels.Details
horizontal rear yard addition on all levels. | $250,000 |
| Sep 9, 2010 | Completed final sign-off May 2011 | 557 Valencia St | Alsterlind Construction Inc. | new restaurant ti: demo office and wait station. reconfigure bar to accomodate larger area of stool seating. reconstruction of facade to accomodate relocated entry. kitchen prep and dishroom area reconfiguration. lighting changes. interior finish updatesDetails
new restaurant ti: demo office and wait station. reconfigure bar to accomodate larger area of stool seating. reconstruction of facade to accomodate relocated entry. kitchen prep and dishroom area reconfiguration. lighting changes. interior finish updates | $275,000 |
| Aug 27, 2010 | Never finaled filed Aug 2010, never issued | 404 Octavia St | Details
| $24,195 | |
| Aug 27, 2010 | Completed final sign-off Oct 2011 | 404 Octavia St | S J L Construction*** Pls See 959755**** | to erect 1 story, storage for full service restaurant.Details
to erect 1 story, storage for full service restaurant. | $24,195 |
| Aug 27, 2010 | Completed final sign-off Oct 2011 | 428 Octavia St | S J L Construction*** Pls See 959755**** | to erect 1 story, dishwash, storage for full service restaurant.Details
to erect 1 story, dishwash, storage for full service restaurant. | $44,800 |
| Aug 27, 2010 | Completed final sign-off Oct 2011 | 370 Linden St | S J L Construction*** Pls See 959755**** | to erect 2 stories, storage for full service restaurant.Details
to erect 2 stories, storage for full service restaurant. | $108,432 |
| Jul 8, 2010 | Expired or cancelled cancelled Mar 2020 | 1125 Mariposa St | cosntruction of casework coffeebar. electrical + plumbing work to service coffebar equipment. construction of 42" h. barrier to separate cafe space from coffee roasting facilities.Details
cosntruction of casework coffeebar. electrical + plumbing work to service coffebar equipment. construction of 42" h. barrier to separate cafe space from coffee roasting facilities. | $25,000 | |
| Jun 23, 2010 | Completed final sign-off Jun 2011 | 432 Octavia St | S J L Construction*** Pls See 959755**** | to erect 1 story, restaurant building.Details
to erect 1 story, restaurant building. | $100,000 |
| Jun 23, 2010 | Completed final sign-off Oct 2011 | 424 Octavia St | S J L Construction*** Pls See 959755**** | to erect 1 story restaurantDetails
to erect 1 story restaurant | $75,000 |
| Aug 17, 2009 | Never finaled issued Aug 2009, no final | 215 Leidesdorff St | Wci-Gc Inc | reconfiguration of entry to provide accessible means of access to 1st floor. structural work to accommodate revised entry; reconfiguration of (e) restrooms to meet accessibility requirements.Details
reconfiguration of entry to provide accessible means of access to 1st floor. structural work to accommodate revised entry; reconfiguration of (e) restrooms to meet accessibility requirements. | $50,000 |
| Apr 10, 2009 | Completed final sign-off Jul 2009 | 1539 Treat Av | revision to pa #200708149672s1, reduce scope work, no roof over deck, and change size of post, change run of stairs.Details
revision to pa #200708149672s1, reduce scope work, no roof over deck, and change size of post, change run of stairs. | ||
| Oct 1, 2008 | Never finaled issued Jun 2019, no final | 300 Octavia St | Impact Builders Llc | to erect 5 stories, no basement, type iii-a / i-a, 12 units multi-family residential over ground level retail. (r-2,m)Details
to erect 5 stories, no basement, type iii-a / i-a, 12 units multi-family residential over ground level retail. (r-2,m) | $3,250,000 |
| Oct 1, 2008 | Never finaled issued Jun 2019, no final | 350 Octavia St | Impact Builders Llc | to erect 12 dwelling units with 5 stories new bldg(condo and retail)Details
to erect 12 dwelling units with 5 stories new bldg(condo and retail) | $3,250,000 |
| Sep 18, 2008 | Completed final sign-off Nov 2008 | 2406 California St | Alsterlind Construction Inc. | revision to application 2008/02/15/4893, per plans. replace awning & add heat lamps.Details
revision to application 2008/02/15/4893, per plans. replace awning & add heat lamps. | $2,670 |
| May 1, 2008 | Completed final sign-off Nov 2008 | 2406 California St | demolition of wait station. renovation of kitchen area to accomodate stool seating, lighting changes. eschange of (e) hood for new hood. hvac system rebalance. (n) dropped ceiling over portion of dinning.Details
demolition of wait station. renovation of kitchen area to accomodate stool seating, lighting changes. eschange of (e) hood for new hood. hvac system rebalance. (n) dropped ceiling over portion of dinning. | $200,000 | |
| Sep 21, 2007 | Expired or cancelled expired Jun 2010 | 1666 Market St | to install a sign attached to the buildingDetails
to install a sign attached to the building | $2,500 | |
| Aug 22, 2007 | Completed final sign-off Aug 2008 | 3941 Washington St | Matarozzi/Pelsinger Builders Inc. | structural revision to existing permit 2007-0123-2283, restructure of e framing due to discovered conditions. foundation footing use existing,discovered brace frame at nort side of basementDetails
structural revision to existing permit 2007-0123-2283, restructure of e framing due to discovered conditions. foundation footing use existing,discovered brace frame at nort side of basement | $5,000 |
| Jan 23, 2007 | Completed final sign-off Aug 2008 | 3941 Washington St | horizontal addition - 50 sq ft addition @ 2nd level (sideyard). interior renovation w/ structural upgrades.Details
horizontal addition - 50 sq ft addition @ 2nd level (sideyard). interior renovation w/ structural upgrades. | $1,000,000 | |
| Nov 20, 2006 | Never finaled issued Nov 2006, no final | 421 Tehama St | Matarozzi/Pelsinger Builders Inc. | revision to pa# 200604138936-building inspector required add guardrails around (e) rooftop skylights, inspector asked for permit addendum for rooftop cycline security fence.Details
revision to pa# 200604138936-building inspector required add guardrails around (e) rooftop skylights, inspector asked for permit addendum for rooftop cycline security fence. | $3,000 |
| Apr 26, 2005 | Never finaled issued Jun 2005, no final | 3611 18th St | rev. appl#2004/01/12/3780 change from type ii to type i hood (mech.only)Details
rev. appl#2004/01/12/3780 change from type ii to type i hood (mech.only) | $7,000 | |
| Mar 17, 2005 | Completed final sign-off Jul 2005 | 650 Delancey St | in fill flooring at (e) interior light well. work will result in 43 sq. ft addition floor space.Details
in fill flooring at (e) interior light well. work will result in 43 sq. ft addition floor space. | $15,000 | |
| Apr 1, 2003 | Completed final sign-off Jun 2004 | 2901 Pierce St | window replacement, demo (e)exterior main entry stair+construct (n) street level entry w/(n)interiorDetails
window replacement, demo (e)exterior main entry stair+construct (n) street level entry w/(n)interior | $275,000 |