45 permits since 2000 (architect on 41 permits, authorized agent-others on 2 permits, engineer on 2 permits): 36 completed, 4 never finaled, 5 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Nov 20, 2018 | Completed final sign-off May 2021 | 181 Fremont St | Level 10 Construction Lp | level 4 to 6 new grease exhaust system. revision to level 4, 201712065692. grease interceptor room to accept duct from level 6 new grease duct exhaust screens on level 4. new air intake louvers on level 6. grease duct shaft under 201808298664, 201808298666, mech under 201811075285, 201811075286Details
level 4 to 6 new grease exhaust system. revision to level 4, 201712065692. grease interceptor room to accept duct from level 6 new grease duct exhaust screens on level 4. new air intake louvers on level 6. grease duct shaft under 201808298664, 201808298666, mech under 201811075285, 201811075286 | $20,000 |
| Oct 29, 2018 | Completed final sign-off Nov 2019 | 181 Fremont St | removal/demo of doors, door frames, and door hardware of residential convenience door from residential unit into fsae lobby on level 57 (door 5701) & patch (e) w/new wall to maintain fire rating. remove trench drain at door 5701, fill trench and cap line maher naDetails
removal/demo of doors, door frames, and door hardware of residential convenience door from residential unit into fsae lobby on level 57 (door 5701) & patch (e) w/new wall to maintain fire rating. remove trench drain at door 5701, fill trench and cap line maher na | $10,000 | |
| Oct 29, 2018 | Completed final sign-off Nov 2019 | 181 Fremont St | removal/demo of doors, door frames, and door hardware of residential convenience door from residential unit into fsae lobby on level 55 & 56 (door 5501 & 5601) & patch (e) w/new wall to maintain fire rating. remove trench drain, fill trench and cap line maher naDetails
removal/demo of doors, door frames, and door hardware of residential convenience door from residential unit into fsae lobby on level 55 & 56 (door 5501 & 5601) & patch (e) w/new wall to maintain fire rating. remove trench drain, fill trench and cap line maher na | $15,000 | |
| Aug 3, 2018 | Completed final sign-off Jun 2019 | 350 Bush St | Control Air North Inc | hvac build out of an (e) space ti - ref 201805118936, only for locker rooms, plan room, engineering shop. approx 1000 sq ft area for janitorial and building maintenance staff located in level 2 basement. 4 new fsd's. maher n/a.Details
hvac build out of an (e) space ti - ref 201805118936, only for locker rooms, plan room, engineering shop. approx 1000 sq ft area for janitorial and building maintenance staff located in level 2 basement. 4 new fsd's. maher n/a. | $120,000 |
| May 11, 2018 | Completed final sign-off Jun 2019 | 350 Bush St | Plant Construction Co, Lp | t.i. basement level 1, basement level 2. work includes converting mail room into office, additonal mail room, building engineer shop, ments womens lockerroom, janitorial break rm. mep fire spr, fire alarm under sep permit. n/a maherDetails
t.i. basement level 1, basement level 2. work includes converting mail room into office, additonal mail room, building engineer shop, ments womens lockerroom, janitorial break rm. mep fire spr, fire alarm under sep permit. n/a maher | $450,000 |
| Nov 6, 2017 | Completed final sign-off Feb 2019 | 181 Fremont St | Level 10 Construction Lp | high-rise elevators modified to stop @ levels 13 & 25. the relocation of the women's restrm @ lvl 13. (e) transfer flr mid-rise/highrise elevator lobby 2 level 25, modified to create a transfer flr mid-rise/high-rise elevator lobby. new transfer flr mid-rise/high-rise elevator lobby created @ 13 lvlDetails
high-rise elevators modified to stop @ levels 13 & 25. the relocation of the women's restrm @ lvl 13. (e) transfer flr mid-rise/highrise elevator lobby 2 level 25, modified to create a transfer flr mid-rise/high-rise elevator lobby. new transfer flr mid-rise/high-rise elevator lobby created @ 13 lvl | $110,000 |
| Sep 12, 2017 | Completed final sign-off Jul 2020 | 181 Fremont St | Level 10 Construction Lp | revision to generator fuel oil pa#201305015894-s9 for fuel oil equipment & vent clarifications. n/a ordinance #155-13Details
revision to generator fuel oil pa#201305015894-s9 for fuel oil equipment & vent clarifications. n/a ordinance #155-13 | |
| Sep 1, 2017 | Completed final sign-off Feb 2019 | 181 Fremont St | Level 10 Construction Lp | revision to arch/mep addendum pa #201305015894s4. floor level numbers and accompanying documents(smoke control report, fsae report, etc) have been updated and refected in plans.Details
revision to arch/mep addendum pa #201305015894s4. floor level numbers and accompanying documents(smoke control report, fsae report, etc) have been updated and refected in plans. | |
| Jun 20, 2017 | Completed final sign-off Feb 2019 | 181 Fremont St | Level 10 Construction Lp | revision to 2013-0501-5894 s4: remove interior design features (finishes, fixtures, art, etc) in 3 lobbies from scope of work. signage and life saftey features to remain. adding temporary provisions need for tcoDetails
revision to 2013-0501-5894 s4: remove interior design features (finishes, fixtures, art, etc) in 3 lobbies from scope of work. signage and life saftey features to remain. adding temporary provisions need for tco | |
| May 24, 2017 | Never finaled issued Aug 2017, no final | 199 Fremont St | Level 10 Construction Lp | the landscape design integrates the new building footprint at 181 fremont with 199 fremont's (e) poets garden. the design renovations re-use and re-configure all of the (e) granite stone blocks, continues to use the same palette of stone paving materials and re-interprets the poetry wall byengravingDetails
the landscape design integrates the new building footprint at 181 fremont with 199 fremont's (e) poets garden. the design renovations re-use and re-configure all of the (e) granite stone blocks, continues to use the same palette of stone paving materials and re-interprets the poetry wall byengraving | $200,000 |
| May 23, 2017 | Completed final sign-off Jan 2018 | 350 Bush St | Hathaway Dinwiddie Co. | mep revision to pa #2007-0807-8938 & including deferred work for pa #2016-1214-4926.Details
mep revision to pa #2007-0807-8938 & including deferred work for pa #2016-1214-4926. | |
| Apr 7, 2017 | Completed final sign-off Jan 2019 | 181 Fremont St | Level 10 Construction Lp | evac maps all floors maher naDetails
evac maps all floors maher na | |
| Jun 29, 2016 | Completed final sign-off Mar 2017 | 433 Kearny St | Hathaway Dinwiddie Co. | minor landscaping work in st marys park, work includes creation of additional paths through planting areas. n/a ordinance #155-13Details
minor landscaping work in st marys park, work includes creation of additional paths through planting areas. n/a ordinance #155-13 | $10,000 |
| Jan 20, 2016 | Completed final sign-off Mar 2017 | 433 Kearny St | Hathaway Dinwiddie Co. | work includes removal of parapet & portions of planters on eastern edge of (e) st. mary's square. work will extend this (e) park to the proposed st. mary's square extension new construction ( ref pa #200011024683-s). n/a maher ordinanceDetails
work includes removal of parapet & portions of planters on eastern edge of (e) st. mary's square. work will extend this (e) park to the proposed st. mary's square extension new construction ( ref pa #200011024683-s). n/a maher ordinance | $15,000 |
| Jan 6, 2016 | Expired or cancelled cancelled Jan 2026 | 501 Brannan St | removal atm screens & covers, existing landscaping, light post, & exisitng curbs. add new temporary fabric awnings to match existing window awnings, paving to interior driv eaisle & parking zone, & interior temporary driveway.Details
removal atm screens & covers, existing landscaping, light post, & exisitng curbs. add new temporary fabric awnings to match existing window awnings, paving to interior driv eaisle & parking zone, & interior temporary driveway. | $25,000 | |
| Feb 26, 2015 | Never finaled issued Jun 2015, no final | 500 Pine St | Hathaway Dinwiddie Co. | revision to pa# 200011024683s for stair location, adjusted & door locations on ground floor for 500 pine street site permit.Details
revision to pa# 200011024683s for stair location, adjusted & door locations on ground floor for 500 pine street site permit. | |
| Feb 19, 2015 | Completed final sign-off May 2015 | 350 Bush St | Hathaway Dinwiddie Co. | g/f-interior demo of non-structural west wall; ; re-constructtion of this west wall under separate permit; ab-017 applies. maher n/aDetails
g/f-interior demo of non-structural west wall; ; re-constructtion of this west wall under separate permit; ab-017 applies. maher n/a | $7,000 |
| May 13, 2014 | Completed final sign-off Jan 2015 | 441 Pine St | Hathaway Dinwiddie Co. | to demolish 2 stories, restaurant. ** maher: compliance with ordinance no# 155-13 not required **Details
to demolish 2 stories, restaurant. ** maher: compliance with ordinance no# 155-13 not required ** | $25,000 |
| Apr 18, 2014 | Completed final sign-off Oct 2014 | 470 Pacific Av | remodel portions of an existing office at 2nd floor above quince restaurant including demolition, new partitoins, reinstall windows, new dining for office use, add new unisex bathroom.office brake roomDetails
remodel portions of an existing office at 2nd floor above quince restaurant including demolition, new partitoins, reinstall windows, new dining for office use, add new unisex bathroom.office brake room | $250,000 | |
| Apr 16, 2014 | Never finaled issued Aug 2014, no final | 181 Fremont St | Level 10 Construction Lp | altered site permit 2013-05-01-5894s. correct number stories fr 54 to 55. add 1 story.no increase in overall bldg height. previously added floor, 101b was not accurately reflected in story count. parking ramp between level b2 to b5. replace by auto lift. maher ord not applicable.Details
altered site permit 2013-05-01-5894s. correct number stories fr 54 to 55. add 1 story.no increase in overall bldg height. previously added floor, 101b was not accurately reflected in story count. parking ramp between level b2 to b5. replace by auto lift. maher ord not applicable. | |
| Nov 22, 2013 | Completed final sign-off Dec 2014 | 470 Pacific Av | Hathaway Dinwiddie Co. | remodel (e) quince restaurant to include renovations to (e) dining room including relocating bar. renovations to (e) kitchen including new equipment.Details
remodel (e) quince restaurant to include renovations to (e) dining room including relocating bar. renovations to (e) kitchen including new equipment. | $1,500,000 |
| Oct 22, 2013 | Completed final sign-off Mar 2015 | 181 Fremont St | Level 10 Construction Lp | test drill shaft and location of caission & for building use.Details
test drill shaft and location of caission & for building use. | $60,000 |
| May 16, 2013 | Completed final sign-off Apr 2014 | 183 Fremont St | Level 10 Construction Lp | to demolish 2 stories, office building.Details
to demolish 2 stories, office building. | $95,000 |
| May 15, 2013 | Completed final sign-off Aug 2014 | 181 Fremont St | Level 10 Construction Lp | to demolish 4 stories, office building.Details
to demolish 4 stories, office building. | $395,000 |
| Oct 14, 2011 | Expired or cancelled expired Feb 2013 | 3565 Geary Bl | T F G Construction Inc | construction access. refer to p/a#201105045379 at 1 loraine ct. misc site grading.Details
construction access. refer to p/a#201105045379 at 1 loraine ct. misc site grading. | |
| May 4, 2011 | Never finaled issued Dec 2011, no final | 1 Loraine Ct | T F G Construction Inc | construct approx 60 lf of retaining wall, loackfill, replace existing fence 160 new 4"cc walkway.Details
construct approx 60 lf of retaining wall, loackfill, replace existing fence 160 new 4"cc walkway. | $75,000 |
| Nov 19, 2010 | Completed final sign-off Apr 2012 | 1 Loraine Ct | to erect 1 story "s" occupancy (mausoleum)Details
to erect 1 story "s" occupancy (mausoleum) | $198,400 | |
| Nov 18, 2010 | Completed final sign-off Apr 2012 | 1 Loraine Ct | to erect 1 story "s" occupancy (mausoleum)Details
to erect 1 story "s" occupancy (mausoleum) | $248,000 | |
| Nov 12, 2010 | Completed final sign-off Apr 2012 | 1 Loraine Ct | horizontal extension to (e) administration bldg. add "s" occupancy to building "a"(existing b occupancy). walling in a garage door opening in & providing a new exit to (e) administration building. nichie furnished by owner & installed by contractor. title -24 included.Details
horizontal extension to (e) administration bldg. add "s" occupancy to building "a"(existing b occupancy). walling in a garage door opening in & providing a new exit to (e) administration building. nichie furnished by owner & installed by contractor. title -24 included. | $173,600 | |
| Mar 25, 2010 | Completed final sign-off Apr 2010 | 338 Spear St | Solstice Construction | alteration to single condo unit-demolish closets, laundry wing walls, relocate laundry to new closet, modify closets & add closet. no structural work, no envelope changes. electrical & plumbing under seperate permitDetails
alteration to single condo unit-demolish closets, laundry wing walls, relocate laundry to new closet, modify closets & add closet. no structural work, no envelope changes. electrical & plumbing under seperate permit | $10,000 |
| Jul 9, 2008 | Completed final sign-off Nov 2008 | 555 Mission St | revision to pa #200110130668 s4 & 200806023431 for as built and disabled compliance w/ 2007 cbc, chapter 11b. compliance verification for core and shell to include path of travel from building entry to tenant spaces, restrooms, elevators, drinking fountains, parking and signage for all floors.Details
revision to pa #200110130668 s4 & 200806023431 for as built and disabled compliance w/ 2007 cbc, chapter 11b. compliance verification for core and shell to include path of travel from building entry to tenant spaces, restrooms, elevators, drinking fountains, parking and signage for all floors. | ||
| Jul 9, 2008 | Completed final sign-off Nov 2008 | 555 Mission St | revision to pa 200110130668s4 to change door ratings, from floor b1 to 33rd floor.Details
revision to pa 200110130668s4 to change door ratings, from floor b1 to 33rd floor. | ||
| Jun 26, 2008 | Expired or cancelled expired Aug 2021 | 1028 Market St | interior non structural demo to remove previous tenant improvement in advance of seismic upgrade and future ti work under separate permit. sidewalk barrier. fire protection under seperate permit.Details
interior non structural demo to remove previous tenant improvement in advance of seismic upgrade and future ti work under separate permit. sidewalk barrier. fire protection under seperate permit. | $30,000 | |
| Jun 2, 2008 | Completed final sign-off Nov 2008 | 555 Mission St | revision to 200110130668-s4. accessible stall door swings to be reversed to comply with 2007 code, floors 2-34.Details
revision to 200110130668-s4. accessible stall door swings to be reversed to comply with 2007 code, floors 2-34. | ||
| Aug 7, 2007 | Completed final sign-off Jan 2019 | 350 Bush St | Hathaway Dinwiddie Co. | to erect 20 stories, 3 basements, office bldg.Details
to erect 20 stories, 3 basements, office bldg. | $25,000,000 |
| Jul 6, 2007 | Completed final sign-off Oct 2008 | 55 Page St | revision to appl#200110110515 to provide additional detail to clarify wall type 52 for 2 hr. shaft wall.Details
revision to appl#200110110515 to provide additional detail to clarify wall type 52 for 2 hr. shaft wall. | ||
| Jun 1, 2007 | Completed final sign-off May 2008 | 555 Mission St | Turner Construction Co | erect towner crane per ab23 for pa# 200110130668.Details
erect towner crane per ab23 for pa# 200110130668. | $100,000 |
| Jul 27, 2006 | Expired or cancelled cancelled Oct 2007 | 55 Page St | Superior Automatic Sprinkler | new eight story building, 2 sub level garage. install (n) automatic sprinkler system with wet standpipe. (n) booster pump installed at b-1 level.Details
new eight story building, 2 sub level garage. install (n) automatic sprinkler system with wet standpipe. (n) booster pump installed at b-1 level. | $639,000 |
| Sep 19, 2005 | Completed final sign-off Jul 2016 | 360 Fremont St | Suffolk Constr Co. Inc. Dba Suffolk-Roel | demo 4 story office building.Details
demo 4 story office building. | $175,000 |
| Sep 19, 2005 | Completed final sign-off Jul 2016 | 340 Fremont St | Suffolk Constr Co. Inc. Dba Suffolk-Roel | demo 2 story office building.Details
demo 2 story office building. | $125,000 |
| Sep 19, 2005 | Completed final sign-off Mar 2017 | 340 Fremont St | Suffolk Constr Co. Inc. Dba Suffolk-Roel | erect 40 story residential with 348 dwelling unitsDetails
erect 40 story residential with 348 dwelling units | $60,000,000 |
| Dec 16, 2003 | Expired or cancelled suspend Jun 2004 | 80 Natoma St | revise to app #9817951/s and app #9904253/s includes revised structure system revise unit layoutsDetails
revise to app #9817951/s and app #9904253/s includes revised structure system revise unit layouts | ||
| Oct 13, 2001 | Completed final sign-off Jun 2005 | 557 Mission St | demolish a four story retail bldgDetails
demolish a four story retail bldg | ||
| Jul 20, 2001 | Completed final sign-off Jan 2006 | 199 New Montgomery St | to erect parking retail 166 residentialsDetails
to erect parking retail 166 residentials | $500,000 | |
| Nov 2, 2000 | Completed final sign-off Mar 2017 | 500 Pine St | to erect office/storage/parking/retail.Details
to erect office/storage/parking/retail. | $1,000,000 |