FiledOutcomeAddressContractorWork described on the permitDeclared cost
Sep 16, 2026In progress181 Fremont St18th fl - installation of door hardware release of electronically locked egress doors. reference pa# 202412187109$2,500
Sep 15, 2026In progress181 Fremont Stlevel 16: egress path revision and installation of door hardware release of electronic door lockers. (ref bpa: 2024.1218.7109 and 2024.0730.7534)$5,000
Sep 15, 2026In progress181 Fremont St16th and 18th fl: installation of pre manufactured phone booths$30,000
Jul 31, 2026In progress181 Fremont StSc Builders, Inc30th fl - revision to pa 202604239936, removal of scope from conference room/yoga room which includes lighting & mechanical
Jul 20, 2026In progress181 Fremont StSc Builders, Incinstallation of architectural, non-rated stair enclosure at existing architectural convenience/communicating stair on level 36. no changes in use, occupancy load, nor egress occupant load cabacity. no change to smoke control.$50,000
Jul 1, 2026In progress181 Fremont StSc Builders, Incref pa# 202604018674 (10th fl) & pa# 202604159456 (11th fl.): deffered submitals: phone booths anchorage and fan powered box seismic anchorage structural details on l10 & 11$10,000
Apr 23, 2026In progress181 Fremont StSc Builders, Inc30/f: addition of power, modifications to (e) millwork in (e) pantry. conversion of storage room into conference room.$250,000
Mar 24, 2026In progress181 Fremont StSc Builders, Incto comply with disables access - per ab-056. in order to demonstrate compliance with diabled access requirments for commericial office building access at 181 fremont st.
Sep 22, 2025Completed181 Fremont StRapid Fire Safety&Security Llc Dba Pafa21st floor: fire alarm t.i. adding 1 relay to existing notifier nfs2-3030 fire alarm system.$6,695
Jul 16, 2025Completed181 Fremont StAllied Fire Protection17th/fl: modify sprinkler system - ti revisions ref#2025-0703-0191$5,100
Jul 3, 2025Completed181 Fremont StLevel 10 Construction Lp17th floor: board room revisions including grid and title ceilings, light fixtures, millwork and finishes. no plumbing fixtures.$250,000
May 5, 2025In progress181 Fremont StRapid Fire Safety&Security Llc Dba Pafa19th,20th,21st fl fire alarm t.i. adding 3 smoke detectors to e) notifier nfs2-3030 fire alarm system ref pa 2025-0505-5811$8,350
May 5, 2025In progress181 Fremont StMetropolitan Electrical Constructionadd card readers @ loby door ad noted. floors 19,20,21$30,000
Dec 18, 2024In progress181 Fremont StLevel 10 Construction Lp18/fl- revision 202407307548- work includes relocation of exit sign and path of travel on level 18 (e) security card readers to remain
Dec 18, 2024In progress181 Fremont StLevel 10 Construction Lp16/fl- revision 202407307534- work includes relocation of exit sign and path of travel on level 16 (e) security card readers to remain
Oct 31, 2024Completed181 Fremont StAcco Engineered Systems Inc. Dba Acco En28/fl- install (n) ductwork on (e) fan powered box on northside$38,000
Oct 15, 2024Completed181 Fremont StRapid Fire Safety&Security Llc Dba Pafa28th fl- fire alarm ti relocate (1) existing speaker strobe on (e) notifier nfs2-3038 fire alarm system pa: 202409261659$2,910
Sep 26, 2024Completed181 Fremont StSc Builders, Inc25th fl: construction of (n) millwork including minor non structural partitions. (e) acoustical grid, tile & gyp board ceilings. light fixtures and finishes to remain. no change in use and exit stairs. egress path elevators (deferred sprinklers, fire alarm & mep if needed)$188,000
Sep 26, 2024Completed181 Fremont StSc Builders, Inc28/f. construction of new meeting room including non str partition, acounstical grid ceiling panel light fixture, door and finishes. existing acounstcial grid tile and gyp board ceiling light fixtures and finishes to remain. no change in use, exit stair egress path, elevators (mep fire alarm sprinkl$188,000
Sep 9, 2024In progress181 Fremont StLevel 10 Construction Lp17/f: admin permit - obtain fire assembly permit correction to pa# 202408209070 to denote it was a revision to pa# 202406104047 and not pa#202406104048.
Aug 21, 2024In progress181 Fremont StRapid Fire Safety&Security Llc Dba Pafafloors# 4, 7, 17, 24, 34: fire alarm ti - stairwell door locks are being reconnected to main building security system as existing tenant vacates. no new equipment; existing relay modules to be revised.$6,280
Aug 20, 2024Completed181 Fremont StLevel 10 Construction Lprevision to 202406104048, work includes the addition of new card readers and ceiling addition
Jul 30, 2024Completed181 Fremont StLevel 10 Construction Lp18th fl revision to pa # 2024-0610-4048 addition of new card readers
Jul 30, 2024Completed181 Fremont StLevel 10 Construction Lprevision to 202406104044, work includes the addition of new card readers.
Jul 9, 2024Completed181 Fremont StRapid Fire Safety&Security Llc Dba Pafafire alarm ti adding 6 speaker strobes, 1 duct detectord, 4 relay modules to e notifier nfs2-3030 fire alarm system$15,380
Jul 3, 2024Completed181 Fremont StAllied Fire Protection17th/f: modify fire sprinklers system, relocate 18 & add 10 sprinklers. ref to 202406104047$10,534
Jul 3, 2024Completed181 Fremont StAllied Fire Protectionref 202406104048- 18 flr-fire only modify fire spirinkler system. relocated (4) and add (6) sprinklers$4,000
Jul 3, 2024In progress181 Fremont StAllied Fire Protectionref pa 2024-0610-4044 modify fire sprinkler system relocate 4 & add 6 sprinklers$5,000
Jun 10, 2024Completed181 Fremont StLevel 10 Construction Lpconstruction of new non-structural partitions, acoustical grid and tiles and gyp board ceilings, light fixtures, millwork, and finishes 16th fl.$224,577
Jun 10, 2024Completed181 Fremont StLevel 10 Construction Lpconstruction of new non-structural partitions, acoustical grid and tile and gyp board ceilings, light fixtures, millwork, and finishes 18th fl.$331,360
Jun 10, 2024Completed181 Fremont StLevel 10 Construction Lpconstruction of new non-structural partitions, acoustical grid and tiles and gyp board ceilings, light fixtures, millwork, and finishes 17th fl.$232,309
Nov 20, 2023Completed181 Fremont StSc Builders, Inc7th flr: construction of new non-structural partition, gyp. bd. gyp board ceiling. (1) light fixture added (1) plumbing fixtures to be relocated, finishes to include changes to the (e) hallway 701. mep deferred for future application. no change in exit stair or elevator$175,000
Nov 1, 2021Completed181 Fremont StPacific Auxiliary Fire Alarm55th fl: fire alarm ti: adding 1 new speakers and relocate 3 (e) speaker on (e) nfs2-3030 fire alarm system$8,502
Aug 2, 2021Completed181 Fremont StPacific Auxiliary Fire Alarmfire alarm ti: add (1) relay, (1) smoke detector, (1) monitor module, (1) dual point monitor module to (e) notifier nfs2-3030 fa system$6,630
May 20, 2021Completed181 Fremont StPacific Auxiliary Fire Alarmfire alarm ti: adding (15) speakers to existing notifier nfs2-3030 fa system.$8,224
May 10, 2021Completed181 Fremont StLevel 10 Construction Lpto obtain final inspection for work approved under permit# 201804166439, 201804277573, and 201804277574. all work is completed.
May 10, 2021Completed181 Fremont StLevel 10 Construction Lpto obtain final inspection for work approved under permit application #'s 201804166436, 201804166442, 201804166440. all work is completed.
Apr 28, 2021Completed181 Fremont Stas-built permit for errcs. replace yagi antenna on roof, and reprogram bda with new frequencies. ref. pa # 2013-0501-5894 s19
Mar 22, 2021Completed181 Fremont Stlevel 40: new battery rack and ac/dc charger as required by pg&e. level 58: trash chute exhaust revision. level 58: new fan and louver for extg microturbine cooling load.$46,000
Jan 14, 2021Completed181 Fremont StParadise Door And Serviceti l-39 assembly revision. administrative permit only for sffd assembly stamps for approved permit. see pa #2020-1008-6196.
Dec 8, 2020Completed181 Fremont StPacific Auxiliary Fire Alarmfire alarm ti: (3) speaker-strobes, (3) duct detectors, (2) monitor modules, (4) dual point monitor modules, (2) dual point monitor/relay modules & (1) relay module are being relocated and reinstalled (to provide easier access) to existing notifier nrs2-3030 fa system.$20,400
Sep 19, 2020Completed181 Fremont StPacific Auxiliary Fire Alarmfire alarm only - existing doas fans are being replaced from level 5 to level 38. fire alarm devices (duct smoke detector & control modules/relays are being removed and the being reinstalled on new fnns.$25,000
Mar 11, 2020Expired or cancelled181 Fremont StLevel 10 Construction Lpinstall new trash chute exhaust fan at roof level$20,000
Jan 29, 2020Completed181 Fremont StAllied Fire Protectionfire sprinklers: hoa level 3 & 4. 7 added level (3), 2 relocated on level 4. total 9 sprinklers ref pa 2019-0923-2376$4,400
Jan 24, 2020Completed181 Fremont StLevel 10 Construction Lprevision to pa #201908078142 - remove existing lobby doors at level 1 & 7, replace with new ballistic reinforced doors, add ballistic reinforcement panels at level 7 lobby walls, replace millwokr at levels 1 & 7.$10,000
Dec 19, 2019Completed181 Fremont StPacific Auxiliary Fire Alarmfire alarm t.i. adding (2) speakers and (4) speaker-strobes, to existing notifier nfs2-3030 fire alarm system$6,516
Nov 25, 2019Never finaled181 Fremont StPacific Auxiliary Fire Alarmfloors 5,6,13: fire alarm t.i. to delete 3 duct detectors from extg notifier nfs2-3030 fa system. ref app#201907317407. n/a for maher$9,300
Oct 23, 2019Completed181 Fremont StPacific Auxiliary Fire Alarmlevel 4: fire alarm only. t.i. to extg notifier nfs2-3030. adding 1 control relay for door holder. n/a for maher$6,000
Sep 23, 2019Expired or cancelled181 Fremont StAcco Engineered Systems Inc. Dba Acco Enrevision to app#201907317407 to change fsd to smoke control damper. n/a for maher$10,000
Sep 23, 2019Never finaled181 Fremont StBaxter Constructionti on level 3 & 4 - level 3 add all gender restroom, convert existing storage to laundry room, remove storage lockers; 4th fl - convert existing office to break room, hvac, plumbing, electrical under separate permits$150,000
Aug 7, 2019Completed181 Fremont StLevel 10 Construction Lpreplace millwork at level 1 and 7. remove e lobby doors at level 1 and 7. replace with new ballistic reinformced doors. add aballistic reinforcement panels at level 7 lobby walls$100,000
Jul 31, 2019Never finaled181 Fremont StAcco Engineered Systems Inc. Dba Acco Enrev to pa#'s 201805149058, 201808167576, 201811075285, 201811075286; remove fire smoke dampers on floors 4/5/6/13/14. maher n/a.$10,000
Mar 19, 2019Completed181 Fremont StPacific Auxiliary Fire Alarm6th fl - full floor ti to existing notifier nfs2-3030 ref pa 2018-0829-8666. adding 3 smoke detectors, 12 duct detectors, 7 relay modules, 8 monitor modules, 5 dual monitor modules; islator module; 25 speaker strobes, 2 speaker strobe to be relocated$33,000
Mar 19, 2019Completed181 Fremont StPacific Auxiliary Fire Alarm5th fl - full floor ti to existing notifier nfs2-3030 ref pa 2018-0829-8664. adding 4 smoke detectors, 15 duct detectors, 8 replay modules; 9 dual monitor modules; islator module; 17 speaker strobes, relocating 2 existing speaker strobes$39,000
Mar 11, 2019Completed181 Fremont StEdison Fire Extinguisher Company Inclevel 6: ul 300 fire system installation. n/a for maher$27,730
Mar 4, 2019Completed181 Fremont StPacific Auxiliary Fire Alarmfull floor fire alarm t.i. to extg notifier nsf2-3030. adding 2 smoke detectors, 13 duct detectors, 5 relay modules, 5 monitor modules, 2 speakers, and 18 speaker strobes. 4 speaker strobes are being relocated. ref app#201810102809.$36,000
Mar 4, 2019Completed181 Fremont StLevel 10 Construction Lp5th floor- construction of new rater 11 have partition at (e) perimeter window. sprinkler removal under separate applicatton$15,000
Mar 4, 2019Completed181 Fremont StPacific Auxiliary Fire Alarm4th flr. fire alarm 39th fl offices, 4 smoke detectors, 12 duct detectors, 6 monitor modules, 7 relay modules, 1 isolator module, 19 spaker strobes, 1 speaker$32,000
Mar 4, 2019Never finaled181 Fremont StLevel 10 Construction Lp6th floor- construction of new rater 11 have partition at (e) perimeter window. sprinkler removal under separate application$15,000
Feb 22, 2019Completed181 Fremont StPacific Auxiliary Fire Alarmbuild permit #2018-1010-2810 36th floor fire alarm ti (3) new smoke detectors, (16) duct detectors, (8) relay modules, (5) monitor modules, (1) speaker, (25) speakers/strobes.$16,000
Feb 15, 2019Never finaled181 Fremont StPacific Auxiliary Fire Alarminstall remodel communicator in security office on l2$5,208
Feb 15, 2019Completed181 Fremont StPacific Auxiliary Fire Alarmfire arlm 2 new smoke detectors, 13 duct detectors, 5 relay modules, 5 monitor modures 5 speakers, 16 speaker strobes$6,000
Jan 10, 2019Completed181 Fremont StAllied Fire Protection38th flr - fire sprinklers 54 added, 9 relocated total 63 red 201810102812 maher na$58,300
Jan 10, 2019Never finaled181 Fremont StAllied Fire Protection6th flr - fire sprinklers 95 addes, 12 relocated total 107 red 201808298666 maher na$58,300
Dec 18, 2018Completed181 Fremont StPacific Auxiliary Fire Alarm29/f: ref building pa# 201801310021; ref fire pa# 201804166484; revision & as built fire alarm drawing addition/smoke detector$2,900
Dec 18, 2018Completed181 Fremont StPacific Auxiliary Fire Alarmref building pa# 201801310021; ref fire pa# 201804166483; revision & as builts fire alarm drawings, added 2 smoke detector (unisex restroom & corridor)$2,900
Dec 18, 2018Completed181 Fremont StAllied Fire Protectionfire sprinkler 111 added, 14 relocated, 125 total 201808298664 facebook ti lvl 5$68,000
Dec 18, 2018Completed181 Fremont StPacific Auxiliary Fire Alarmref building pa# 201803284864; ref fire pa# 201803123398; revision & as built fire alarm drawings, per sffd fire inspector adding 1 smoke detector above pre action panel$2,900
Dec 11, 2018Completed181 Fremont StAllied Fire Protectionlevel 7 fire sprinklers: (3) added adendum #1 (original fire sprinkler pa# 201811085354)$1,500
Dec 11, 2018Completed181 Fremont StPacific Auxiliary Fire Alarm14th fl: fire alarm full floor ti to (e) nfs2-3030. adding 2 smoke detectors, 12 duct detectors, 6 relay modules, 6 monitor modules, 1 isolator module, 2 speakers, & 24 speaker strobes, 1 (e) speaker to be relocated. ref oa #201808167576.$40,000
Dec 4, 2018Completed181 Fremont StAllied Fire Protectionlevel 15: ref pa# 201808167574; fire sprinklers: (26) added, (2) relocated, total (28) sprinklers$14,400
Dec 4, 2018Never finaled181 Fremont StAllied Fire Protectionlevel 18: ref pa# 201809170503; fire sprinklers (31) added, (5) relocated, total (36) sprinklers$18,500
Dec 3, 2018Completed181 Fremont StLevel 10 Construction Lphealth only routing. bldg review uner #2018.0816.7576
Nov 30, 2018Completed181 Fremont StLevel 10 Construction Lp7/f: rev to pa# 201808107073; to revise occupant load in 7th fl. cafe area per sffd field inspection. reduce occupancy from 66pp to 48pp
Nov 29, 2018Completed181 Fremont StPacific Auxiliary Fire Alarmfull floor ti to e nfs2 3030 adding 2 smoke detectors, 16 duct detecotrs, 6 control relay modules, 6 monitor modules, 1 isolator module, 5 speakers, 18 speaker strobes, 3 speaker strobe$36,400
Nov 29, 2018Completed181 Fremont StPacific Auxiliary Fire Alarmfire alarm full fl ti to e nfs2-3030, adding 2 smoke det, 16 duct detectors, 6 control relay modules, 6 monitor modules, 1 isolator modules, 5 speaker, 18 speaker strobes, 3 speaker strobes, being relocated$36,400
Nov 29, 2018Completed181 Fremont StPacific Auxiliary Fire Alarmlevel 20: fire alarm full fl ti to e nfs2 3030 add 3 smoke dete, 19 duct detectors, 11 control relay modules, 1 isolator module, 4 speakers, 31 speaker strobes. 3 speaker strobes are being relocated$38,200
Nov 29, 2018Completed181 Fremont StPacific Auxiliary Fire Alarmlevel 21: fire alarm full fl ti to e nfs2-3030, adding 2 smoke det, 17 duct detectors, 6 control relay modules, 6 monitor modules, 1 isolator modules, 5 speaker, 18 speaker strobes, 2 speaker strobes being relocated ref 201810011839$36,400
Nov 29, 2018Completed181 Fremont StPacific Auxiliary Fire Alarm16 fl: full fl f/a ti to (e) nfs2-3030. add: 2 smoke detectors, 16 duct detectors, 6 control relay modules, 6 monitor modules, 5 speakers, 21 speaker strobes, 3 speaker strobe being relocated. ref pa #201809170487.$38,000
Nov 29, 2018Completed181 Fremont StPacific Auxiliary Fire Alarm17 fl: full fl f/a ti to (e) nfs2-3030. add: 3 smoke detectors, 19 duct detectors, 11 control relays, 6 monitor modules, 1 isolater module, 7 speakers, 33 speaker strobes, 2 speaker strobe being relocated. ref pa #201809170501.$40,000
Nov 27, 2018Completed181 Fremont StAllied Fire Protectionfl0or 16 -fire sprinkler 43 added, 6 relocated, 49 total 201809170487$26,800
Nov 27, 2018Completed181 Fremont StAllied Fire Protectionon 19th floor - revise sprinkler system - fire sprinkler 31 added, 5 relocated, total 36 ref 201810011844. n/a for maher.$19,600
Nov 27, 2018Completed181 Fremont StAllied Fire Protectionon 20th floor revise sprinkler system -fire sprinkler 48 added, 2 relocated total 50 ref 201810022002. n/a for maher.$27,200
Nov 27, 2018Completed181 Fremont StAllied Fire Protectionon 14th floor - fire sprinkler system revision -fire sprinklers 96 added, 4 relocated, 100 total ref 201808167576. n/a for maher.$54,400
Nov 20, 2018Completed181 Fremont StLevel 10 Construction Lplevel 4 to 6 new grease exhaust system. revision to level 4, 201712065692. grease interceptor room to accept duct from level 6 new grease duct exhaust screens on level 4. new air intake louvers on level 6. grease duct shaft under 201808298664, 201808298666, mech under 201811075285, 201811075286$20,000
Nov 16, 2018Completed181 Fremont StPacific Auxiliary Fire Alarm13th fl - full floor ti to existing notifier nfs2-3030, adding 4 smoke detectors, 12 duct detectors, 8 relay modules, 11 monitor modules, 8 dual monitor/relay modules, 2 speakers, 27 speaker strobes, 1 speaker strobe is being relocated; ref pa#201805149058$42,000
Nov 15, 2018Completed181 Fremont StAllied Fire Protection35th floor: fire sprinklers: 23 added. 10 relocated. total 33. ref app#201810102809. n/a for maher$18,000
Nov 15, 2018Completed181 Fremont StAllied Fire Protection37th floor: fire sprinklers: 41 added. 7 relocated. total 48. ref app#201810102811. n/a for maher$14,600
Nov 15, 2018Completed181 Fremont StAllied Fire Protection36th floor: fire sprinklers: 65 added. ref #201810102810. n/a for maher$35,400
Nov 15, 2018Completed181 Fremont StAllied Fire Protection57th floor: fire sprinklers: 1 added. 10 relocated. total 11. ref app#201305015894. n/a for maher$5,500
Nov 14, 2018Completed181 Fremont StEdison Fire Extinguisher Company Incul300 fire sprinl hood & ducts ref 201808167576 maher na$14,000
Nov 14, 2018Completed181 Fremont StEdison Fire Extinguisher Company Incul300 fire sprinl hood & ducts ref 201805149058 maher na$33,000
Nov 8, 2018Completed181 Fremont StAllied Fire Protection7th fl - fire sprinklers (20) added, (1) relocated, total 21 sprinklers. ref pa 2018-0810-7073$10,500
Nov 7, 2018Completed181 Fremont StLevel 10 Construction Lp6th floor - mep only arch approved under pa# 201808298666 - installation of dining area grease duct term on 4th floor fire alarm & sprinklers under seperate permit. ** maher: n/a **$10,000
Nov 7, 2018Completed181 Fremont StLevel 10 Construction Lp5th floor - mep only arch approved under pa# 201808298664 - installation of dining area & servery for employee use. ** maher: n/a **$10,000
Nov 6, 2018Completed181 Fremont StAllied Fire Protection21st fl - facebook ti lve. 21 fire sprinklers 34 added. ref pa 2018-1001-1839$18,300
Nov 6, 2018Completed181 Fremont StAllied Fire Protectionfire sprinklers 74 new 16 relocated 90 total ref 201809170501 maher na$46,400
Oct 31, 2018Completed181 Fremont StAllied Fire Protection13/f: new f/s system - add 78, relocate 32 for a total of 110 f/s heads. ref t.i. pa201805149058. maher n/a.$59,000
Oct 30, 2018Completed181 Fremont StPacific Auxiliary Fire Alarm15th fl: fire alarm ti to existing notifier nfs2-3030. adding 2 smoke detectors, 14 duct detectors, 19 control relays, 5 monitor modules, 1 isolator modules, 2 speakers, and 13 speaker strobes, 3 speaker strobes are being relocated. ref pa #$46,000
Oct 30, 2018Completed181 Fremont StPacific Auxiliary Fire Alarm7th fl: fire alarm ti on existing notifier nfs2-3030. adding 4 duct smoke detectors, 2 monitor modules (1 dual and 1 single input), 5 control relay, 1 solator module, and 6 speaker strobes. ref pa #201808107073$74,000
Oct 30, 2018Completed181 Fremont StPacific Auxiliary Fire Alarm14th fl: fire alarm ti to an existing nfs2-3030. adding 1 smoke detector, 5 relay modules, 1 speaker strobe. ref pa #201805290380.$4,500
Oct 29, 2018Completed181 Fremont Stremoval/demo of doors, door frames, and door hardware of residential convenience door from residential unit into fsae lobby on level 55 & 56 (door 5501 & 5601) & patch (e) w/new wall to maintain fire rating. remove trench drain, fill trench and cap line maher na$15,000
Oct 29, 2018Completed181 Fremont Stremoval/demo of doors, door frames, and door hardware of residential convenience door from residential unit into fsae lobby on level 57 (door 5701) & patch (e) w/new wall to maintain fire rating. remove trench drain at door 5701, fill trench and cap line maher na$10,000
Oct 10, 2018Completed181 Fremont StLevel 10 Construction Lp37th flr - open office ti - non bearing partitions, millwork & finishes. mep included. fire/life safety under sep permit$1,300,000
Oct 10, 2018Completed181 Fremont StLevel 10 Construction Lp35th flr - open office ti - non bearing partitions, millwork & finishes. mep included. fire/life safety under sep permit$1,300,000
Oct 10, 2018Completed181 Fremont StLevel 10 Construction Lp38th flr - open office ti - non bearing partitions, millwork & finishes. mep included. fire/life safety under sep permit$1,300,000
Oct 10, 2018Completed181 Fremont StLevel 10 Construction Lp36th flr - open office ti - non bearing partitions, millwork & finishes. mep included. fire/life safety under sep permit$1,300,000
Oct 2, 2018Completed181 Fremont StLevel 10 Construction Lp20th fl: construction of new non structural partitions, acoustical grid and tile & 649, board ceilings, millwork, finishes, mech, elec, and plumbing. conv. stairs, fire alarm, sprinklers, under seperate permit$1,365,000
Oct 1, 2018Completed181 Fremont StLevel 10 Construction Lp21st fl: construction of non-structural partitions, acoustical grid & tile & gyp. board ceilings, millwork, finishes, mech, electrical & plumbing. connecting stairs, fire alarm, sprinklers under sep permit. maher na$1,365,000
Oct 1, 2018Completed181 Fremont StLevel 10 Construction Lp19th fl: construction of new non-structural partitions, acoustical grid & tile & gyp board ceilings, light fixtures, millwork, finishes, mechanical work, electrical, plumbing. connecting stairs, fire alarm, sprinklers under sep permit. maher na$1,365,000
Sep 21, 2018Completed181 Fremont StPacific Auxiliary Fire Alarm7th fl: fire alarm ti to (r) notifies nfs2-30303 adding 2 duct smk det w/internal control relay ref 201806141936$6,253
Sep 19, 2018Expired or cancelled181 Fremont Stretail tenant street level non structural partitions light fixtures, millwork finishes$16,000
Sep 19, 2018Completed181 Fremont StLevel 10 Construction Lpretail tenant street level non structural partitions, light fixtures, millwork finishes$16,000
Sep 18, 2018Completed181 Fremont StLevel 10 Construction Lplevel 38: new fan room with new tenant fan and seismic isolation. new exhaust fan for commercial tennants. n/a for maher$220,000
Sep 18, 2018Completed181 Fremont StLevel 10 Construction Lpnew distribution switchboard entrance. new 480 bosduct, new bosduct from utility vault on b2 to floor 5 distribution panel. enlarge electrical room on b2. rate electrical room on 5th to 2 hours - new fsd. ** maher: n/a **$220,000
Sep 17, 2018Completed181 Fremont StLevel 10 Construction Lp17th fl tenant improvement, non bearing partition new ceiling, finishes, pantry$1,365,000
Sep 17, 2018Completed181 Fremont StLevel 10 Construction Lp16th floor - construction of new non-structural partitions, acoustical grid & tile and gyp board ceilings, light fixtures, millwork and finishes. mep included - sprinklers & f/a under separate permit. convenience stair under separate permit$1,365,000
Sep 17, 2018Completed181 Fremont StLevel 10 Construction Lp18th fl tenant improvement, non bearing partition new ceiling, finishes, pantry$1,365,000
Aug 29, 2018Completed181 Fremont StLevel 10 Construction Lp5th flr - arch ti - non bearing walls, office millwork, finishes, kitchen and servery. mep under separate permit$1,575,000
Aug 29, 2018Completed181 Fremont StLevel 10 Construction Lp6th flr - arch ti - non structural walls, office millwork, finishes, kitchen and servery. mep under separate permit$1,593,930
Aug 16, 2018Completed181 Fremont StLevel 10 Construction Lp15th - ti with no bearing partitions for open office$1,300,000
Aug 16, 2018Completed181 Fremont StLevel 10 Construction Lp14th - ti with no bearing partitions. kitchen with back of house support areas. offices & conference rooms$1,300,000
Aug 14, 2018Completed181 Fremont StAllied Fire Protection8th floor - fire sprinklers 58 added, 11 relocated = 69 sprinklers total. ref pa 2018-0507-8360. maher n/a.$37,600
Aug 10, 2018Completed181 Fremont StPacific Auxiliary Fire Alarm8th floor: fire alarm t.i. to an extg notifier nfs2-3030 adding 6 smoke detectors, 15 duct smoke detectors, 16 relay modules, 10 monitor modules, 2 seakers and 22 speaker strobes, 4 extg speaker strobe are being relocated. ref app#201805078360$33,000
Aug 10, 2018Completed181 Fremont StPacific Auxiliary Fire Alarm12th fl ref pa# 201805108812; fire alarm full fl t.i. to existing notifier nfs2-3030, adding (3) smoke detectors, (16) duct smoke detector, (7) relay modules, (7) monitor modules, (5) spearkers, and (19) speaker strobes, (4) speaker strobes devicies are being relocated$33,000
Aug 10, 2018Completed181 Fremont StPacific Auxiliary Fire Alarm10th floor: fire alarm t.i. to an extg notifier nfs2-3030 adding 3 smoke detectors, 16 duct smoke detectors, 7 relay modules, 7 monitor modules, 1 isolator modules, 5 speakers and 19 speaker strobes, 4 extg speaker strobe are being relocated. floor 10 is part of a internal$33,000
Aug 10, 2018Completed181 Fremont StPacific Auxiliary Fire Alarm9th floor: fire alarm t.i. to an extg notifier nfs2-3030 adding 3 smoke detectors, 18 duct detectors, 7 relay modules, 7 monitor modules, 1 isolator modules, 7 seakers and 24 speaker strobes, 4 extg speaker strobe are being relocated. 9th floor is partof internal stairway conecting fl 9-11$33,000
Aug 10, 2018Completed181 Fremont StPacific Auxiliary Fire Alarmref pa# 201805088579; fire alarm t.i. to (e) notifier nfs2-3030, adding (4) smoke detctors, (10) relay modules, (7) monitor modules, (1) isolator module, (9) sprinklers and (33) speaker/strobes, (4) existing speaker strobes are being relocated. 11th fl. is part of a internal stairwell connecting$33,000
Aug 10, 2018Completed181 Fremont StLevel 10 Construction Lp7th fl l- construction of cafe - no open flame. electric only. 64 occupant load. retail coffee sales$75,000
Jul 26, 2018Completed181 Fremont StLevel 10 Construction Lprevision to 201805149058. add external louvers on level 13. maher na
Jul 25, 2018Completed181 Fremont StLevel 10 Construction Lprevision to pa 2018-0508-8579- add ul detail for partition head. add carreaders matrix- upgrade egress plans with cardreaders and door tags- upgrade wd-2 stubstrates add fire treated notes. no work.
Jul 25, 2018Completed181 Fremont StLevel 10 Construction Lprevision to pa 2018-0510-8812- add ul detail for partition head. add carreaders matrix- upgrade egress plans with cardreaders and door tags- upgrade wd-2 stubstrates add fire treated notes. no work.
Jul 25, 2018Completed181 Fremont StLevel 10 Construction Lprevision to pa 2018-0508-8574- add ul detail for partition head. add carreaders matrix- upgrade egress plans with cardreaders and door tags- upgrade wd-2 stubstrates add fire treated notes. no work.
Jul 25, 2018Completed181 Fremont StLevel 10 Construction Lprevision to pa 2018-0507-8356- add ul detail for partition head. add carreaders matrix- upgrade egress plans with cardreaders and door tags- upgrade wd-2 stubstrates add fire treated notes. no work.
Jul 19, 2018Completed181 Fremont StAllied Fire Protection11th fl - facebook ti - 74 added, 11 relocated ref pa 2018-0508-8579$43,800
Jul 19, 2018Completed181 Fremont StAllied Fire Protection12th fl fire sprinklers - facebook - 49 added, 8 relocated. ref pa 2018-0510-8812$29,300
Jul 19, 2018Completed181 Fremont StAllied Fire Protection9th fl - facebook fire sprinklers 59 added, 7 relocated ref pa 2018-0507-8356$33,900
Jul 19, 2018Completed181 Fremont StAllied Fire Protection10th fl, facebook ti - 39 added, 7 relcoated ref pa 2018-0508-8574$23,700
Jul 18, 2018Completed181 Fremont StPacific Auxiliary Fire Alarm13/f: ref arch/mep 201805048265 & f/a 201803163922 based on bldg t.i.: change the arch background location of the women restroom, smoke detector and speaker. strobe location moed to new locations. maher n/a.
Jun 18, 2018Completed181 Fremont StLevel 10 Construction Lpstormwater control systems reference pa #013-0501-5894.
Jun 14, 2018Completed181 Fremont StLevel 10 Construction Lp7th fl- installation of light standards in lobby are, add rack room, and storage room.$9,000
May 31, 2018Completed181 Fremont StAllied Fire Protection32nd floor - fire sprinklers: 32 added, 3 relocated ref 201803264634$18,200
May 31, 2018Completed181 Fremont StAllied Fire Protection33rd floor - fire sprinklers: 52 added, 6 relocated ref 201803264630$30,200
May 30, 2018Completed181 Fremont StAllied Fire Protectionfire sprinklers 21 added, 0 relocated. total 21 sprinklers. ref pa 2018-0326-4637$10,800
May 23, 2018Completed181 Fremont StLevel 10 Construction Lpconvenience stairs connecting levels 19 - 21 n/a for maher$250,000
May 23, 2018Completed181 Fremont StAllied Fire Protectionref# 201803264632 fire sprinklers (45) added sprinklers, (6) relocated, (51) total, n/a maher$26,200
May 23, 2018Completed181 Fremont StLevel 10 Construction Lpconvenience stairs connecting levels 16 - 18. n/a for maher$250,000
May 23, 2018Completed181 Fremont StAllied Fire Protection22/f: ref: 201803264623 fire sprinklers: (33) added sprinklers, (5) relocated, (38) total sprinklers. n/a maher$19,600
May 23, 2018Never finaled181 Fremont StAllied Fire Protectionref# 201803264629; fire sprinklers (21) added, (8) relocated, (29) sprinklers total. n/a maher$14,900
May 21, 2018Completed181 Fremont StGolden State Fire Safety/Dba:Gs Fire Sansul install as built submittal pa# 201805108799; smoke control report added to drawings.$35,000
May 16, 2018Completed181 Fremont StPacific Auxiliary Fire Alarmfl 23 ref pa 2018-0326-4632 - full floor ti, 2 smoke detectors, 18 duct detectors, 7 relay modules, 6 monitor modules, 1 isolat0r modules, 1 speaker, 29 speaker strobes are being added to (e) notifier nfs2-3030. 3 speaker strobes are being relocated, level 23 is part of internal stairway connecting$34,500
May 16, 2018Completed181 Fremont StPacific Auxiliary Fire Alarmref pa 2018-0326-4634 - full floor ti, 2 smoke detectors, 15 duct detectors, 6 relay modules, 6 monitor modules, 1 isolator modules, 4 speakers and 17 speaker strobes are being added to (e) notifier nfs2-3030. 3 speaker strobes are being relocated. level 32 is part of internal stairway connecting$34,500
May 16, 2018Completed181 Fremont StPacific Auxiliary Fire Alarmfl24 repa 2018-0326-4632 - full floor ti, 2 smoke detectors, 16 duct detectors, 2 relay modules, 6 monitor modules, 1 isolater modules, 4 speakers and 19 speaker strobes are being added to (e) notifier nfs2-3030. 4 speaker strobes are being relocated, level 24 is part of internal stairway connecting$34,500
May 16, 2018Completed181 Fremont StPacific Auxiliary Fire Alarmfl34 ref:pa 2018-0326-4637 full floor ti, 2 smoke detectors, 15 duct detectors, 6 relay modules, 6 monitor modules, 1 isolator modules, 4 speakers and 16 speaker strobes are being added to (e) notifier nfs2-3030. 4 speaker strobes are being relocated. level 34 is part of internal stairway connecting$33,000
May 16, 2018Completed181 Fremont StPacific Auxiliary Fire Alarmlevel 33. full floor tenant improvement. 3 smoke detector, 19 duct detectors, 9 relay modules, 6 monitor modules, 1 isolator module, 2 sprinklers & 28 speaker strobes are being added to nfs2-3030. 4 speaker strobes are being relocated. level 33 is part of internal stairway connecting levels 32-34.$33,500
May 16, 2018Completed181 Fremont StPacific Auxiliary Fire Alarmlevel 22. full floor tenant improvement. 2 smoke detectors, 16 duct detectors, 6 relay modules, 6 monitor modules, 1 isolation module, 4 speaker & 19 speaker strobes are being added to (e) notifier nfs2-3030. 4 speaker strobes are being relocated. level 22 is part of internal stairway$34,500
May 14, 2018Completed181 Fremont StLevel 10 Construction Lp13th fl ti constuction of new non structural partitions, acoustical grid and tile and gyp bd ceiling. construction of kitchen and servery. structural reinforcement to cooridinate with mep service maher not req$2,800,000
May 10, 2018Completed181 Fremont Stlevel 12 construction of new non structural paritions, acoustical grid and tile, and gyb bd ceilig light fix, millwork, finishes. fire alarm fire spr, stairs under sep permit. maher n/a.$1,400,000
May 10, 2018Completed181 Fremont StGolden State Fire Safety/Dba:Gs Fire Sinstall 2 ea ansul kitchen fire system total of 9 tanks. n/a for maher.$6,000
May 8, 2018Completed181 Fremont St11th fl - construction of new non-structural partitions, accoustical grid and tile and gyp board ceilings, light fixtures, millwork and finishes. fire alarm and sprinkler under a separate permit$5,078,680
May 8, 2018Completed181 Fremont StLevel 10 Construction Lp10th fl - construction of new non-structural partitions, acoustical grid and tile and gyp board ceilings, light fixtures, millwork and finish. fire alarm and sprinkler under a separate permit. maher n/a.$3,863,014
May 7, 2018Completed181 Fremont StLevel 10 Construction Lp8/f: construction of new non-structural partitions, acoustical grid and tile and gyp board ceilings, light fixtures, millwork, and finishes. fire alarm and sprinklers under a seperate permit.$2,500,000
May 7, 2018Completed181 Fremont StLevel 10 Construction Lpinstallation of 4 levels of convenience stairs floor 35 thru 38. two hour enclosure at level 35$3,788,000
Apr 27, 2018Completed181 Fremont StLevel 10 Construction Lplevel 7 - egress sheet updated to include card readers and door tags. new sheet added to show card reader matrix ref 201812015329 maher na
Apr 27, 2018Completed181 Fremont StLevel 10 Construction Lplevel 26 - egress sheet updated to include card readers and door tags. new sheet added to show card reader matrix ref 201804075825 maher na
Apr 27, 2018Completed181 Fremont StLevel 10 Construction Lplevel 4 - egress sheet updated to include card readers and door tags. new sheet added to show card reader matrix ref 20804105993 maher na
Apr 27, 2018Completed181 Fremont StLevel 10 Construction Lplevel 25 - egress sheet updated to include card readers and door tags. new sheet added to show card reader matrix ref maher na
Apr 27, 2018Completed181 Fremont StLevel 10 Construction Lplevel 1 - egress sheet updated to include card readers and door tags. new sheet added to show card reader matrix ref 201812015327 maher na
Apr 27, 2018Completed181 Fremont StLevel 10 Construction Lplevel 28 - egress sheet updated to include card readers and door tags. new sheet added to show card reader matrix ref 201804095827 maher na
Apr 27, 2018Completed181 Fremont StLevel 10 Construction Lplevel 27 - egress sheet updated to include card readers and door tags. new sheet added to show card reader matrix ref 201804106004 maher na
Apr 25, 2018Completed181 Fremont StAllied Fire Protection25th floor - add 45 ssp pendent fire sprinklers, add 7 ws sprinklers, add 18 ssu upright sprinklers, relocaate 9 sso sprinkers maher na$45,000
Apr 25, 2018Completed181 Fremont StAllied Fire Protection26th fl: add 39 fire sprinklers; relocate 2 fire sprinklers.$18,100
Apr 19, 2018Completed181 Fremont StLevel 10 Construction Lpinstallation of convincence stairs from level 13 to level 15$475,000
Apr 18, 2018Expired or cancelled181 Fremont StAllied Fire Protection26 - fire sprinker 39 added, 2 relocated ref 201711073351 maher na$21,000
Apr 18, 2018Completed181 Fremont StAllied Fire Protection31 - fire sprinker 24 added, 5 relocated ref 201801310022 maher na$15,000
Apr 18, 2018Expired or cancelled181 Fremont StAllied Fire Protection25 - fire sprinker 89 added, 6 relocated ref 201711073346 maher na$48,950
Apr 16, 2018Completed181 Fremont StLevel 10 Construction Lp31st flr - revision to 201801310022 updated smoke control system. revision to finishes, mens core restroom to remain as urinal per base bld. added card readers added details maher na$1,000
Apr 16, 2018Completed181 Fremont StLevel 10 Construction Lp29th flr - revision to 201801310020 card readers added, added details, mens urinal to remain as is maher na$1,000
Apr 16, 2018Completed181 Fremont StPacific Auxiliary Fire Alarm30th fl. ref pa 2018-0131-0021 full floor ti to notifier nps2-3030. 3 smoke detector, 16 duct smoke detectors, 8 relay modules, 6 monitor modules, 3 speakers, and 27 speaker strobe are being added. 3 speaker strobes are being relocated. internal stairwell will be installed connecting levels 29-31.$35,000
Apr 16, 2018Completed181 Fremont StLevel 10 Construction Lprevision to pa 2018-0131-0021 updated smoke control system note, revision to finishes, men's urinal per base bldg, add card readers, revised lighting at elevator lobby, revised details$1,000
Apr 16, 2018Completed181 Fremont StPacific Auxiliary Fire Alarm29 - arch & mep ref pa 2018-0131-0020 - full fl ti to notifire nfs2-30300 3 smoke detectors, 15 duct detector, 6 relay modules, 6 monitor modules, 1 isolator module, 4 speaker & 21 speaker strobes are being added, 3 speaker/strobe are being relocated. internal stairwell is being installed connecting$34,000
Apr 16, 2018Completed181 Fremont StPacific Auxiliary Fire Alarm31st fl - arch & mep permit 2018-0131-0022 this is a full ti to a notifire nfs2-3030. 3 smoke detectors, 15 duct smoke detectors, 8 relay modules, 7 monitor modules, 5 speaker and 18 speaker strobes are being added. 3 speaker strobe are being relocated. an internal stairwell is being installed$34,000
Apr 16, 2018Completed181 Fremont StLevel 10 Construction Lpti revision to pa 2017-1201-5329 updated smoke control enlarged pre app meeting minutes, updated green bldg checklist, move drinking fountains, revised minor changes in room layout, add 2 hour rated enclosure in stair vestibule, approve assembly occupancy load$10,000
Apr 16, 2018Completed181 Fremont StPacific Auxiliary Fire Alarm25th fl arch & mep ref pa 201711073346 full floor ti to notifire nfs2-3030. 5 smoke detector, 9 duct smoke detectors, 13 relay modules, 6 monitor modules, 3 speakers and 27 speaker strobe are being added. 2 sprinkler strobe are being added$34,000
Apr 13, 2018Completed181 Fremont StLevel 10 Construction Lpadministrative permit only to correct dwelling unit count; this permit is to correct/updte dwelling unit count from 74 to 67 as recognized in boxes 9 and 9a of this application; no work will be peformed under this permit; reference approved permits 201404163418s - altered site permit page a.007 to o
Apr 12, 2018Completed181 Fremont StLevel 10 Construction Lp5th flr - revisiont o 201712156629 update smoke control system note & green bld checklist for leep project. revise layout of mdf pic action closet. add transformer closet add exhaust shaft. pic action sprinkler system on sep permit
Apr 12, 2018Completed181 Fremont StLevel 10 Construction Lp39th flr - installation of fire pits revision to 201305015894 s8 residential addenda. maher na$10,000
Apr 12, 2018Never finaled181 Fremont StAllied Fire Protection1st flr - 1 added fire sprinklers ref 201712015327 maher na$1,000
Apr 12, 2018Completed181 Fremont StLevel 10 Construction Lp4th flr - revision to power layout & circuiting for bld maintenance - residential management & bld engineering shop maher na$6,000
Apr 10, 2018Completed181 Fremont StLevel 10 Construction Lp23rd floor revision to pa 2017-1215-6634(33rd floor) updated smoke control system notes & green building checklist for leed projects. add card reader locations and transformer closet. mep to coordinate with architectural changes; n/a maher$1,000
Apr 10, 2018Completed181 Fremont StLevel 10 Construction Lp24th floor: revision to pa 2017-1215-6635 update smoke control system notes & green building checklist for leed projects. revise location of idf room. mep to coordinate with architectural changes; n/a maher$1,000
Apr 10, 2018Completed181 Fremont StLevel 10 Construction Lprevision to pa 2017-1107-3338 27th fl - update smoke control system not & green building checklist for leed projects. revision to finish descriptions. men's stall at core restroom to remain. add card reader locations. additional details for finishes. mep to coordinate with architectural changes$1,000
Apr 10, 2018Completed181 Fremont StLevel 10 Construction Lprevision ro 201712065692. updated smoke control report, enlarged text of pre app minutes, green building form, updated revisions to finish descriptions, revisions to security control and av rooms maher na
Apr 9, 2018Completed181 Fremont StLevel 10 Construction Lprevision to t.i permit 201711073382 - updated smoke control report, updated green building checklist, revision to finish descriptions, bse building mens urinal to remain
Apr 9, 2018Completed181 Fremont StAllied Fire Protection4th floor: 5 added fire sprinklers. ref app#201712065692. n/a for maher$2,600
Apr 9, 2018Completed181 Fremont StLevel 10 Construction Lprevision to t.i permit 201711073351 - updated smoke control report, updated green building checklist, revision to finish descriptions, bse building mens urinal to remain
Apr 4, 2018Completed181 Fremont StAllied Fire Protectionadd 36 fire sprinklers at new ceiling and new construction at floor 29 ref pa 2018-0131-0020$18,300
Apr 4, 2018Completed181 Fremont StAllied Fire Protectionrelocate 6 fire sprinklers and add 58 sprinklers at 30th floor to accomodate new tenant work. ref pa 2018-0131-0021$30,800
Mar 30, 2018Never finaled181 Fremont Ststreet space
Mar 28, 2018Completed181 Fremont StIntelligent Technologies & Services Incprovide for pre-action detection (4 smokes) & notification (1 bell) 5th fl. preaction and fire alarm separate permits-$8,000