How long do bathroom remodel permits take in San Francisco's Potrero Hill neighborhood?

In the Potrero Hill neighborhood of San Francisco, of the 60 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 40 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 138 days of being issued, down from 247 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sPotrero Hill neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/potrero-hill/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202660 issued075 issued0
Permit issued to final sign-offOctober 2023 through September 202440 finished13858 finished247

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q43000too recent
2026-Q322170710too recent
2026-Q2201402840too recent
2026-Q1211901313661440too recent
2025-Q412100245972060too recent
2025-Q32222018161203000too recent
2025-Q216166184111973670too recent
2025-Q130251112171122810too recent
2024-Q412120176101222860too recent
2024-Q32121199972580yes
2024-Q21212030101313310yes
2024-Q1131206112996220yes
2023-Q412115113101462800yes
2023-Q31110816983585702yes
2023-Q224226264203068051yes
2023-Q119193166141526463yes
2022-Q421194137162507263yes
2022-Q3242406201533853yes
2022-Q216160222121222282yes
2022-Q118177514152306021yes
2021-Q433291103231996065yes
2021-Q316146190102104342yes
2021-Q226230183171814035yes
2021-Q1181822360132006914yes
2020-Q434300276282301,1323yes
2020-Q32119038141355116yes
2020-Q2774110461103541yes
2020-Q121180269161725261yes
2019-Q428272225221864216yes
2019-Q3232042367183105863yes
2019-Q228244173241866701yes
2019-Q1161401121602492yes
2018-Q42121258171454713yes
2018-Q325242278211601,1951yes
2018-Q229273287222221,0874yes
2018-Q131312227192928317yes
2017-Q418184219112116586yes
2017-Q323200101162627792yes
2017-Q219162250112344554yes
2017-Q124225581183029152yes
2016-Q418151913893006654yes
2016-Q326244315162055386yes
2016-Q220170470153351,7201yes
2016-Q123190273161141,2804yes
2015-Q42120054163648724yes
2015-Q321202143131514924yes
2015-Q22422056202421,1581yes
2015-Q1242340282171586971yes
2014-Q424242516202571,7414yes
2014-Q32929493242291,1245yes
2014-Q220199154162236332yes
2014-Q116152104111181,1532yes
2013-Q415153467141289501yes
2013-Q31919031152076202yes
2013-Q22322058181124043yes
2013-Q12020656181254810yes
2012-Q423210223141864666yes
2012-Q319181252121785054yes
2012-Q21515031131003511yes
2012-Q11514039131325671yes
2011-Q41919128141685944yes
2011-Q317164156143398611yes
2011-Q218170102161035341yes
2011-Q11919021161924162yes
2010-Q4111110229112691,3530yes
2010-Q320195277141142884yes
2010-Q217170279152094862yes
2010-Q1161464013957770yes
2009-Q417151348111717624yes
2009-Q316140106121262752yes
2009-Q299016461584322yes
2009-Q11413096121482811yes
2008-Q41090781601830yes
2008-Q315140391874873yes
2008-Q2101034681343050yes
2008-Q197013951603151yes
2007-Q41290533yes
2007-Q31919012121333374yes
2007-Q21616023081707462yes
2007-Q110100597982711yes
2006-Q4880061692280yes
2006-Q310100927993260yes
2006-Q21212032782102720yes
2006-Q116160711871611yes
2005-Q41212033172975252yes
2005-Q3990071444490yes
2005-Q24430yes
2005-Q11090081784591yes
2004-Q41010043781226060yes
2004-Q3750022yes
2004-Q2141405891885903yes
2004-Q188029651753592yes
2003-Q49903115664122yes
2003-Q399010452894181yes
2003-Q212120271404653yes
2003-Q16613446430yes
2002-Q44410yes
2002-Q312110052473530yes
2002-Q216150260102283382yes
2002-Q188024971962910yes
2001-Q4111102751904081yes
2001-Q35410yes
2001-Q21111025971332450yes
2001-Q166013440yes
2000-Q477041121yes
2000-Q39805520yes
2000-Q29903751235610yes
2000-Q1771215940yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

197 of the 1,780 bathroom remodel permits filed since 2000 (11%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Potrero Hill neighborhood

Shown apart, with their own page here: bathroom remodel (1,780 filed, 1,238 finished; contractors); kitchen remodel (1,479 filed, 1,013 finished; contractors); stairs (1,133 filed, 718 finished; contractors); deck (754 filed, 510 finished; contractors); roof deck (191 filed, 118 finished; contractors). Other types: 12,029 permits. All permits in San Francisco's Potrero Hill neighborhood

Nearby neighborhoods

Mission Bay, Mission, South of Market; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.