How long do roof deck permits take in San Francisco's Noe Valley neighborhood?

In the Noe Valley neighborhood of San Francisco, of the 11 roof deck permits filed from October 2025 through September 2026 that have been issued, half were issued within 58 days, up from 55 days a year earlier. Of the 10 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 208 days of being issued, down from 280 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long roof deck permits take in San Francisco's Noe ValleyneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge02004006008002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/noe-valley/roof-deck · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202611 issued589 issued55
Permit issued to final sign-offOctober 2023 through September 202410 finished2085 finished280

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 32 days to issue and 250 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q36300too recent
2026-Q25310too recent
2026-Q12200too recent
2025-Q44300too recent
2025-Q34300too recent
2025-Q22210too recent
2025-Q13200too recent
2024-Q42210too recent
2024-Q3556712830yes
2024-Q21110yes
2024-Q14440yes
2023-Q42220yes
2023-Q32210yes
2023-Q23211yes
2023-Q13201yes
2022-Q47657496831yes
2022-Q33220yes
2022-Q26543872331yes
2022-Q13111yes
2021-Q44322yes
2021-Q37727084656671,0140yes
2021-Q2666981,33431yes
2021-Q14321yes
2020-Q45320yes
2020-Q38752980642yes
2020-Q21101yes
2020-Q15331yes
2019-Q47634153641yes
2019-Q3774981,92941yes
2019-Q25431yes
2019-Q13320yes
2018-Q44431yes
2018-Q3554192140yes
2018-Q26646880441yes
2018-Q12220yes
2017-Q476551,70652094030yes
2017-Q34431yes
2017-Q22220yes
2017-Q13211yes
2016-Q4661781,07052971,0771yes
2016-Q36412yes
2016-Q23311yes
2016-Q14331yes
2015-Q47539083141yes
2015-Q37646868857501,7851yes
2015-Q2754294032yes
2015-Q1551035232yes
2014-Q42210yes
2014-Q310103841,12384486811yes
2014-Q210931559064948092yes
2014-Q1551726653425360yes
2013-Q49829561557451,1321yes
2013-Q38611662341yes
2013-Q25514347240yes
2013-Q1883023673227571yes
2012-Q49818442873348660yes
2012-Q32220yes
2012-Q25431yes
2012-Q13330yes
2011-Q43330yes
2011-Q32220yes
2011-Q22220yes
2010-Q45517535440yes
2010-Q3773620762143981yes
2010-Q26603506802900yes
2010-Q14440yes
2009-Q43321yes
2009-Q33110yes
2009-Q24430yes
2009-Q12100yes
2008-Q43220yes
2008-Q32211yes
2008-Q1771325362284200yes
2007-Q46431yes
2007-Q31100yes
2007-Q23220yes
2007-Q14431yes
2006-Q455027313yes
2006-Q33210yes
2006-Q23320yes
2005-Q42200yes
2005-Q2559735740yes
2004-Q42101yes
2004-Q35518260240yes
2004-Q11110yes
2003-Q43220yes
2003-Q32220yes
2003-Q22211yes
2002-Q41110yes
2002-Q33320yes
2002-Q23301yes
2001-Q42210yes
2001-Q32220yes
2001-Q21101yes
2001-Q12200yes
2000-Q42210yes
2000-Q32200yes
2000-Q23320yes
2000-Q11100yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

50 of the 405 roof deck permits filed since 2000 (12%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Noe Valley neighborhood

Shown apart, with their own page here: bathroom remodel (4,669 filed, 3,402 finished; contractors); kitchen remodel (3,842 filed, 2,770 finished; contractors); stairs (2,707 filed, 1,804 finished; contractors); deck (1,767 filed, 1,161 finished; contractors); roof deck (405 filed, 239 finished; contractors). Other types: 22,798 permits. All permits in San Francisco's Noe Valley neighborhood

Nearby neighborhoods

Glen Park, Twin Peaks, Castro/Upper Market; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.