How long do kitchen remodel permits take in San Francisco's Noe Valley neighborhood?

In the Noe Valley neighborhood of San Francisco, of the 108 kitchen remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, down from 1 day a year earlier. Of the 89 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 189 days of being issued, up from 169 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long kitchen remodel permits take in San Francisco's NoeValley neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/noe-valley/kitchen · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026108 issued0153 issued1
Permit issued to final sign-offOctober 2023 through September 202489 finished189120 finished169

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 176 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q44000too recent
2026-Q327150800too recent
2026-Q2433202271331430too recent
2026-Q1302809916781590too recent
2025-Q435333108191472530too recent
2025-Q33636064231293090too recent
2025-Q24746158341993480too recent
2025-Q13734662201803130too recent
2024-Q437370104311003860too recent
2024-Q34039126312114350yes
2024-Q226250108171814000yes
2024-Q12121049202685380yes
2023-Q429290134211684891yes
2023-Q334320207271354584yes
2023-Q244431300371603943yes
2023-Q13534042251513597yes
2022-Q444406108312804879yes
2022-Q336329139261765147yes
2022-Q231300333263228225yes
2022-Q13534082272134715yes
2021-Q429290222222507527yes
2021-Q3292618542223308103yes
2021-Q234310159252567552yes
2021-Q143390213352445595yes
2020-Q442410189292631,0279yes
2020-Q344431200322069967yes
2020-Q212103587995682yes
2020-Q138375435322795463yes
2019-Q447469388353017187yes
2019-Q337364192323047892yes
2019-Q24040096361767084yes
2019-Q13330038252667233yes
2018-Q448455374392731,1705yes
2018-Q32626054232045032yes
2018-Q247450123392188235yes
2018-Q130302513231841,0356yes
2017-Q428270683212096194yes
2017-Q345430210362439385yes
2017-Q248450122382586143yes
2017-Q12524031192145803yes
2016-Q447450294362047445yes
2016-Q341382553331937094yes
2016-Q250460156411744231yes
2016-Q153492347422037536yes
2015-Q4454122202921875410yes
2015-Q346411530282041,03711yes
2015-Q254510241382471,1429yes
2015-Q1464601233225559610yes
2014-Q443420445271921,19511yes
2014-Q340390322271667678yes
2014-Q25552056441166717yes
2014-Q1434302153016353811yes
2013-Q4515010457372951,2727yes
2013-Q347460270391787916yes
2013-Q245440302371455074yes
2013-Q140405165322426685yes
2012-Q442406207342064124yes
2012-Q33736052331554572yes
2012-Q23736034301704434yes
2012-Q134330149301684290yes
2011-Q42827070242105192yes
2011-Q3343404231927072yes
2011-Q23838062351356261yes
2011-Q141401102371343841yes
2010-Q431300176271795573yes
2010-Q334331105271046455yes
2010-Q235351133341803500yes
2010-Q127270188231514391yes
2009-Q431301128262066512yes
2009-Q33030060241284874yes
2009-Q23232010301323560yes
2009-Q1353402424984283yes
2008-Q427260160182086713yes
2008-Q3363606291093731yes
2008-Q25453030381323494yes
2008-Q135340141231535694yes
2007-Q44039014282083732yes
2007-Q34848017321705153yes
2007-Q237370154221023302yes
2007-Q138380266271374567yes
2006-Q420200243122024413yes
2006-Q335340158251415502yes
2006-Q2414000271537227yes
2006-Q1333300291462992yes
2005-Q439390278251554287yes
2005-Q342420214261703619yes
2005-Q232310456231694737yes
2005-Q133330310201333245yes
2004-Q4252500112474056yes
2004-Q34040058341785933yes
2004-Q2282800191812344yes
2004-Q12827026162104617yes
2003-Q430300131191421,1427yes
2003-Q32222038121772725yes
2003-Q22928049181615625yes
2003-Q1333300171887886yes
2002-Q4282702172363625yes
2002-Q331310167173491,0327yes
2002-Q2313000161453707yes
2002-Q1212002141462461yes
2001-Q4171609181362302yes
2001-Q3313100221082400yes
2001-Q224230150181464471yes
2001-Q1171702091472581yes
2000-Q418180491964861yes
2000-Q3414000211352520yes
2000-Q23232049191764430yes
2000-Q13837056211523720yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

413 of the 3,842 kitchen remodel permits filed since 2000 (11%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Noe Valley neighborhood

Shown apart, with their own page here: bathroom remodel (4,669 filed, 3,402 finished; contractors); kitchen remodel (3,842 filed, 2,770 finished; contractors); stairs (2,707 filed, 1,804 finished; contractors); deck (1,767 filed, 1,161 finished; contractors); roof deck (405 filed, 239 finished; contractors). Other types: 22,798 permits. All permits in San Francisco's Noe Valley neighborhood

Nearby neighborhoods

Glen Park, Twin Peaks, Castro/Upper Market; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.