Permit GraphShortlistSan Francisco building permits since 2000

How long do bathroom remodel permits take in San Francisco's Noe Valley neighborhood?

In the Noe Valley neighborhood of San Francisco, of the 173 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 119 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 188 days of being issued, up from 169 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco's NoeValley neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/noe-valley/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026173 issued0193 issued0
Permit issued to final sign-offOctober 2023 through September 2024119 finished188137 finished169

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41000too recent
2026-Q341260910too recent
2026-Q25849071171061410too recent
2026-Q1494705025761610too recent
2025-Q45651290351512540too recent
2025-Q35251090331643210too recent
2025-Q26867195501763460too recent
2025-Q144393125241583310too recent
2024-Q437360139281764130too recent
2024-Q34039158302043850yes
2024-Q240380121311393800yes
2024-Q13838039322685420yes
2023-Q4353410137262465620yes
2023-Q34239067361554645yes
2023-Q237362120321604622yes
2023-Q14138046301613967yes
2022-Q4544928480392805147yes
2022-Q3453914110331914737yes
2022-Q254530451461867168yes
2022-Q13936482291985486yes
2021-Q443410315312057569yes
2021-Q349456546362286018yes
2021-Q242390815282458627yes
2021-Q1605502524330856511yes
2020-Q454490190422751,0168yes
2020-Q358521272402009447yes
2020-Q2181766012832154yes
2020-Q144423475342335356yes
2019-Q463617389493017949yes
2019-Q348483389411908373yes
2019-Q260540118501345725yes
2019-Q149461154401617684yes
2018-Q456524349462621,1006yes
2018-Q338370257311675335yes
2018-Q252510253442017465yes
2018-Q149471415401811,0646yes
2017-Q447426634342407437yes
2017-Q35651187392701,3128yes
2017-Q248432397361825544yes
2017-Q130297247232595793yes
2016-Q452491297382027117yes
2016-Q3504713773525275412yes
2016-Q266580237492277116yes
2016-Q1827505046424584711yes
2015-Q4514813551362468208yes
2015-Q3575465443822497214yes
2015-Q261583163481621,0247yes
2015-Q156551125451115028yes
2014-Q465611457443041,21212yes
2014-Q340382326312157695yes
2014-Q260584365492007467yes
2014-Q149480239372006018yes
2013-Q4636310405502561,2428yes
2013-Q355540272481887275yes
2013-Q254535372451765134yes
2013-Q1505052103323153314yes
2012-Q443437238372105555yes
2012-Q35756090481553775yes
2012-Q255510195461536094yes
2012-Q141400261371874872yes
2011-Q439371225352115522yes
2011-Q3505001847803493yes
2011-Q25655030491446192yes
2011-Q142402114371653843yes
2010-Q439361166321655543yes
2010-Q342412109341906485yes
2010-Q249490104461343520yes
2010-Q135333168282304732yes
2009-Q44847137382227682yes
2009-Q34138125321854452yes
2009-Q240391176351984101yes
2009-Q1323003024984790yes
2008-Q436340208272166242yes
2008-Q335330108261225341yes
2008-Q25151012401303625yes
2008-Q143400217281906223yes
2007-Q45452068312094494yes
2007-Q35453019371283625yes
2007-Q241400179242584254yes
2007-Q151490267351405627yes
2006-Q437350147211814495yes
2006-Q344430300261764763yes
2006-Q236350154311794751yes
2006-Q1363600301522803yes
2005-Q438370390252424974yes
2005-Q3353500211644057yes
2005-Q2383802322416845110yes
2005-Q133320358231563381yes
2004-Q43533069201864065yes
2004-Q341410118271453765yes
2004-Q22119023141482951yes
2004-Q13433015201623398yes
2003-Q430300177211463046yes
2003-Q332320179192244347yes
2003-Q233320332191825698yes
2003-Q1212100121063813yes
2002-Q426260312171974925yes
2002-Q333320165181527418yes
2002-Q230290137161783157yes
2002-Q12523090201592302yes
2001-Q4131305471182790yes
2001-Q32323057121953300yes
2001-Q231280283181484801yes
2001-Q12524098171342172yes
2000-Q423230115162324850yes
2000-Q31818079141503890yes
2000-Q227240177151533370yes
2000-Q131310111202326020yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

477 of the 4,669 bathroom remodel permits filed since 2000 (10%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Noe Valley neighborhood

Shown apart, with their own page here: bathroom remodel (4,669 filed, 3,402 finished; contractors); kitchen remodel (3,842 filed, 2,770 finished; contractors); stairs (2,707 filed, 1,804 finished; contractors); deck (1,767 filed, 1,161 finished; contractors); roof deck (405 filed, 239 finished; contractors). Other types: 22,798 permits. All permits in San Francisco's Noe Valley neighborhood

Nearby neighborhoods

Glen Park, Twin Peaks, Castro/Upper Market; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.