- Last 24 months
- 7 permits filed
24 permits since 2000: 12 completed, 5 in progress, 6 never finaled, 1 expired or cancelled.
Of the 6 never-finaled permits, 3 are 3 to 5 years old, 3 are 5 to 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Feb 13, 2026 | In progress issued May 2026 | 685 07th St | replace 1) 25 ton & 1) 30 ton gas/electric package unit with new heat pump with same tonageDetails
replace 1) 25 ton & 1) 30 ton gas/electric package unit with new heat pump with same tonage | $302,000 |
| Dec 4, 2025 | In progress issued Dec 2025 | 750 Van Ness Av | to obtain final inspection for work approved under pa# 202411134890. all work is complete.Details
to obtain final inspection for work approved under pa# 202411134890. all work is complete. | |
| Jun 4, 2025 | Completed final sign-off Nov 2025 | 685 07th St | replace 1 25 ton gas/electric package unit with 1 22.5-ton heat pumpDetails
replace 1 25 ton gas/electric package unit with 1 22.5-ton heat pump | $143,000 |
| May 13, 2025 | In progress issued Jun 2025 | 1500 Owens St | remove 2 chillers ch-11-ch-2 on the roof and replace with 2 new chillers like for likeDetails
remove 2 chillers ch-11-ch-2 on the roof and replace with 2 new chillers like for like | $127,583 |
| Nov 13, 2024 | In progress issued Nov 2024 | 750 Van Ness Av | mechanical roof-replace 1 makeup air unit and 2 duct furnacesDetails
mechanical roof-replace 1 makeup air unit and 2 duct furnaces | $65,000 |
| Nov 13, 2024 | In progress issued Nov 2024 | 650 Turk St | mechanical roof replace four rooftop exhaust fans units like for like. repalce 2 gas ducts furnace mua units with newDetails
mechanical roof replace four rooftop exhaust fans units like for like. repalce 2 gas ducts furnace mua units with new | $101,000 |
| Oct 18, 2024 | Completed final sign-off Oct 2025 | 743 Washington St | 1st flr: hvac. 1) provide and install 2 new ducted fan coil units including associated ductwork, registers, and accessories. roof: 1) provde install two new condensing units and accessories. 2) provide and install new ac unit for basement, like for like replacement. mech piping: 1st flr: installDetails
1st flr: hvac. 1) provide and install 2 new ducted fan coil units including associated ductwork, registers, and accessories. roof: 1) provde install two new condensing units and accessories. 2) provide and install new ac unit for basement, like for like replacement. mech piping: 1st flr: install | $114,171 |
| Jul 17, 2024 | Completed final sign-off Jan 2025 | 499 Illinois St | seismic bracing of in-row cooling units & server racks @ 2nd floor of chan zuckerberg biohubDetails
seismic bracing of in-row cooling units & server racks @ 2nd floor of chan zuckerberg biohub | $10,000 |
| Aug 29, 2023 | Completed final sign-off Nov 2024 | 499 Illinois St | demo (1) 45 ton air cooled chiller, (2) 3hp chilled water pumps. install(2) 60 ton air cooled chillers, 3 chilled water pumps and new electrical service for 2nd chiller & reconnect extg utilities where applicableDetails
demo (1) 45 ton air cooled chiller, (2) 3hp chilled water pumps. install(2) 60 ton air cooled chillers, 3 chilled water pumps and new electrical service for 2nd chiller & reconnect extg utilities where applicable | $300,000 |
| Jan 13, 2023 | Never finaled issued Jan 2023, no final | 1661 Pine St | install (1) new in-line ventilation fan, (2) intake ducts and grilles inlet louver, tabb balance ref pa# 2022-0331-1320Details
install (1) new in-line ventilation fan, (2) intake ducts and grilles inlet louver, tabb balance ref pa# 2022-0331-1320 | $21,000 |
| Jan 13, 2023 | Expired or cancelled withdrawn May 2023 | 855 Geary St | install 2 water closets, 1 lavatory 1 break room sink, 1 restroom on-demand water heater, 1 flr cleanout, 1 weil duplex sump pump w/ fiber glass basin, 1 trench drain.Details
install 2 water closets, 1 lavatory 1 break room sink, 1 restroom on-demand water heater, 1 flr cleanout, 1 weil duplex sump pump w/ fiber glass basin, 1 trench drain. | $187,000 |
| Sep 27, 2022 | Never finaled issued Sep 2022, no final | 1500 Owens St | remove and replace boiler b-2 in boiler room in-kind on roof.Details
remove and replace boiler b-2 in boiler room in-kind on roof. | $116,623 |
| Jun 22, 2022 | Never finaled issued Mar 2023, no final | 1700 Owens St | provide & install 2 cda compressors, 1 air dryer & 1 air tank on roof. provide & install 1 nitrogen generator on 2nd fl mechancial room. relocate (e) dryer in mechanical room.Details
provide & install 2 cda compressors, 1 air dryer & 1 air tank on roof. provide & install 1 nitrogen generator on 2nd fl mechancial room. relocate (e) dryer in mechanical room. | $82,750 |
| Feb 2, 2022 | Completed final sign-off Jun 2022 | 455 Mission Bay Blvd South | remove and replace air compressor and storage tank.Details
remove and replace air compressor and storage tank. | $94,000 |
| Aug 20, 2021 | Never finaled issued Aug 2021, no final | 1387 Valencia St | demo (e) ductwork & gas furnaces, provide & install (n) ductwork, registers & heat pump units to replace existing. fire alarm/sprinklers under sep permits.Details
demo (e) ductwork & gas furnaces, provide & install (n) ductwork, registers & heat pump units to replace existing. fire alarm/sprinklers under sep permits. | $92,801 |
| Jun 25, 2021 | Completed final sign-off Dec 2021 | 1725 03rd St | remove 4 heat pumps and replace with 5 fan coil units and 2 water condensing jDetails
remove 4 heat pumps and replace with 5 fan coil units and 2 water condensing j | $222,000 |
| Jun 21, 2021 | Completed final sign-off Dec 2021 | 1655 03rd St | main: demo 4 existing trane water source heat pumps. provide and install new daikan vrv including 5 fan coil units. 2 water cooled condensing unitsDetails
main: demo 4 existing trane water source heat pumps. provide and install new daikan vrv including 5 fan coil units. 2 water cooled condensing units | $222,000 |
| Mar 22, 2021 | Completed final sign-off Nov 2021 | 455 Mission Bay Blvd South | provide and install new 70 ton chiller.Details
provide and install new 70 ton chiller. | $149,037 |
| Feb 6, 2020 | Never finaled issued Feb 2020, no final | 2101 Fulton St | remove and replace 3 ac units, like for like. same location and same weight.Details
remove and replace 3 ac units, like for like. same location and same weight. | $340,000 |
| Aug 14, 2019 | Completed final sign-off Nov 2019 | 2130 Fulton St | install 6 additional chilled water, heating hot water, fan coils. ref pa 201906123231Details
install 6 additional chilled water, heating hot water, fan coils. ref pa 201906123231 | $180,000 |
| Jun 5, 2019 | Completed final sign-off Dec 2019 | 2350 Turk Bl | install 1 supply fan, 2 circulating, fans & 1 gas fired unit heater for greenhouse under building permit 2017-0110-6845Details
install 1 supply fan, 2 circulating, fans & 1 gas fired unit heater for greenhouse under building permit 2017-0110-6845 | $8,500 |
| May 24, 2019 | Never finaled issued May 2019, no final | 114 Sansome St | 8/f: install a/c ductless mini-split system.Details
8/f: install a/c ductless mini-split system. | $23,340 |
| Aug 1, 2018 | Completed final sign-off Apr 2019 | 250 King St | roof: remove and replace (1) air handling units on roof top same capacity, same mounting layout at original location.Details
roof: remove and replace (1) air handling units on roof top same capacity, same mounting layout at original location. | $30,000 |
| Aug 1, 2018 | Completed final sign-off Apr 2019 | 260 King St | roof: remove and replace (2) air handling units on roof top same capacity, same mounting layout at original location.Details
roof: remove and replace (2) air handling units on roof top same capacity, same mounting layout at original location. | $60,000 |