Permit GraphSan Francisco building permits since 2000

Block 1190, lot 001

2195 Fulton St

City’s use
Commercial Misc
Built
2000
Stories
4
Rooms
6 bathrooms
Building
63,579 sq ft
Lot
63,938 sq ft
Zoning
RH3
Construction type
D

From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map

Permits filed here

36 permits filed for this property since 2000.

CompletedIn progressNever finaledExpired or cancelled
FiledOutcomeAddressContractorWork described on the permitDeclared cost
Mar 20, 2025In progress
filed Mar 2025, not yet issued
2195 Fulton Stt-mobile - remove (e) cabinet, (3) antennas, (3) rrus & cabling. install (3) ericsson air 6419 b41 antennas, (3) amphenol apxvaall18m-u-j20 antennas, (3) ericsson 4460 rrus, (3) ericsson 4480 rrus, (3) hybrid cables, (1) 200a power panel cabinet w/ cam-lok, (1) e6160 v2 ac cabinet,
Details
Permit
202503202662
Status
filed
Filed
Mar 20, 2025
Declared cost
$50,000
Address
2195 Fulton St

t-mobile - remove (e) cabinet, (3) antennas, (3) rrus & cabling. install (3) ericsson air 6419 b41 antennas, (3) amphenol apxvaall18m-u-j20 antennas, (3) ericsson 4460 rrus, (3) ericsson 4480 rrus, (3) hybrid cables, (1) 200a power panel cabinet w/ cam-lok, (1) e6160 v2 ac cabinet,

Open the permit page

$50,000
Apr 12, 2023Never finaled
issued Apr 2023, no final
2199 Fulton StUos Construction Inc.de-construction of legacy sprint equipment: antennas, tmas, antennas hardware, rrus, telcom cabinets, h-frames, coax cabling
Details
Permit
202304125596
Status
issued
Filed
Apr 12, 2023
Permit issued
Apr 20, 2023
Declared cost
$5,000
Address
2199 Fulton St

de-construction of legacy sprint equipment: antennas, tmas, antennas hardware, rrus, telcom cabinets, h-frames, coax cabling

Open the permit page

$5,000
May 31, 2022Completed
final sign-off Jun 2023
2101 Fulton StFire Alarm System Servicesinstall celllar transmitter to replace pots lines at zief law library.
Details
Permit
202205315251
Status
complete
Filed
May 31, 2022
Permit issued
Jul 26, 2022
Final sign-off
Jun 5, 2023
Declared cost
$4,000
Address
2101 Fulton St

install celllar transmitter to replace pots lines at zief law library.

Open the permit page

$4,000
May 23, 2022Completed
final sign-off Jun 2023
2199 Fulton StFire Alarm System Servicesinstall celllar transmitter to replace pots lines at kendrick
Details
Permit
202205234775
Status
complete
Filed
May 23, 2022
Permit issued
Jul 26, 2022
Final sign-off
Jun 5, 2023
Declared cost
$4,000
Address
2199 Fulton St

install celllar transmitter to replace pots lines at kendrick

Open the permit page

$4,000
Feb 6, 2020Never finaled
issued Feb 2020, no final
2101 Fulton StTherma Llcremove and replace 3 ac units, like for like. same location and same weight.
Details
Permit
202002063695
Status
issued
Filed
Feb 6, 2020
Permit issued
Feb 26, 2020
Declared cost
$340,000
Address
2101 Fulton St

remove and replace 3 ac units, like for like. same location and same weight.

Open the permit page

$340,000
May 30, 2019Expired or cancelled
cancelled Jan 2026
2195 Fulton Stt mobile modification to replace 3 antennas with new and install 3 rrus
Details
Permit
201905302038
Status
cancelled
Filed
May 30, 2019
Declared cost
$25,000
Address
2195 Fulton St

t mobile modification to replace 3 antennas with new and install 3 rrus

Open the permit page

$25,000
Mar 23, 2018Completed
final sign-off Aug 2019
2199 Fulton Stsprint - swap 3 (e) antenna & replace with 3 new antenna add 3 rrus units maher na sapw (3) (e) rrus & replace w/ (3) new rrus.
Details
Permit
201803234503
Status
complete
Filed
Mar 23, 2018
Permit issued
Mar 7, 2019
Final sign-off
Aug 7, 2019
Declared cost
$12,000
Address
2199 Fulton St

sprint - swap 3 (e) antenna & replace with 3 new antenna add 3 rrus units maher na sapw (3) (e) rrus & replace w/ (3) new rrus.

Open the permit page

$12,000
Mar 17, 2014Expired or cancelled
withdrawn Jul 2018
2199 Fulton Stadd new 2.5 ghz equipment inside (e) mmbs cabinet, add (1) string of batteries inside (e) mmbs cabinet. re-use (e) hubrid cabes as needed or install new as needed, add (3) 2.5 ghz antennas & (3) rrh 1 per sector (a, b & c). compliance with ordinance no. 155-13. not required. sprint
Details
Permit
201403170945
Status
withdrawn
Filed
Mar 17, 2014
Declared cost
$30,000
Address
2199 Fulton St

add new 2.5 ghz equipment inside (e) mmbs cabinet, add (1) string of batteries inside (e) mmbs cabinet. re-use (e) hubrid cabes as needed or install new as needed, add (3) 2.5 ghz antennas & (3) rrh 1 per sector (a, b & c). compliance with ordinance no. 155-13. not required. sprint

Open the permit page

$30,000
Sep 4, 2012Expired or cancelled
cancelled Jan 2026
2199 Fulton Stbanner: 7'-6"x26'-0", 25' above sidewalk. mesh fabric, connected at the columns.
Details
Permit
201209048869
Status
cancelled
Filed
Sep 4, 2012
Declared cost
$100
Address
2199 Fulton St

banner: 7'-6"x26'-0", 25' above sidewalk. mesh fabric, connected at the columns.

Open the permit page

$100
Jul 20, 2012Never finaled
issued Jul 2012, no final
2199 Fulton StWestern Roofing Servicereroofing
Details
Permit
201207205363
Status
issued
Filed
Jul 20, 2012
Permit issued
Jul 20, 2012
Declared cost
$370,000
Address
2199 Fulton St

reroofing

Open the permit page

$370,000
Jul 9, 2012Never finaled
issued Jul 2012, no final
2101 Fulton StRcm Fire Protection Inc.1st & 2nd floor-add (27) & relocate (46) sprinkler heads to fit new ceiling configurations for t.i pa# 2012-0604-1776 total: 73 heads
Details
Permit
201207094291
Status
issued
Filed
Jul 9, 2012
Permit issued
Jul 9, 2012
Declared cost
$38,000
Address
2101 Fulton St

1st & 2nd floor-add (27) & relocate (46) sprinkler heads to fit new ceiling configurations for t.i pa# 2012-0604-1776 total: 73 heads

Open the permit page

$38,000
Jun 15, 2012Completed
final sign-off Mar 2015
2199 Fulton StOverland Contracting Incsprint wireless modification. replace 6 (e) antennas with 3 new antennas on (e) roof. replace 3 (e) equipment cabinets with 2 new equipment cabinets on (e) steel beam on roof.
Details
Permit
201206152690
Status
complete
Filed
Jun 15, 2012
Permit issued
Sep 27, 2012
Final sign-off
Mar 12, 2015
Declared cost
$45,000
Address
2199 Fulton St

sprint wireless modification. replace 6 (e) antennas with 3 new antennas on (e) roof. replace 3 (e) equipment cabinets with 2 new equipment cabinets on (e) steel beam on roof.

Open the permit page

$45,000
Jun 8, 2012Never finaled
issued Jun 2012, no final
2101 Fulton Ststreet space permit
Details
Permit
M327007
Status
issued
Filed
Jun 8, 2012
Permit issued
Jun 8, 2012
Address
2101 Fulton St

street space permit

Open the permit page

Jun 4, 2012Completed
final sign-off Aug 2012
2101 Fulton StTurner Construction Colibrary renovations - first & second floor office reconfiguration.mep under separate permit
Details
Permit
201206041776
Status
complete
Filed
Jun 4, 2012
Permit issued
Jun 19, 2012
Final sign-off
Aug 16, 2012
Declared cost
$500,000
Address
2101 Fulton St

library renovations - first & second floor office reconfiguration.mep under separate permit

Open the permit page

$500,000
Feb 24, 2012Never finaled
issued Feb 2012, no final
2199 Fulton Ststreet space & sidewalk permit.
Details
Permit
M304247
Status
issued
Filed
Feb 24, 2012
Permit issued
Feb 24, 2012
Address
2199 Fulton St

street space & sidewalk permit.

Open the permit page

Jan 14, 2010Expired or cancelled
cancelled Jun 2011
2195 Fulton StTransceive Communications Inc.install one new bts equipment cabinet on (e) pad on roof within t-mobile lease area.
Details
Permit
201001144767
Status
cancelled
Filed
Jan 14, 2010
Declared cost
$1,000
Address
2195 Fulton St

install one new bts equipment cabinet on (e) pad on roof within t-mobile lease area.

Open the permit page

$1,000
Jun 4, 2009Completed
final sign-off May 2010
2195 Fulton StTransceive Communications Inc.removal of 3 antennas & 1 bts cabinet from an (e) t-mobile cell site facility, to bring it into planning compliance. revision to application 09720541.
Details
Permit
200906049740
Status
complete
Filed
Jun 4, 2009
Permit issued
Nov 24, 2009
Final sign-off
May 27, 2010
Declared cost
$2,000
Address
2195 Fulton St

removal of 3 antennas & 1 bts cabinet from an (e) t-mobile cell site facility, to bring it into planning compliance. revision to application 09720541.

Open the permit page

$2,000
Sep 7, 2005Expired or cancelled
cancelled Jun 2007
2195 Fulton Stantenna swap on sector c from polar to quad port
Details
Permit
200509072197
Status
cancelled
Filed
Sep 7, 2005
Declared cost
$10,000
Address
2195 Fulton St

antenna swap on sector c from polar to quad port

Open the permit page

$10,000
Jan 7, 2004Completed
final sign-off Jan 2004
2199 Fulton StPlant Constructionrenew expired fire sprinkler permits forfinal inspection: 200202078705,200205317904 & 20035154075
Details
Permit
200401073499
Status
complete
Filed
Jan 7, 2004
Permit issued
Jan 7, 2004
Final sign-off
Jan 23, 2004
Address
2199 Fulton St

renew expired fire sprinkler permits forfinal inspection: 200202078705,200205317904 & 20035154075

Open the permit page

Oct 24, 2003Completed
final sign-off Dec 2003
2199 Fulton StDecker Electric Co Inc Electrical Contrarev. to orig. pa#2002/05/07/5898 - additional firealarm devices as required by sffd
Details
Permit
200310248521
Status
complete
Filed
Oct 24, 2003
Permit issued
Oct 24, 2003
Final sign-off
Dec 11, 2003
Declared cost
$4,000
Address
2199 Fulton St

rev. to orig. pa#2002/05/07/5898 - additional firealarm devices as required by sffd

Open the permit page

$4,000
Aug 20, 2003Completed
final sign-off Dec 2003
2101 Fulton St`
Details
Permit
200308202603
Status
complete
Filed
Aug 20, 2003
Permit issued
Aug 20, 2003
Final sign-off
Dec 3, 2003
Declared cost
$4,000
Address
2101 Fulton St

`

Open the permit page

$4,000
Jul 28, 2003Completed
final sign-off Dec 2003
2199 Fulton Strenew expired permit 200201308103 for final inspection only
Details
Permit
200307280554
Status
complete
Filed
Jul 28, 2003
Permit issued
Jul 28, 2003
Final sign-off
Dec 3, 2003
Address
2199 Fulton St

renew expired permit 200201308103 for final inspection only

Open the permit page

May 15, 2003Expired or cancelled
expired Nov 2003
2199 Fulton StPribuss Engineering Incphase 3 wet std. pipe @ 3rd, 4th & 5th floor
Details
Permit
200305154675
Status
expired
Filed
May 15, 2003
Permit issued
Jun 23, 2003
Declared cost
$4,600
Address
2199 Fulton St

phase 3 wet std. pipe @ 3rd, 4th & 5th floor

Open the permit page

$4,600
Mar 6, 2003Never finaled
issued Mar 2003, no final
2199 Fulton Ststreet space permit
Details
Permit
M23083
Status
issued
Filed
Mar 6, 2003
Permit issued
Mar 6, 2003
Address
2199 Fulton St

street space permit

Open the permit page

Feb 13, 2003Completed
final sign-off Dec 2003
2199 Fulton StPribuss Engineering Incfire sprinkler installation, usf kendrick hall
Details
Permit
200302137356
Status
complete
Filed
Feb 13, 2003
Permit issued
Jun 23, 2003
Final sign-off
Dec 10, 2003
Declared cost
$34,000
Address
2199 Fulton St

fire sprinkler installation, usf kendrick hall

Open the permit page

$34,000
Dec 9, 2002Never finaled
issued Dec 2002, no final
2199 Fulton Ststreet space
Details
Permit
M22393
Status
issued
Filed
Dec 9, 2002
Permit issued
Dec 9, 2002
Address
2199 Fulton St

street space

Open the permit page

Dec 9, 2002Never finaled
issued Dec 2002, no final
2199 Fulton Ststreet space
Details
Permit
M22392
Status
issued
Filed
Dec 9, 2002
Permit issued
Dec 9, 2002
Address
2199 Fulton St

street space

Open the permit page

May 31, 2002Expired or cancelled
expired Nov 2003
2199 Fulton StPribuss Engineering Incfire spkr installation @ kendrick hall 265 heads total
Details
Permit
200205317904
Status
expired
Filed
May 31, 2002
Permit issued
Jun 6, 2002
Declared cost
$41,000
Address
2199 Fulton St

fire spkr installation @ kendrick hall 265 heads total

Open the permit page

$41,000
May 7, 2002Expired or cancelled
expired Jan 2004
2199 Fulton StDecker Electric Co Inc Electrical Contrainstall a (n) fire alarm system to the (e) buildg. include (n) horns, strobes, smoke detectors and
Details
Permit
200205075898
Status
expired
Filed
May 7, 2002
Permit issued
Jun 11, 2002
Declared cost
$20,000
Address
2199 Fulton St

install a (n) fire alarm system to the (e) buildg. include (n) horns, strobes, smoke detectors and

Open the permit page

$20,000
Feb 7, 2002Expired or cancelled
expired Nov 2003
2199 Fulton StPribuss Engineering Incfire sprinkler installation nfpa 13 throughout
Details
Permit
200202078705
Status
expired
Filed
Feb 7, 2002
Permit issued
Mar 15, 2002
Declared cost
$68,000
Address
2199 Fulton St

fire sprinkler installation nfpa 13 throughout

Open the permit page

$68,000
Jan 30, 2002Expired or cancelled
expired Sep 2002
2199 Fulton Stwork under this application is for phase 1 mechanical and lighting
Details
Permit
200201308103
Status
expired
Filed
Jan 30, 2002
Permit issued
May 2, 2002
Address
2199 Fulton St

work under this application is for phase 1 mechanical and lighting

Open the permit page

Jan 30, 2002Completed
final sign-off Jul 2003
2199 Fulton Stthis appication i s for bsm renew only and for assess street space fees/ref #200107274739s
Details
Permit
200201308070
Status
complete
Filed
Jan 30, 2002
Permit issued
Jan 30, 2002
Final sign-off
Jul 16, 2003
Address
2199 Fulton St

this appication i s for bsm renew only and for assess street space fees/ref #200107274739s

Open the permit page

Dec 19, 2001Completed
final sign-off Mar 2002
2199 Fulton Stinterior demolition of (e) wall as indicated on drawings on fls.1-5
Details
Permit
200112195618
Status
complete
Filed
Dec 19, 2001
Permit issued
Dec 19, 2001
Final sign-off
Mar 13, 2002
Declared cost
$50,000
Address
2199 Fulton St

interior demolition of (e) wall as indicated on drawings on fls.1-5

Open the permit page

$50,000
Jul 27, 2001Completed
final sign-off Jan 2004
2199 Fulton Stphase four of alteration to kendrick hall: interior alteration. see attached letter
Details
Permit
200107274739
Status
complete
Filed
Jul 27, 2001
Permit issued
Dec 12, 2001
Final sign-off
Jan 23, 2004
Declared cost
$3,800,000
Address
2199 Fulton St

phase four of alteration to kendrick hall: interior alteration. see attached letter

Open the permit page

$3,800,000
Mar 28, 2000Completed
final sign-off Apr 2001
2101 Fulton StCupertino Electric Inc.sf fire department plan check only-new fire alarm system
Details
Permit
200003285677
Status
complete
Filed
Mar 28, 2000
Permit issued
Mar 28, 2000
Final sign-off
Apr 4, 2001
Declared cost
$50,000
Address
2101 Fulton St

sf fire department plan check only-new fire alarm system

Open the permit page

$50,000
Mar 2, 2000Completed
final sign-off Apr 2001
2101 Fulton StDpw Inc.revision & correction to appl 9917521, change stories of occupancy t0 3, change address to 2101 fult
Details
Permit
200003023283
Status
complete
Filed
Mar 2, 2000
Permit issued
Mar 2, 2000
Final sign-off
Apr 4, 2001
Address
2101 Fulton St

revision & correction to appl 9917521, change stories of occupancy t0 3, change address to 2101 fult

Open the permit page

Find contractors for work like this

Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.

Filter the results