Block 3722, lot 257
125 03rd St
- City’s use
- Commercial Hotel
- Built
- 2005
- Stories
- 20
- Units
- 260
- Rooms
- 268 bathrooms
- Building
- 324,161 sq ft
- Lot
- 33,031 sq ft
- Zoning
- C3O
- Construction type
- NA
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
34 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Oct 6, 2026 | In progress filed Oct 2026, not yet issued | 125 03rd St | construct permanent tent on 4/f to be fire sprinkled and alarmed. new lighting and receptacles for temp event lighting. no change to (e) roof drainage.Details
construct permanent tent on 4/f to be fire sprinkled and alarmed. new lighting and receptacles for temp event lighting. no change to (e) roof drainage. | $4,217,680 | |
| Jun 23, 2026 | In progress issued Jun 2026 | 125 03rd St | Prima Acquire Inc Dba Lahue And Associat | 5th and 6th fl evacuation signs (4)Details
5th and 6th fl evacuation signs (4) | |
| Oct 16, 2025 | Completed final sign-off May 2026 | 125 03rd St | Richlen Construction | revision 202503273212 for (n) storage roomDetails
revision 202503273212 for (n) storage room | $5,000 |
| Oct 2, 2025 | Completed final sign-off Oct 2025 | 125 03rd St | Pioneer Fire Inc. | 6th fl - fire sprinkler add 1 pendent; ref pa 202503273212Details
6th fl - fire sprinkler add 1 pendent; ref pa 202503273212 | $500 |
| Mar 27, 2025 | Completed final sign-off May 2026 | 125 03rd St | Richlen Construction | interior renovation of (e) spa @ 5th & 6th floors.Details
interior renovation of (e) spa @ 5th & 6th floors. | $652,844 |
| Sep 12, 2024 | In progress filed Sep 2024, not yet issued | 125 03rd St | temporary portal and archway for event at st. regis san francisco on september 17-19 2024Details
temporary portal and archway for event at st. regis san francisco on september 17-19 2024 | $12,000 | |
| Apr 10, 2023 | Completed final sign-off Apr 2023 | 125 03rd St | relocate 8, add 1 and delete 3 pendent sprinklers on the 6th fl. t.i. pa# 2022-1101-5632Details
relocate 8, add 1 and delete 3 pendent sprinklers on the 6th fl. t.i. pa# 2022-1101-5632 | $2,500 | |
| Mar 8, 2023 | Never finaled issued Mar 2023, no final | 125 03rd St | Sabah International Incorporated | pool area: demo existing notification devices, provide and install new devices as shown on plans.Details
pool area: demo existing notification devices, provide and install new devices as shown on plans. | $13,640 |
| Nov 1, 2022 | Completed final sign-off Jan 2024 | 125 03rd St | Hathaway Dinwiddie Co. | 6/f: renovation of a natatorium and required accessibility upgrades to the adjacent restroom. installation of a pre-fab pool in (e) vault, plumbing and electrical work as shown.Details
6/f: renovation of a natatorium and required accessibility upgrades to the adjacent restroom. installation of a pre-fab pool in (e) vault, plumbing and electrical work as shown. | $944,425 |
| Jan 13, 2022 | Completed final sign-off Feb 2022 | 125 03rd St | Sabah International Incorporated | revision to pa# 202112154470: revised drawings showing devices not being deleted from the program.Details
revision to pa# 202112154470: revised drawings showing devices not being deleted from the program. | |
| Dec 15, 2021 | Completed final sign-off Feb 2022 | 125 03rd St | Sabah International Incorporated | 1st fl ti # 202106031577 & 202110180649. modify existing fire alarm system. demo (4) dectectors w/ carbon monoxide sensor. add (1) ceiling speaker/strobe.Details
1st fl ti # 202106031577 & 202110180649. modify existing fire alarm system. demo (4) dectectors w/ carbon monoxide sensor. add (1) ceiling speaker/strobe. | $23,510 |
| Nov 8, 2021 | Completed final sign-off Mar 2022 | 125 03rd St | Hathaway Dinwiddie Co. | new evacuation signage at lobby lvel of e hotel. interior renovation approved under 202106031577Details
new evacuation signage at lobby lvel of e hotel. interior renovation approved under 202106031577 | $2,200 |
| Oct 18, 2021 | Completed final sign-off Mar 2022 | 125 03rd St | Hathaway Dinwiddie Construct Co | administrative permit to update/change/correct property address. job card states "ave" instead of "street" ref pa# 202106031577.Details
administrative permit to update/change/correct property address. job card states "ave" instead of "street" ref pa# 202106031577. | |
| Sep 30, 2021 | Completed final sign-off Oct 2021 | 125 03rd St | relocate four 4 pendents through area of tenant improvement. no other work to system. area of work limited to lobby bar. ti 202106031577Details
relocate four 4 pendents through area of tenant improvement. no other work to system. area of work limited to lobby bar. ti 202106031577 | $5,000 | |
| Jun 29, 2021 | Never finaled issued Aug 2021, no final | 689 Mission St | applying for level 9 roof terrace assembly permit. all spaces over 49 occupants require a place of assembly permit. per a recent correction notice from sffd, a place of assembly permit has never been filed even though the space is not new. provided plans include ref.200008309233 to show occupantloadDetails
applying for level 9 roof terrace assembly permit. all spaces over 49 occupants require a place of assembly permit. per a recent correction notice from sffd, a place of assembly permit has never been filed even though the space is not new. provided plans include ref.200008309233 to show occupantload | ||
| Dec 24, 2020 | Completed final sign-off Mar 2022 | 125 03rd St | Hathaway Dinwiddie Co. | barrier removel: accessible passenger drop-off/loading zone & access aisle, accessible entries, modification to accessible parking signage & elevator door jamp signs. widen women's accessible restroom stall. removal of urinal in men's restroom to probide adequate door clearance.Details
barrier removel: accessible passenger drop-off/loading zone & access aisle, accessible entries, modification to accessible parking signage & elevator door jamp signs. widen women's accessible restroom stall. removal of urinal in men's restroom to probide adequate door clearance. | $150,000 |
| Dec 10, 2019 | Never finaled issued Dec 2019, no final | 125 03rd St | streetspace | ||
| Oct 29, 2019 | Completed final sign-off Feb 2020 | 125 03rd St | Continental Contractors Inc | unit 1102. barrier removal at guestroom including new finishes, plumbing fixtures, and flooringDetails
unit 1102. barrier removal at guestroom including new finishes, plumbing fixtures, and flooring | $20,776 |
| Jun 13, 2019 | Completed final sign-off Feb 2024 | 125 03rd St | Waterworks Industries Incorporated | demo and removal of pool lining, tile at lower wall coursing and ledge tile finishDetails
demo and removal of pool lining, tile at lower wall coursing and ledge tile finish | $18,235 |
| Feb 19, 2019 | Never finaled issued Feb 2019, no final | 125 03rd St | street space | ||
| Jun 18, 2018 | Never finaled issued Jun 2018, no final | 125 03rd St | temporary tent structure/ tent size 60w x 60d. 22'-9.5 h// this has been approved in the past, the historical building next door has prompted this approval with dbi prior to getting the temp membrane and occupancy(seperate permit) with 698 2nd street at sffd hq.Details
temporary tent structure/ tent size 60w x 60d. 22'-9.5 h// this has been approved in the past, the historical building next door has prompted this approval with dbi prior to getting the temp membrane and occupancy(seperate permit) with 698 2nd street at sffd hq. | $10,000 | |
| Jan 12, 2017 | Completed final sign-off May 2017 | 125 03rd St | Marchetti Group | to obtain final inspection for work approved under pa#2014-10-09-8487. all work is complete.Details
to obtain final inspection for work approved under pa#2014-10-09-8487. all work is complete. | |
| Jan 14, 2016 | Expired or cancelled cancelled Jan 2026 | 125 03rd St | Sabah International Incorporated | upgrade existing fire alarm system for the st regis museum tower. install 86 manual pull stations on floor 2-38, install 6 door holders on 3rd and 4th flsDetails
upgrade existing fire alarm system for the st regis museum tower. install 86 manual pull stations on floor 2-38, install 6 door holders on 3rd and 4th fls | $25,040 |
| Dec 17, 2015 | Expired or cancelled cancelled Jan 2026 | 125 03rd St | tenant improvement to existing restaurant on gr fl. set includes architectural and mep.Details
tenant improvement to existing restaurant on gr fl. set includes architectural and mep. | $350,000 | |
| Dec 17, 2015 | Expired or cancelled cancelled Mar 2019 | 125 03rd St | (n) entrance door & awning @ 3rd street. (n) wall scences on (e) facade.Details
(n) entrance door & awning @ 3rd street. (n) wall scences on (e) facade. | $35,000 | |
| Oct 16, 2015 | Expired or cancelled withdrawn Jun 2018 | 125 03rd St | temporary tent structure dates of use 4/16-5/24 2016. tent size 60wx 60 dx 22'9.5 hDetails
temporary tent structure dates of use 4/16-5/24 2016. tent size 60wx 60 dx 22'9.5 h | $10,000 | |
| Jul 21, 2015 | Completed final sign-off Feb 2017 | 125 03rd St | Sabah International Incorporated | upgrade existing fire alarm system on 1/f, 2/f & 4/f. remove/replace (6) smoke detectors with (6) combination smoke/carbon monoxide detectors. remove/replace (4) heat detectors with (4) combination heat/carbon monoxide detectors.they are being installed because of fire places,and kitchen gas cookingDetails
upgrade existing fire alarm system on 1/f, 2/f & 4/f. remove/replace (6) smoke detectors with (6) combination smoke/carbon monoxide detectors. remove/replace (4) heat detectors with (4) combination heat/carbon monoxide detectors.they are being installed because of fire places,and kitchen gas cooking | $12,467 |
| Jun 29, 2015 | Expired or cancelled cancelled Jan 2026 | 125 03rd St | installation of head end radio equipment within extg bldg to connect to extg idas system. no new antenna will be installed under this permit.Details
installation of head end radio equipment within extg bldg to connect to extg idas system. no new antenna will be installed under this permit. | $30,000 | |
| Dec 15, 2014 | Completed final sign-off Jan 2015 | 685 Mission St | Principal Builders Inc. | 3rd flr: reduction of original scope of work to remove 3rd flr from project and delete pages & details on 201406279886, 3/a00.60; page a02.03, 3/a06.00; 1,2,3,4,5,6 &9/12.02; 3/g02.01; and 7/ref-1 on 201407221894; 3/a00.60d & 3/a06.00.Details
3rd flr: reduction of original scope of work to remove 3rd flr from project and delete pages & details on 201406279886, 3/a00.60; page a02.03, 3/a06.00; 1,2,3,4,5,6 &9/12.02; 3/g02.01; and 7/ref-1 on 201407221894; 3/a00.60d & 3/a06.00. | |
| Oct 9, 2014 | Completed final sign-off May 2017 | 125 03rd St | Marchetti Group | miscellaneous accessibility improvement in public spaces and accessible guestrooms - voluntary removal of barriers to meet 2013 cbc accessible standardsDetails
miscellaneous accessibility improvement in public spaces and accessible guestrooms - voluntary removal of barriers to meet 2013 cbc accessible standards | $75,000 |
| Jul 22, 2014 | Completed final sign-off Nov 2014 | 685 Mission St | Principal Builders Inc. | floors 1-3: demolish of nonload bearing partition doors, cieling, millwork and finishes. no occupancy per abo-17 and all ada issued to be addressed under seperate t.i. permit.Details
floors 1-3: demolish of nonload bearing partition doors, cieling, millwork and finishes. no occupancy per abo-17 and all ada issued to be addressed under seperate t.i. permit. | $20,000 |
| Apr 1, 2014 | Completed final sign-off Nov 2014 | 125 03rd St | Marchetti Construction Inc. | 21/f- add 2 gates for security in stairwells. (interior only)Details
21/f- add 2 gates for security in stairwells. (interior only) | $20,000 |
| May 14, 2009 | Completed final sign-off Dec 2009 | 125 03rd St | Diversified Fire Products | to complete work and obtain final inspection for work approved under pa 200804180040Details
to complete work and obtain final inspection for work approved under pa 200804180040 | |
| Apr 18, 2008 | Expired or cancelled expired Dec 2009 | 125 03rd St | Diversified Fire Products | fire alarm t.i. for penthouse, floors 39 & 40. 28 addr relays, 14 monitor modules, 2 smoke detectors, 2 duct detectors, 54 sprinklers, 9 wp spkrs, 1 spkr/strobe, 21 door holders, 3 fsds, 8 vesda units.Details
fire alarm t.i. for penthouse, floors 39 & 40. 28 addr relays, 14 monitor modules, 2 smoke detectors, 2 duct detectors, 54 sprinklers, 9 wp spkrs, 1 spkr/strobe, 21 door holders, 3 fsds, 8 vesda units. | $252,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Sabah International Incorporated (5), Hathaway Dinwiddie Co. (3), Diversified Fire Products (2), Marchetti Group (2), Principal Builders Inc. (2), Richlen Construction (2), Continental Contractors Inc, Hathaway Dinwiddie Construct Co, Marchetti Construction Inc., Pioneer Fire Inc., Prima Acquire Inc Dba Lahue And Associat, Waterworks Industries Incorporated
- Architects
- Rory James Carroll (4), Paul Cooper (3), Clifton Boswell, Douglas Zucker, Mark Cavagnero
- Engineers
- Antonio Jacksalem, Daniel Stringer, Peter Kraut, Roberto Cortez, Vincent Waters
- Authorized agents
- Sara Solis
Find contractors for work like this