Block 3706, lot 064
717 Market St
- City’s use
- Commercial Office
- Built
- 1908
- Stories
- 7
- Units
- 2
- Rooms
- 14 bathrooms
- Building
- 74,366 sq ft
- Lot
- 10,598 sq ft
- Zoning
- C3R
- Construction type
- A
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
136 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Oct 8, 2019 | Completed final sign-off Oct 2019 | 717 Market St | Golden Gate Fire Protection Inc | ground fl - fire sprinklers relocate 1 side wall sprinkler head. ref pa 2019-0924-2481Details
ground fl - fire sprinklers relocate 1 side wall sprinkler head. ref pa 2019-0924-2481 | $500 |
| Sep 24, 2019 | Completed final sign-off Oct 2019 | 717 Market St | Rossi Builders Inc. | ground floor: install box truss assembly for future display, rlocate hand drying machine. no mechanical or plumbing work. electical work under seperate trade permit.Details
ground floor: install box truss assembly for future display, rlocate hand drying machine. no mechanical or plumbing work. electical work under seperate trade permit. | $21,064 |
| Jun 6, 2017 | Never finaled issued Jun 2017, no final | 717 Market St | Bilcor Inc | fire alarm ti relocate 1 wall mount strobe, relocate 1 wall mount speaker strobe, install 1 ceiling mount speaker-strobe. remove and reinstall (1) smoke detectors with base. ref pa 2017-0516-6744Details
fire alarm ti relocate 1 wall mount strobe, relocate 1 wall mount speaker strobe, install 1 ceiling mount speaker-strobe. remove and reinstall (1) smoke detectors with base. ref pa 2017-0516-6744 | $2,000 |
| May 24, 2017 | Completed final sign-off Jun 2017 | 717 Market St | Best Way Plumbing | 8th fl: fs: modify 5 sprinkler heads need to raise into t bar ceiling. ref #2017-0516-6744.Details
8th fl: fs: modify 5 sprinkler heads need to raise into t bar ceiling. ref #2017-0516-6744. | $2,500 |
| May 16, 2017 | Completed final sign-off Jul 2017 | 717 Market St | Constructive Solutions Inc. | 8th flr: removal of (e) private offices at open offices. new t-bar ceiling at break room & elevator hallway. ada upgrade at (e) mens & womens rrestroomsDetails
8th flr: removal of (e) private offices at open offices. new t-bar ceiling at break room & elevator hallway. ada upgrade at (e) mens & womens rrestrooms | $36,532 |
| Apr 25, 2017 | Expired or cancelled cancelled Jan 2026 | 717 Market St | Constructive Solutions Inc. | 1st and 2nd floors - reconfigureation of (e) private offices & break room light replacement. new phone roomDetails
1st and 2nd floors - reconfigureation of (e) private offices & break room light replacement. new phone room | $135,000 |
| Aug 25, 2014 | Completed final sign-off Oct 2014 | 715 Market St | Golden Gate Sign Company Inc. | erect a non electric double faced signDetails
erect a non electric double faced sign | $2,500 |
| May 9, 2014 | Completed final sign-off Jun 2014 | 717 Market St | Acco Engineered Systems Inc. Dba Acco En | inall (1) new split system ac unit, instal new refrigerant piping demo/cap existing duct, work is on 4th flr, t.i on app# 201311273042Details
inall (1) new split system ac unit, instal new refrigerant piping demo/cap existing duct, work is on 4th flr, t.i on app# 201311273042 | $25,000 |
| Mar 28, 2014 | Completed final sign-off May 2014 | 717 Market St | Pribuss Engineering Inc | 4th floor fire sprinkler ti total 1 relocated pendent sprinklerDetails
4th floor fire sprinkler ti total 1 relocated pendent sprinkler | $514 |
| Nov 27, 2013 | Completed final sign-off Jun 2014 | 717 Market St | Turner Construction Co | tenant improvements, 1 small ti closet, furniture, 1 small split unit for ac. electrical outlets. 4th fl, partition 3rd floor.Details
tenant improvements, 1 small ti closet, furniture, 1 small split unit for ac. electrical outlets. 4th fl, partition 3rd floor. | $250,000 |
| Oct 25, 2013 | Never finaled issued Oct 2013, no final | 717 Market St | Specialized Graphics Inc | to erect electrical halo lit led channel letters.Details
to erect electrical halo lit led channel letters. | $10,000 |
| Oct 25, 2013 | Never finaled issued Oct 2013, no final | 717 Market St | Specialized Graphics Inc | to erect electrical 2 banners with led lighting in the posts.Details
to erect electrical 2 banners with led lighting in the posts. | $2,000 |
| Oct 25, 2013 | Never finaled issued Oct 2013, no final | 717 Market St | Specialized Graphics Inc | painted logo on garage door. non-structural signDetails
painted logo on garage door. non-structural sign | $750 |
| Oct 25, 2013 | Never finaled issued Oct 2013, no final | 717 Market St | Specialized Graphics Inc | to erect electrical wall graphic with led light tape.Details
to erect electrical wall graphic with led light tape. | $5,000 |
| Oct 23, 2013 | Completed final sign-off Dec 2013 | 717 Market St | Specialized Graphics Inc | evacuation maps: three at basement, three at first floor, and three at second floor. (9) total signs.Details
evacuation maps: three at basement, three at first floor, and three at second floor. (9) total signs. | $1,800 |
| Oct 23, 2013 | Completed final sign-off Nov 2013 | 719 Market St | Specialized Graphics Inc | install (1) evacuation sign on ground floor.Details
install (1) evacuation sign on ground floor. | $300 |
| Oct 4, 2013 | Expired or cancelled cancelled Sep 2023 | 717 Market St | Bilcor Inc | remove 1 wall strobe, install 1 wall mount speaker-strobe, install 3 duct detectors and install 2 control relays.Details
remove 1 wall strobe, install 1 wall mount speaker-strobe, install 3 duct detectors and install 2 control relays. | $1,200 |
| Sep 16, 2013 | Never finaled issued Sep 2013, no final | 717 Market St | the permit is to establish an art activity use at the ground floor per the attached za determination letter dated 7/22/2013. no construction will be performed, no increase in occupancy load.Details
the permit is to establish an art activity use at the ground floor per the attached za determination letter dated 7/22/2013. no construction will be performed, no increase in occupancy load. | ||
| Aug 16, 2013 | Completed final sign-off Nov 2013 | 717 Market St | Sequoia Construction Services Inc | reroofingDetails
reroofing | $19,987 |
| Jul 22, 2013 | Never finaled issued Jul 2013, no final | 717 Market St | Gci, Inc | mech & electrical for t.i. retail space on ground level to relocate and add new equipment. refer to pa#201307031108 for t.i. work.Details
mech & electrical for t.i. retail space on ground level to relocate and add new equipment. refer to pa#201307031108 for t.i. work. | $87,350 |
| Jul 19, 2013 | Completed final sign-off Oct 2013 | 717 Market St | Ayoob & Peery Plumbing Co Inc | 1st & 2nd floors-install new fire sprinkler system, connect to (e) valve assembly, 135 heads totalDetails
1st & 2nd floors-install new fire sprinkler system, connect to (e) valve assembly, 135 heads total | $69,300 |
| Jul 18, 2013 | Completed final sign-off Oct 2013 | 717 Market St | Ayoob & Peery Plumbing Co Inc | 1st floor:relocate and add fire sprinkler head per t.i. add one, 6 relocate. ref app#201307031108Details
1st floor:relocate and add fire sprinkler head per t.i. add one, 6 relocate. ref app#201307031108 | $3,600 |
| Jul 8, 2013 | Never finaled issued Jul 2013, no final | 717 Market St | Bilcor Inc | 1st and 2nd floors:f.a. addition of one ceiling mount strobe, one wall mount strobe, 11 ceiling mount speaker/strobes, 14 wall mounted speaker/strobes, 5 smoke detectors, 3 control relays, one booster panel and 3 duct detectors.Details
1st and 2nd floors:f.a. addition of one ceiling mount strobe, one wall mount strobe, 11 ceiling mount speaker/strobes, 14 wall mounted speaker/strobes, 5 smoke detectors, 3 control relays, one booster panel and 3 duct detectors. | $13,000 |
| Jul 3, 2013 | Never finaled issued Jul 2013, no final | 717 Market St | Gci, Inc | 1st floor - demolition & construction of non-structural partitoins, finishes & ceiling. mech, elec & life safety, sprinklers under separate permit.Details
1st floor - demolition & construction of non-structural partitoins, finishes & ceiling. mech, elec & life safety, sprinklers under separate permit. | $60,000 |
| Jul 1, 2013 | Never finaled issued Jul 2013, no final | 717 Market St | street spaceDetails
street space | ||
| Feb 28, 2013 | Completed final sign-off Jun 2013 | 717 Market St | Principal Builders Inc. | revision to appl #2013.01.07.7352 to show change to hardship request form & restroom details.Details
revision to appl #2013.01.07.7352 to show change to hardship request form & restroom details. | $100 |
| Feb 13, 2013 | Completed final sign-off Feb 2013 | 717 Market St | Pribuss Engineering Inc | 7th floor-fire sprinkler ti add 1 head, change out 5 heads. ti pa# 2013-01-07-7352Details
7th floor-fire sprinkler ti add 1 head, change out 5 heads. ti pa# 2013-01-07-7352 | $3,000 |
| Feb 8, 2013 | Completed final sign-off Mar 2013 | 717 Market St | C B F Inc | 7th floor: install 6 ceiling mount speakers, install 2 ceiling mount speaker-strobes, replace 2 wall strobes with wall speaker strobes. ref app#201301077352Details
7th floor: install 6 ceiling mount speakers, install 2 ceiling mount speaker-strobes, replace 2 wall strobes with wall speaker strobes. ref app#201301077352 | $4,000 |
| Jan 7, 2013 | Completed final sign-off Jun 2013 | 717 Market St | Principal Builders Inc. | 7th floor-tenant improvement to demo & construct non load bearing partitions. mechanical, electrical, life safety will be under seperate permitsDetails
7th floor-tenant improvement to demo & construct non load bearing partitions. mechanical, electrical, life safety will be under seperate permits | $550,000 |
| Aug 17, 2012 | Completed final sign-off Mar 2014 | 717 Market St | Gci, Inc, Skyline Construction | remodel 1st fl & 2nd fl, restroom, office rooms. add (n) exit stair on stevenson st & replace (e) stair. (n) catwalk that connects elevator lobby to south area of 2nd fl. all (n) lighting, mechanical electric + plumbing. sprinkler & fire alarm & sprinkler on separate permit. panic hardware req'd.Details
remodel 1st fl & 2nd fl, restroom, office rooms. add (n) exit stair on stevenson st & replace (e) stair. (n) catwalk that connects elevator lobby to south area of 2nd fl. all (n) lighting, mechanical electric + plumbing. sprinkler & fire alarm & sprinkler on separate permit. panic hardware req'd. | $136,000 |
| May 23, 2012 | Completed final sign-off May 2013 | 717 Market St | 1st & mezzanine-demolition of interior non structural partitions, doors, frames, plumbing fixtures (e) ceiling, light fixtures, per ab-017Details
1st & mezzanine-demolition of interior non structural partitions, doors, frames, plumbing fixtures (e) ceiling, light fixtures, per ab-017 | $5,000 | |
| Jan 17, 2012 | Never finaled issued Jan 2012, no final | 717 Market St | Pacific Auxiliary Fire Alarm | ste #600: renewal of expired permit appn. 200908245418 for final inspection, all work has been completedDetails
ste #600: renewal of expired permit appn. 200908245418 for final inspection, all work has been completed | |
| Nov 18, 2011 | Never finaled issued Nov 2011, no final | 717 Market St | Novo Construction Inc | to obtain final inspection for work approved under pa#200912022458 all work is complete.Details
to obtain final inspection for work approved under pa#200912022458 all work is complete. | |
| Sep 3, 2010 | Never finaled issued Sep 2010, no final | 717 Market St | Basic Partners Inc/Dba Sign & Sign Again | erect banner signDetails
erect banner sign | $2,300 |
| Jul 30, 2010 | Completed final sign-off Oct 2010 | 717 Market St | Pacific Auxiliary Fire Alarm | 4th floor-add 1 smoke detector, 4 speaker strobes, 1 speaker, 1 strobe, 1 relay due to tenant improvment of suite 425Details
4th floor-add 1 smoke detector, 4 speaker strobes, 1 speaker, 1 strobe, 1 relay due to tenant improvment of suite 425 | $5,000 |
| Jul 30, 2010 | Completed final sign-off Oct 2010 | 717 Market St | Pioneer Fire Inc. | 4th floor - relocate one fire sprinkler, add one head.Details
4th floor - relocate one fire sprinkler, add one head. | $2,000 |
| Jul 27, 2010 | Completed final sign-off Sep 2010 | 717 Market St | Ayoob & Peery Plumbing Co Inc | relocate and add fire sprinklers on the 3rd floor . 15 relocate, 2 addDetails
relocate and add fire sprinklers on the 3rd floor . 15 relocate, 2 add | $3,500 |
| Jul 22, 2010 | Completed final sign-off Sep 2010 | 717 Market St | Pacific Auxiliary Fire Alarm | add 14 speaker/strobes, 2 speakers, 1 smoke detection, 5 duct detector and 5 relay modules due to 8 tenant improvment on 3rd flDetails
add 14 speaker/strobes, 2 speakers, 1 smoke detection, 5 duct detector and 5 relay modules due to 8 tenant improvment on 3rd fl | $14,000 |
| Jul 19, 2010 | Completed final sign-off Oct 2010 | 717 Market St | Novo Construction Inc | office ti on the 4th fl. demo of interior non load bearing partitions and door assemblies. construction of new partitions and door assemblies. mep, fire and ls under separate permitDetails
office ti on the 4th fl. demo of interior non load bearing partitions and door assemblies. construction of new partitions and door assemblies. mep, fire and ls under separate permit | $47,500 |
| Jun 30, 2010 | Completed final sign-off Sep 2010 | 717 Market St | Skyline Construction | 3rd floor-construction of non load bearing partitions, new office doors & glazing, partial new ceiling & grid. electrical & mechanical included. life safety & fire sprinkler under seperate permitDetails
3rd floor-construction of non load bearing partitions, new office doors & glazing, partial new ceiling & grid. electrical & mechanical included. life safety & fire sprinkler under seperate permit | $661,182 |
| Dec 2, 2009 | Expired or cancelled expired Oct 2013 | 717 Market St | Novo Construction Inc | 2nd floor office ti. demo interior non-load bearing partitions and door assemblies. construction of new partitions and door assemblies. provide new finishes throughout. mep and fire/life safety under separate permitDetails
2nd floor office ti. demo interior non-load bearing partitions and door assemblies. construction of new partitions and door assemblies. provide new finishes throughout. mep and fire/life safety under separate permit | $4,456 |
| Sep 9, 2009 | Completed final sign-off Mar 2010 | 717 Market St | Novo Construction Inc | mechanical work for 6th fl tenant improvementDetails
mechanical work for 6th fl tenant improvement | $18,000 |
| Sep 3, 2009 | Completed final sign-off Sep 2009 | 717 Market St | Ayoob & Peery Plumbing Co Inc | relocate fire sprinklers per tenant improvments, 6 relocateDetails
relocate fire sprinklers per tenant improvments, 6 relocate | $1,080 |
| Aug 24, 2009 | Never finaled issued Aug 2009, no final | 717 Market St | Pacific Auxiliary Fire Alarm | addition of 2-strobes & 4-speaker/strobes and relocation of 5-existing speaker/strobes.Details
addition of 2-strobes & 4-speaker/strobes and relocation of 5-existing speaker/strobes. | $7,000 |
| Jul 22, 2009 | Completed final sign-off Mar 2010 | 717 Market St | Novo Construction Inc | demolition of non-load bearing partitions and door assembles. construction of new partitions and door assembles. mep, fire & life safety under separate permit.Details
demolition of non-load bearing partitions and door assembles. construction of new partitions and door assembles. mep, fire & life safety under separate permit. | $275,000 |
| Feb 25, 2009 | Completed final sign-off May 2009 | 717 Market St | Novo Construction Inc | renew pa# 2007/11/26/8850 to obtain final inspection. all work has been completed.Details
renew pa# 2007/11/26/8850 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off Apr 2009 | 717 Market St | Novo Construction Inc | renew pa# 2007/12/10/0033 to obtain final inspection. all work has been completed.Details
renew pa# 2007/12/10/0033 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off May 2009 | 717 Market St | Novo Construction Inc | renew pa# 2008/07/24/7527 to obtain final inspection. all work has been completed.Details
renew pa# 2008/07/24/7527 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off May 2009 | 715 Market St | Novo Construction Inc | renew pa# 2007/06/22/4795 to obtain final inspection. all work has been completed.Details
renew pa# 2007/06/22/4795 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off May 2009 | 715 Market St | Novo Construction Inc | renew pa# 2007/11/26/8800 to obtain final inspection. all work has been completed.Details
renew pa# 2007/11/26/8800 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off Apr 2009 | 717 Market St | Novo Construction Inc | renew pa# 2007/12/06/9802 to obtain final inspection. all work has been completed.Details
renew pa# 2007/12/06/9802 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off Nov 2011 | 715 Market St | Novo Construction Inc | renew pa# 2007/06/15/4073 to obtain final inspection. all work has been completed.Details
renew pa# 2007/06/15/4073 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off May 2009 | 717 Market St | Novo Construction Inc | renew pa# 2008/07/23/7451 to obtain final inspection. all work has been completed.Details
renew pa# 2008/07/23/7451 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off Apr 2009 | 715 Market St | Novo Construction Inc | renew pa# 2007/11/27/8998 to obtain final inspection. all work has been completed.Details
renew pa# 2007/11/27/8998 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off Apr 2009 | 717 Market St | Novo Construction Inc | renew pa# 2007/08/29/1217 to obtain final inspection. all work has been completed.Details
renew pa# 2007/08/29/1217 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off Nov 2011 | 715 Market St | Novo Construction Inc | renew pa# 2007/07/27/7918 to obtain final inspection. all work has been completed.Details
renew pa# 2007/07/27/7918 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off May 2009 | 717 Market St | Novo Construction Inc | renew pa# 2007/11/26/8797 to obtain final inspection. all work has been completed.Details
renew pa# 2007/11/26/8797 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off Apr 2009 | 717 Market St | Novo Construction Inc | renew pa# 2007/05/23/2055 to obtain final inspection. all work has been completed.Details
renew pa# 2007/05/23/2055 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off May 2009 | 715 Market St | Novo Construction Inc | renew pa# 2007/06/22/4797 to obtain final inspection. all work has been completed.Details
renew pa# 2007/06/22/4797 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off Nov 2011 | 717 Market St | Novo Construction Inc | renew pa# 2007/12/10/0024 to obtain final inspection. all work has been completed.Details
renew pa# 2007/12/10/0024 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off May 2009 | 717 Market St | Novo Construction Inc | renew pa# 2007/10/24/6328 to obtain final inspection. all work has been completed.Details
renew pa# 2007/10/24/6328 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off Apr 2009 | 717 Market St | Novo Construction Inc | renew pa# 2007/11/26/8853 to obtain final inspection. all work has been completed.Details
renew pa# 2007/11/26/8853 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off Oct 2011 | 717 Market St | Novo Construction Inc | renew pa# 2007/12/10/0030 to obtain final inspection. all work has been completed.Details
renew pa# 2007/12/10/0030 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off Apr 2009 | 717 Market St | Novo Construction Inc | renew pa# 2008/02/20/5125 to obtain final inspection. all work has been completed.Details
renew pa# 2008/02/20/5125 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off May 2009 | 717 Market St | Novo Construction Inc | renew pa# 2008/07/25/7604 to obtain final inspection. all work has been completed.Details
renew pa# 2008/07/25/7604 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off Apr 2009 | 717 Market St | Novo Construction Inc | renew pa# 2008/05/30/3256 to obtain final inspection. all work has been completed.Details
renew pa# 2008/05/30/3256 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off Apr 2009 | 717 Market St | Novo Construction Inc | renew pa# 2007/10/12/5293 to obtain final inspection. all work has been completed.Details
renew pa# 2007/10/12/5293 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off May 2009 | 717 Market St | Novo Construction Inc | renew pa# 2008/07/24/7510 to obtain final inspection. all work has been completed.Details
renew pa# 2008/07/24/7510 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off May 2009 | 717 Market St | Novo Construction Inc | renew pa# 2008/07/23/7450 to obtain final inspection. all work has been completed.Details
renew pa# 2008/07/23/7450 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off May 2009 | 715 Market St | Novo Construction Inc | renew pa# 2007/06/15/4072 to obtain final inspection. all work has been completed.Details
renew pa# 2007/06/15/4072 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off Nov 2011 | 717 Market St | Novo Construction Inc | renew pa# 2007/12/10/0025 to obtain final inspection. all work has been completed.Details
renew pa# 2007/12/10/0025 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off Apr 2009 | 715 Market St | Novo Construction Inc | renew pa# 2007/06/15/4071 to obtain final inspection. all work has been completed.Details
renew pa# 2007/06/15/4071 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off May 2009 | 717 Market St | Novo Construction Inc | renew pa# 2007/11/26/8798 to obtain final inspection. all work has been completed.Details
renew pa# 2007/11/26/8798 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off May 2009 | 717 Market St | Novo Construction Inc | renew pa# 2007/09/18/2906 to obtain final inspection. all work has been completed.Details
renew pa# 2007/09/18/2906 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off Oct 2011 | 717 Market St | Novo Construction Inc | renew pa# 2007/12/10/0031 to obtain final inspection. all work has been completed.Details
renew pa# 2007/12/10/0031 to obtain final inspection. all work has been completed. | |
| Feb 25, 2009 | Completed final sign-off Apr 2009 | 717 Market St | Novo Construction Inc | renew pa# 2007/05/14/1174 to obtain final inspection. all work has been completed.Details
renew pa# 2007/05/14/1174 to obtain final inspection. all work has been completed. | |
| Oct 30, 2008 | Completed final sign-off Dec 2008 | 717 Market St | Pacific Auxiliary Fire Alarm | adding 9 duct detectors and 10 speaker/strobes, 9 relays and 1 control module as part of tenant remodel of the 5th floorDetails
adding 9 duct detectors and 10 speaker/strobes, 9 relays and 1 control module as part of tenant remodel of the 5th floor | $29,000 |
| Oct 29, 2008 | Completed final sign-off Dec 2008 | 719 Market St | Novo Construction Inc | construct 1 hr. rated partitions and door for pg&e gas meter room. mech & elect. scope of works will be filled under separate permit.+Details
construct 1 hr. rated partitions and door for pg&e gas meter room. mech & elect. scope of works will be filled under separate permit.+ | $15,000 |
| Oct 9, 2008 | Completed final sign-off May 2009 | 717 Market St | Anderson, Rowe & Buckley, Inc. | tenant improvement to the existing fire sprinkler system: 9 relocate, 12 newDetails
tenant improvement to the existing fire sprinkler system: 9 relocate, 12 new | $2,500 |
| Sep 26, 2008 | Completed final sign-off Oct 2008 | 717 Market St | compliance with high-rise sprinkler ordinace #377-93/umbrella permitDetails
compliance with high-rise sprinkler ordinace #377-93/umbrella permit | ||
| Sep 26, 2008 | Completed final sign-off Dec 2008 | 717 Market St | Teamwrkx Construction | 5th floor mechanical to include providing heating & ventilation to office space provide heating ventilation & cooling to conference rooms. electrical work to include new lighting/title 24. ref arch pa #200809111390.Details
5th floor mechanical to include providing heating & ventilation to office space provide heating ventilation & cooling to conference rooms. electrical work to include new lighting/title 24. ref arch pa #200809111390. | $160,000 |
| Sep 11, 2008 | Completed final sign-off Dec 2008 | 717 Market St | Teamwrkx Inc. | office tenat improvement: demolition on non-structural partition, building new partition and ada compliant millwork. mep will be filed under separate permits.Details
office tenat improvement: demolition on non-structural partition, building new partition and ada compliant millwork. mep will be filed under separate permits. | $173,260 |
| Aug 28, 2008 | Completed final sign-off Sep 2008 | 717 Market St | Anderson, Rowe & Buckley, Inc. | bsmt, 1st, 2nd, 4th 8th floors & penthouse - t.i. to (e) fire sprinkler system. 12 (n) uprights, 3 (n) pendents, (3) new sidewalls, 2 new ec sidewalls, on bsmt, 1st,2nd,4th,8th, penthouse.Details
bsmt, 1st, 2nd, 4th 8th floors & penthouse - t.i. to (e) fire sprinkler system. 12 (n) uprights, 3 (n) pendents, (3) new sidewalls, 2 new ec sidewalls, on bsmt, 1st,2nd,4th,8th, penthouse. | $4,000 |
| Jul 25, 2008 | Expired or cancelled expired May 2009 | 717 Market St | Anderson, Rowe & Buckley, Inc. | 8th floor - tenant improvements to the existing fire sprinkler, 3 relocated sprinklers.Details
8th floor - tenant improvements to the existing fire sprinkler, 3 relocated sprinklers. | $1,000 |
| Jul 24, 2008 | Expired or cancelled expired May 2009 | 717 Market St | Anderson, Rowe & Buckley, Inc. | 6th floor: ti to existing fire sprinkler system, 15new pendents, 5 new uprights.Details
6th floor: ti to existing fire sprinkler system, 15new pendents, 5 new uprights. | $4,000 |
| Jul 24, 2008 | Expired or cancelled expired May 2009 | 717 Market St | Novo Construction Inc | install 2 fan coils, 1 condenser units on roof, 2 supply grilles and 3 return grilles. ref. pa# 2008/06/09/3986Details
install 2 fan coils, 1 condenser units on roof, 2 supply grilles and 3 return grilles. ref. pa# 2008/06/09/3986 | $21,000 |
| Jul 23, 2008 | Expired or cancelled expired May 2009 | 717 Market St | Novo Construction Inc | revise room's name from server room to tel/data room. revision to application 200806205032.Details
revise room's name from server room to tel/data room. revision to application 200806205032. | |
| Jul 23, 2008 | Expired or cancelled expired May 2009 | 717 Market St | Novo Construction Inc | revise room's name from server room to tel/data room. revision to appliation 200807025794.Details
revise room's name from server room to tel/data room. revision to appliation 200807025794. | |
| Jul 3, 2008 | Completed final sign-off May 2009 | 717 Market St | Novo Construction Inc | demo some interior non-load bearing partition walls and door assemblies. construct new partition walls and door assemblies, provide new finishes throughout. mep and fire safety will be under a separate permit.Details
demo some interior non-load bearing partition walls and door assemblies. construct new partition walls and door assemblies, provide new finishes throughout. mep and fire safety will be under a separate permit. | $90,000 |
| Jun 20, 2008 | Completed final sign-off May 2009 | 717 Market St | Novo Construction Inc | 8th floor office tenant improvements: new ceiling height partitions & doors, remove non-structural interior partitions & doors. modify lighting & hvac layout, mep & life safety system works will be under separate permits.Details
8th floor office tenant improvements: new ceiling height partitions & doors, remove non-structural interior partitions & doors. modify lighting & hvac layout, mep & life safety system works will be under separate permits. | $77,100 |
| Jun 9, 2008 | Completed final sign-off May 2009 | 717 Market St | Novo Construction Inc | 6th floor-tenant improvement works: construct new ceiling height for new offices, equipment room, new sink and millwork. adjust hvac per new layout, m.e.p., life safety will be under seperate permitsDetails
6th floor-tenant improvement works: construct new ceiling height for new offices, equipment room, new sink and millwork. adjust hvac per new layout, m.e.p., life safety will be under seperate permits | $50,000 |
| May 30, 2008 | Expired or cancelled expired Apr 2009 | 717 Market St | Anderson, Rowe & Buckley, Inc. | tenant improvements to extg fire sprinkler system/103 new pendents/4 new uprightsDetails
tenant improvements to extg fire sprinkler system/103 new pendents/4 new uprights | $20,600 |
| May 8, 2008 | Completed final sign-off May 2009 | 717 Market St | Novo Construction Inc | suite 600, 6th floor, demo interior non-load bearing partitions and door assemblies & construct new partitions & door assemblies, new finishes. mep,fire/life safety under separate permit.Details
suite 600, 6th floor, demo interior non-load bearing partitions and door assemblies & construct new partitions & door assemblies, new finishes. mep,fire/life safety under separate permit. | $25,000 |
| Mar 7, 2008 | Completed final sign-off Apr 2009 | 717 Market St | Anderson, Rowe & Buckley, Inc. | replaced fire pump asembly @ basementDetails
replaced fire pump asembly @ basement | $25,000 |
| Feb 20, 2008 | Expired or cancelled expired Apr 2009 | 717 Market St | Novo Construction Inc | construct new 1 hour partitions to create fire pump room and electrical room in basement.Details
construct new 1 hour partitions to create fire pump room and electrical room in basement. | $15,000 |
| Dec 10, 2007 | Expired or cancelled expired Oct 2011 | 717 Market St | Novo Construction Inc | 6th floor - new lighting and electrical work. ref. arch p/a #2007.06.22.4797.Details
6th floor - new lighting and electrical work. ref. arch p/a #2007.06.22.4797. | $21,000 |
| Dec 10, 2007 | Expired or cancelled expired Nov 2011 | 717 Market St | Novo Construction Inc | 5th floor - new lighting and electrical work. ref. p/a #2007.06.15.4072.Details
5th floor - new lighting and electrical work. ref. p/a #2007.06.15.4072. | $25,000 |
| Dec 10, 2007 | Expired or cancelled expired Nov 2011 | 717 Market St | Novo Construction Inc | new lighting and electrical work on the 4th fl. arch. plans on pa# 200706224795 for referenceDetails
new lighting and electrical work on the 4th fl. arch. plans on pa# 200706224795 for reference | $25,000 |
| Dec 10, 2007 | Expired or cancelled expired Oct 2011 | 717 Market St | Novo Construction Inc | new lighting and electrical work on the 3rd floor; ref.arch plans under pa# 2007.06.15.4073Details
new lighting and electrical work on the 3rd floor; ref.arch plans under pa# 2007.06.15.4073 | $16,000 |
| Dec 10, 2007 | Expired or cancelled expired Dec 2011 | 717 Market St | Novo Construction Inc | new lighting and elec. work on the 2nd fl. ref.arch plans under pa# 2007.06.16.15.4071Details
new lighting and elec. work on the 2nd fl. ref.arch plans under pa# 2007.06.16.15.4071 | $18,000 |
| Dec 6, 2007 | Expired or cancelled expired Apr 2009 | 717 Market St | Anderson, Rowe & Buckley, Inc. | 2nd floor: fire sprinklers system - 37 new sprinklers. must submit "plan of action" to replace existing fire pump & install new "back flow preventer".Details
2nd floor: fire sprinklers system - 37 new sprinklers. must submit "plan of action" to replace existing fire pump & install new "back flow preventer". | $7,500 |
| Nov 27, 2007 | Expired or cancelled expired Apr 2009 | 715 Market St | revision to pa# 2007/07/27/7918, emergency generator & smoke control not required.Details
revision to pa# 2007/07/27/7918, emergency generator & smoke control not required. | ||
| Nov 27, 2007 | Completed final sign-off Nov 2011 | 715 Market St | Pacific Auxiliary Fire Alarm | installation of a new fire alarm system throughout building. the occupied spaces will be provided with full coverage.Details
installation of a new fire alarm system throughout building. the occupied spaces will be provided with full coverage. | $296,000 |
| Nov 26, 2007 | Expired or cancelled expired Apr 2009 | 717 Market St | Novo Construction Inc | 2nd floor: 2 fan coils, 1 fire smoke damper, 8 supply grilles, 1 exhaust fan, outside air duct, not water piping, ref #200706154071.Details
2nd floor: 2 fan coils, 1 fire smoke damper, 8 supply grilles, 1 exhaust fan, outside air duct, not water piping, ref #200706154071. | $32,000 |
| Nov 26, 2007 | Expired or cancelled expired May 2009 | 717 Market St | Novo Construction Inc | 5th floor: install 1 new fire smoke damper, 1 new 36 x 1 linear diffuser, new hot water stub outs, ref 200706154072.lifesafety separate permit.Details
5th floor: install 1 new fire smoke damper, 1 new 36 x 1 linear diffuser, new hot water stub outs, ref 200706154072.lifesafety separate permit. | $22,000 |
| Nov 26, 2007 | Expired or cancelled expired May 2009 | 717 Market St | Novo Construction Inc | 6th floor: install 6 hot water fan coil, 2 fire smoke damper, 20 new supplyu grilles, 1 36 x 1 linear diffuser extend condenser stub out and new hot water piping.ref 200706224797.Details
6th floor: install 6 hot water fan coil, 2 fire smoke damper, 20 new supplyu grilles, 1 36 x 1 linear diffuser extend condenser stub out and new hot water piping.ref 200706224797. | $55,000 |
| Nov 26, 2007 | Expired or cancelled expired May 2009 | 717 Market St | Novo Construction Inc | 3rd floor: 1 fire smoke damper, 1 linear diffuser, new hot water stubs, ref #200706154073Details
3rd floor: 1 fire smoke damper, 1 linear diffuser, new hot water stubs, ref #200706154073 | $16,000 |
| Nov 26, 2007 | Expired or cancelled expired May 2009 | 715 Market St | Novo Construction Inc | 4th floor: 3 new hot water fan coil units, 2 fire smoke dampers, 13 supply grilles, 1- 36 x 1 linear diffuser, 7 return grilles, new hot water piping. ref pa# 2007/06/22/4795.Details
4th floor: 3 new hot water fan coil units, 2 fire smoke dampers, 13 supply grilles, 1- 36 x 1 linear diffuser, 7 return grilles, new hot water piping. ref pa# 2007/06/22/4795. | $53,000 |
| Oct 24, 2007 | Expired or cancelled expired May 2009 | 717 Market St | Anderson, Rowe & Buckley, Inc. | 3rd floor-existing fire system expansion. add 64 sprinkler heads.Details
3rd floor-existing fire system expansion. add 64 sprinkler heads. | $12,800 |
| Oct 12, 2007 | Expired or cancelled expired Apr 2009 | 717 Market St | Anderson, Rowe & Buckley, Inc. | sprinkler modification on floors 4,5,and 6, 49 heads/flr.x3=147 headsDetails
sprinkler modification on floors 4,5,and 6, 49 heads/flr.x3=147 heads | $29,000 |
| Sep 18, 2007 | Expired or cancelled expired May 2009 | 717 Market St | Novo Construction Inc | infill a portion of floor slab. provide 2 new skylights on the 3 story portion of bldg. vacant building.Details
infill a portion of floor slab. provide 2 new skylights on the 3 story portion of bldg. vacant building. | $12,000 |
| Aug 29, 2007 | Expired or cancelled expired Apr 2009 | 717 Market St | Novo Construction Inc | new temporary barrier in front of building on sidewalk area.Details
new temporary barrier in front of building on sidewalk area. | $15,000 |
| Jul 27, 2007 | Expired or cancelled expired Dec 2011 | 715 Market St | Novo Construction Inc | re-face first 30'of building exterior, remodel ground floor elevator lobby, mechanical and electrical & life safety under seperate permitDetails
re-face first 30'of building exterior, remodel ground floor elevator lobby, mechanical and electrical & life safety under seperate permit | $400,000 |
| Jun 15, 2007 | Expired or cancelled expired Apr 2009 | 715 Market St | Novo Construction Inc | oti-1, 2nd floor, el, ls, spDetails
oti-1, 2nd floor, el, ls, sp | $100,000 |
| Jun 15, 2007 | Expired or cancelled expired May 2009 | 715 Market St | Novo Construction Inc | oti-1, 5th floor, el, ls, spDetails
oti-1, 5th floor, el, ls, sp | $243,775 |
| Jun 15, 2007 | Expired or cancelled expired May 2009 | 715 Market St | Novo Construction Inc | oti-1, 3rd floor, el, ls, spDetails
oti-1, 3rd floor, el, ls, sp | $304,575 |
| May 23, 2007 | Expired or cancelled expired Apr 2009 | 717 Market St | Novo Construction Inc | interor, non structural demolitio of floors 3 - 6. no increase in office space.Details
interor, non structural demolitio of floors 3 - 6. no increase in office space. | $150,000 |
| May 14, 2007 | Expired or cancelled expired Apr 2009 | 717 Market St | Novo Construction Inc | interior non structural demolition of 1st and 2nd floor partitionsDetails
interior non structural demolition of 1st and 2nd floor partitions | $30,000 |
| Mar 5, 2007 | Completed final sign-off Apr 2007 | 715 Market St | construct temporary wall at sidewalk in front of building. remove extg building sign and awningsDetails
construct temporary wall at sidewalk in front of building. remove extg building sign and awnings | $8,500 | |
| Apr 5, 2005 | Expired or cancelled cancelled Oct 2007 | 715 Market St | conversion of an (e) mixed use office and retail bldg to a mixed use residential loft and retail bldDetails
conversion of an (e) mixed use office and retail bldg to a mixed use residential loft and retail bld | $6,200,000 | |
| Mar 31, 2003 | Expired or cancelled expired Mar 2004 | 717 Market St | renew exp permit app 9925857-for final inspectionDetails
renew exp permit app 9925857-for final inspection | ||
| Jun 11, 2002 | Expired or cancelled expired Oct 2002 | 717 Market St | street space permitDetails
street space permit | ||
| Jan 14, 2002 | Completed final sign-off Mar 2002 | 717 Market St | South Bay Fire Protection | relocate 11 sprinkler heads, add six headsDetails
relocate 11 sprinkler heads, add six heads | $3,000 |
| Dec 19, 2001 | Completed final sign-off Jun 2002 | 717 Market St | Pacific Auxiliary Fire Alarm | add to existing fire alarm system for t7th fl. tenant improvementDetails
add to existing fire alarm system for t7th fl. tenant improvement | $9,000 |
| May 31, 2001 | Completed final sign-off Jun 2002 | 717 Market St | soft demo of non-bearing partition walls, install (n) non-bearing partition walls & lighting fixtureDetails
soft demo of non-bearing partition walls, install (n) non-bearing partition walls & lighting fixture | $25,000 | |
| Apr 13, 2001 | Completed final sign-off Jun 2002 | 717 Market St | Pacific Auxiliary Fire Alarm | add to extg fire alarm system for tenant improvement on 7th floor, fire alarm plan onlyDetails
add to extg fire alarm system for tenant improvement on 7th floor, fire alarm plan only | $9,000 |
| Apr 5, 2001 | Expired or cancelled expired Apr 2002 | 717 Market St | streetspaceDetails
streetspace | ||
| Dec 19, 2000 | Completed final sign-off Jun 2002 | 717 Market St | soft demolition of partition walls install (n) non bearing walls, upgrade restrooms (n) lighting allDetails
soft demolition of partition walls install (n) non bearing walls, upgrade restrooms (n) lighting all | $28,000 | |
| Oct 16, 2000 | Completed final sign-off Nov 2001 | 717 Market St | Kty Enterprises, Inc. | structural bracing for bldg main mechanical unit & mechanical work on roof.Details
structural bracing for bldg main mechanical unit & mechanical work on roof. | $200,000 |
| Sep 11, 2000 | Completed final sign-off Nov 2000 | 717 Market St | Honeywell | access control readers installed in elevator lobby & 2 stariwells. electronics locks to be fail safeDetails
access control readers installed in elevator lobby & 2 stariwells. electronics locks to be fail safe | $9,665 |
| Aug 31, 2000 | Completed final sign-off Sep 2001 | 717 Market St | repair of a damaged brick wall, epoxy cracks for all walls, damage ocurred in last earthquakeDetails
repair of a damaged brick wall, epoxy cracks for all walls, damage ocurred in last earthquake | $50,000 | |
| Jul 25, 2000 | Completed final sign-off Nov 2000 | 717 Market St | Pacific Auxiliary Fire Alarm | tenant improvement fire alarm system on 6th flrDetails
tenant improvement fire alarm system on 6th flr | $9,505 |
| Jun 19, 2000 | Completed final sign-off Nov 2000 | 717 Market St | oti-2 6th floor electrical mechanicalDetails
oti-2 6th floor electrical mechanical | $200,000 | |
| Jun 5, 2000 | Completed final sign-off Nov 2000 | 717 Market St | South Bay Fire Protection | add automatic fire sprinkler through 6th floorDetails
add automatic fire sprinkler through 6th floor | $10,200 |
| May 3, 2000 | Completed final sign-off Nov 2000 | 717 Market St | Kty Enterprises, Inc. | oti-1 6th floor el, me, l/s, spDetails
oti-1 6th floor el, me, l/s, sp | $900,000 |
| Mar 31, 2000 | Completed final sign-off Nov 2000 | 717 Market St | tenant improvement 6th flr,soft demo of partition wall,install t-bar ceiling,remodel toilet-hc req'dDetails
tenant improvement 6th flr,soft demo of partition wall,install t-bar ceiling,remodel toilet-hc req'd | $25,000 |
Find contractors for work like this