Block 0978, lot 018
2750 Jackson St
- City’s use
- Commercial Misc
- Built
- 1956
- Stories
- 3
- Units
- 1
- Rooms
- 9 bathrooms
- Building
- 54,540 sq ft
- Lot
- 35,113 sq ft
- Zoning
- RH2
- Construction type
- B
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
54 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jul 24, 2024 | Completed final sign-off Aug 2024 | 2750 Jackson St | Rapid Fire Safety&Security Llc Dba Pafa | fire alarm ti adding 1 smoke detector and 2 control relays; relocating existing speaker-strobe to existing notifier nfs2-3030 fire alarm system. ref pa 202405222744Details
fire alarm ti adding 1 smoke detector and 2 control relays; relocating existing speaker-strobe to existing notifier nfs2-3030 fire alarm system. ref pa 202405222744 | $11,224 |
| May 22, 2024 | Completed final sign-off Aug 2024 | 2750 Jackson St | Plant Construction Co, Lp | in stall cnc machine & dust collector in rated enclosure.Details
in stall cnc machine & dust collector in rated enclosure. | $25,000 |
| Jul 26, 2023 | Completed final sign-off Aug 2023 | 2750 Jackson St | W C S S Dba Solid Build Construction | infill door between music room and office. add sound insulation.Details
infill door between music room and office. add sound insulation. | $8,000 |
| Jul 12, 2023 | Completed final sign-off Aug 2023 | 2750 Jackson St | Pribuss Engineering Inc | modify fire sprinkler head locations to accommodate new ceiling and partiion layout for (e) classrooms on 1/f & 2/f. 31 total fire sprinkler heads. ref permit 202303284576Details
modify fire sprinkler head locations to accommodate new ceiling and partiion layout for (e) classrooms on 1/f & 2/f. 31 total fire sprinkler heads. ref permit 202303284576 | $15,934 |
| Jul 3, 2023 | Completed final sign-off Aug 2023 | 2750 Jackson St | Pacific Auxiliary Fire Alarm | fire alarm ti 1st fl - replace 8 existing speaker strobes with new; 2nd fl - replace 2 existing strobes with speaker strobes. add 1 speaker - strobe. all additions to existing notifier nfs2-3030 fire alarm systemDetails
fire alarm ti 1st fl - replace 8 existing speaker strobes with new; 2nd fl - replace 2 existing strobes with speaker strobes. add 1 speaker - strobe. all additions to existing notifier nfs2-3030 fire alarm system | $15,098 |
| Jun 21, 2023 | Never finaled issued Jul 2023, no final | 2700 Jackson St | Clayton Timbrell & Co | replacement of (e) property line fence, 10ft, along north property line.Details
replacement of (e) property line fence, 10ft, along north property line. | $30,000 |
| May 31, 2023 | Completed final sign-off Aug 2023 | 2750 Jackson St | The Lawson Roofing Co Inc. | reroofing; per sec 141.0(b)2bi exception 2.Details
reroofing; per sec 141.0(b)2bi exception 2. | $300,000 |
| May 10, 2023 | Completed final sign-off Sep 2023 | 2750 Jackson St | Plant Construction Co, Lp | deferred mechanical only. 202303284576Details
deferred mechanical only. 202303284576 | $64,560 |
| Mar 28, 2023 | Completed final sign-off Sep 2023 | 2750 Jackson St | Plant Construction Co, Lp | interior renovation. work includes re-configuration of 2nd fl vocational room & teacher office & minor partition, door, fixture work on floors 1 & 2. associated electrical. deferred mechanical only.Details
interior renovation. work includes re-configuration of 2nd fl vocational room & teacher office & minor partition, door, fixture work on floors 1 & 2. associated electrical. deferred mechanical only. | $425,000 |
| Dec 23, 2022 | Expired or cancelled withdrawn Apr 2023 | 2750 Jackson St | Plant Construction Co, Lp | 1st fl hallway lighting replacement. restroom renovation. voluntary accessibility upgrade. 2nd fl engineering studio & adjacent offices. (n) fixtures, finishes, & equipment. (n) build-in casework & workstations. (n) m.e.p.. minor structural work at (n) opening at concrete wall.Details
1st fl hallway lighting replacement. restroom renovation. voluntary accessibility upgrade. 2nd fl engineering studio & adjacent offices. (n) fixtures, finishes, & equipment. (n) build-in casework & workstations. (n) m.e.p.. minor structural work at (n) opening at concrete wall. | $800,000 |
| Mar 22, 2022 | Completed final sign-off Aug 2022 | 2750 Jackson St | Pacific Auxiliary Fire Alarm | fire alarm ti: adding 1 speaker strobe to (e) notifier nfs2-3030 fire alarm systemDetails
fire alarm ti: adding 1 speaker strobe to (e) notifier nfs2-3030 fire alarm system | $2,520 |
| Apr 22, 2019 | Never finaled issued Apr 2019, no final | 2750 Jackson St | Occidental Express | increasing of existing netting system at upper playfield from approx 10'0 to 14'0Details
increasing of existing netting system at upper playfield from approx 10'0 to 14'0 | $12,000 |
| Dec 24, 2018 | Completed final sign-off Feb 2019 | 2750 Jackson St | Pacific Auxiliary Fire Alarm | as builts of a tenant improvement to notifier nfs2-3030. relocate gyms beam detectors while still providing required coverage. (gym) ref bpa #201610120018, fa #201809140309Details
as builts of a tenant improvement to notifier nfs2-3030. relocate gyms beam detectors while still providing required coverage. (gym) ref bpa #201610120018, fa #201809140309 | |
| Sep 14, 2018 | Never finaled issued Sep 2018, no final | 2750 Jackson St | Pacific Auxiliary Fire Alarm | ref pa#201610120018; original fire pa# 201704073493; fire alarm t.i. to existing nfs2-30. relocation of (e) beam smoke detector (2) additional of new beam smoke detector(2) in theater seating areaDetails
ref pa#201610120018; original fire pa# 201704073493; fire alarm t.i. to existing nfs2-30. relocation of (e) beam smoke detector (2) additional of new beam smoke detector(2) in theater seating area | $6,340 |
| Jul 6, 2018 | Completed final sign-off Aug 2018 | 2750 Jackson St | Plant Construction Co, Lp | add (n) non-bearing, non-rated demising wall for 2 existing rooms. scope to include finishes, new light fixtures, doors; all to match existing. modify existing supply registered location. maher naDetails
add (n) non-bearing, non-rated demising wall for 2 existing rooms. scope to include finishes, new light fixtures, doors; all to match existing. modify existing supply registered location. maher na | $16,000 |
| Jun 27, 2018 | Never finaled filed Jun 2018, never issued | 2750 Jackson St | fire sprinkler. tenant improvement, extend fire sprinkler system to the last unprotected areas of the building, 1st fl classroom, 2nd fl stair #2, 3rd fl gym & stair #2, add 122 heads ($514.00)Details
fire sprinkler. tenant improvement, extend fire sprinkler system to the last unprotected areas of the building, 1st fl classroom, 2nd fl stair #2, 3rd fl gym & stair #2, add 122 heads ($514.00) | ||
| Jun 27, 2018 | Never finaled issued Aug 2018, no final | 2750 Jackson St | Pribuss Engineering Inc | fire sprinkler. tenant improvement, extend fire sprinkler system to the last unprotected areas of the building. 1st fl classroom, 2nd fl stair #2, 3rd fl gym & stair #2, add 122 heads ($514.00)Details
fire sprinkler. tenant improvement, extend fire sprinkler system to the last unprotected areas of the building. 1st fl classroom, 2nd fl stair #2, 3rd fl gym & stair #2, add 122 heads ($514.00) | $62,708 |
| Oct 4, 2017 | Never finaled issued Oct 2017, no final | 2750 Jackson St | street spaceDetails
street space | ||
| Jul 19, 2017 | Completed final sign-off Feb 2018 | 2750 Jackson St | Allied Fire Protection | fire sprinkler - ti @ gym areas (1st fl) 124 new sprinklers. ref pa 2016-1012-0018Details
fire sprinkler - ti @ gym areas (1st fl) 124 new sprinklers. ref pa 2016-1012-0018 | $53,275 |
| Apr 7, 2017 | Completed final sign-off May 2018 | 2750 Jackson St | Pacific Auxiliary Fire Alarm | fire alarm add 1 pwer supply with control module , 14 speaker strobes, 12 smoke detectors, 4 duct smoke detectorsk, 7 control relays, 1 relay and 2 beam detectors with protective covers. ti to develop existing shell space for gym and theater useDetails
fire alarm add 1 pwer supply with control module , 14 speaker strobes, 12 smoke detectors, 4 duct smoke detectorsk, 7 control relays, 1 relay and 2 beam detectors with protective covers. ti to develop existing shell space for gym and theater use | $19,830 |
| Oct 12, 2016 | Completed final sign-off May 2018 | 2750 Jackson St | Plant Construction Co, Lp | development of existing shell space for gym and theater use including new finishes, lighting, mechanical and structural framing at 2nd fl (maher not req).Details
development of existing shell space for gym and theater use including new finishes, lighting, mechanical and structural framing at 2nd fl (maher not req). | $1,800,000 |
| Nov 13, 2015 | Never finaled issued Nov 2015, no final | 2750 Jackson St | street spaceDetails
street space | ||
| Dec 15, 2014 | Never finaled issued Dec 2014, no final | 2750 Jackson St | street space permitDetails
street space permit | ||
| Sep 9, 2014 | Never finaled issued Sep 2014, no final | 2750 Jackson St | street space permit (renewal of permit m497287)Details
street space permit (renewal of permit m497287) | ||
| Aug 8, 2014 | Completed final sign-off Mar 2015 | 2750 Jackson St | Thomas Swan Sign Co Inc | 15 evacuation plan maps. floors 1 through 4. n/a for the maher ordinance #155-13Details
15 evacuation plan maps. floors 1 through 4. n/a for the maher ordinance #155-13 | $4,500 |
| Jun 17, 2014 | Never finaled issued Jun 2014, no final | 2750 Jackson St | street spaceDetails
street space | ||
| Mar 17, 2014 | Never finaled issued Mar 2014, no final | 2750 Jackson St | renew street space permitDetails
renew street space permit | ||
| Jan 2, 2014 | Never finaled issued Jan 2014, no final | 2750 Jackson St | street space permitDetails
street space permit | ||
| Oct 7, 2013 | Completed final sign-off Aug 2015 | 2750 Jackson St | Herrero Builders Incorporated | rev. to pa# 201211134051 s2- super structure.Details
rev. to pa# 201211134051 s2- super structure. | $10,000 |
| Jul 23, 2013 | Completed final sign-off Apr 2015 | 2750 Jackson St | Legacy Mechanical & Energy Services, Inc | replace boiler with new boilerDetails
replace boiler with new boiler | $215,000 |
| Jul 23, 2013 | Completed final sign-off Aug 2013 | 2750 Jackson St | Pacific Auxiliary Fire Alarm | relocate fire alarm control unit & equipment to provide fire alarm protection in areas not effected by demo & construction workDetails
relocate fire alarm control unit & equipment to provide fire alarm protection in areas not effected by demo & construction work | $7,100 |
| Apr 9, 2013 | Completed final sign-off Jul 2014 | 2750 Jackson St | Herrero Builders Incorporated | demolition and excavation of the project site to a level to accommondate a new below grade storage room will be converted into a multi purpose room & adjacent support spaces under a separate future permit. temporary banicades & egress to partially occupy building during construction.Details
demolition and excavation of the project site to a level to accommondate a new below grade storage room will be converted into a multi purpose room & adjacent support spaces under a separate future permit. temporary banicades & egress to partially occupy building during construction. | $750,000 |
| Mar 4, 2013 | Completed final sign-off Jul 2014 | 2750 Jackson St | temporary shoring & excauation for the construction of below grade improvements at town school for boys. see pa#201304154539 for adjacent property soil nails.Details
temporary shoring & excauation for the construction of below grade improvements at town school for boys. see pa#201304154539 for adjacent property soil nails. | $65,000 | |
| Nov 13, 2012 | Completed final sign-off Aug 2015 | 2750 Jackson St | Herrero Builders Incorporated | demo, excavations & addition to accomodate a new storage room. demo, renovation, & addition in central portion of school. provide new atrium & central stair.Details
demo, excavations & addition to accomodate a new storage room. demo, renovation, & addition in central portion of school. provide new atrium & central stair. | $10,132,487 |
| Aug 16, 2012 | Completed final sign-off Aug 2012 | 2750 Jackson St | Pribuss Engineering Inc | 2nd/3rd floors-fire sprinkler as builts for pa# 2012-0711-4537-2nd fl-add 94 sprinklers & 3rd fl-add 54 sprinklers. install new 4" ames ddcvaDetails
2nd/3rd floors-fire sprinkler as builts for pa# 2012-0711-4537-2nd fl-add 94 sprinklers & 3rd fl-add 54 sprinklers. install new 4" ames ddcva | |
| Aug 6, 2012 | Expired or cancelled cancelled Jan 2026 | 2750 Jackson St | Fisher Development Inc | revision to pa #201112221168. non comustible subfloor into system at theaterDetails
revision to pa #201112221168. non comustible subfloor into system at theater | $35,000 |
| Jul 11, 2012 | Completed final sign-off Aug 2012 | 2750 Jackson St | Pribuss Engineering Inc | fire sprinkler t.i. 2nd floor 90 sprinklers,3rd floor 51Details
fire sprinkler t.i. 2nd floor 90 sprinklers,3rd floor 51 | $72,561 |
| Jun 26, 2012 | Completed final sign-off Nov 2013 | 2750 Jackson St | Pacific Auxiliary Fire Alarm | replacement of existing fire alarm systemDetails
replacement of existing fire alarm system | $46,000 |
| Jun 7, 2012 | Never finaled issued Jun 2012, no final | 2750 Jackson St | street space permit.Details
street space permit. | ||
| May 14, 2012 | Never finaled issued May 2012, no final | 2750 Jackson St | street space and sidewalk repairDetails
street space and sidewalk repair | ||
| May 14, 2012 | Expired or cancelled cancelled May 2014 | 2750 Jackson St | interior non structural demo for floors 1,2,3,. all work to comply with ab 017Details
interior non structural demo for floors 1,2,3,. all work to comply with ab 017 | $30,000 | |
| Dec 22, 2011 | Completed final sign-off Oct 2012 | 2750 Jackson St | Fisher Development Inc | includes interior renovation of a private school, seismic improvements, renovation of a theater space, & replacement of windows at rear elevation.Details
includes interior renovation of a private school, seismic improvements, renovation of a theater space, & replacement of windows at rear elevation. | $2,000,000 |
| Feb 14, 2011 | Expired or cancelled cancelled Jan 2026 | 2750 Jackson St | barrier removal only. removal of non compliant ramps.new accessible ramps and disabled access seating areas in extg theater.Details
barrier removal only. removal of non compliant ramps.new accessible ramps and disabled access seating areas in extg theater. | $16,000 | |
| Oct 13, 2009 | Completed final sign-off Jul 2014 | 2750 Jackson St | Automatic Fire Sprinklers Inc. | fire suppression upgrade on 2nd floor kitchenDetails
fire suppression upgrade on 2nd floor kitchen | $3,500 |
| Jun 15, 2009 | Never finaled issued Jun 2009, no final | 2750 Jackson St | street space permit only.Details
street space permit only. | ||
| May 21, 2009 | Completed final sign-off Sep 2009 | 2750 Jackson St | interior remodel of existing busness office on the 1st floor, interior remodel of existing library andDetails
interior remodel of existing busness office on the 1st floor, interior remodel of existing library and | $123,000 | |
| Apr 2, 2009 | Never finaled issued Apr 2009, no final | 2750 Jackson St | street space permit only.Details
street space permit only. | ||
| Dec 24, 2008 | Never finaled issued Dec 2008, no final | 2750 Jackson St | street space permitDetails
street space permit | ||
| Dec 22, 2008 | Completed final sign-off Jan 2009 | 2750 Jackson St | replacement of existing 14 ft. fence on lower rooftop playfield.Details
replacement of existing 14 ft. fence on lower rooftop playfield. | $20,000 | |
| Jun 27, 2008 | Never finaled issued Jun 2008, no final | 2750 Jackson St | street space permit.Details
street space permit. | ||
| Jun 11, 2008 | Completed final sign-off Oct 2008 | 2750 Jackson St | interior non-structural renovations to areas on 1st, 2nd and 3rd floorsDetails
interior non-structural renovations to areas on 1st, 2nd and 3rd floors | $390,000 | |
| Jun 10, 2008 | Completed final sign-off Oct 2008 | 2750 Jackson St | installation of structural supports for safety barrier netting on (2) rooftop playfields.Details
installation of structural supports for safety barrier netting on (2) rooftop playfields. | $104,550 | |
| Aug 23, 2002 | Expired or cancelled expired Jan 2004 | 2750 Jackson St | revise 2002/08/02/2997. new hc restroom. delete work in other restroom.Details
revise 2002/08/02/2997. new hc restroom. delete work in other restroom. | ||
| Aug 2, 2002 | Expired or cancelled expired Jan 2004 | 2750 Jackson St | divide one classroom into 3 seperate rooms/new door on gym and provide disable access bthrm @ 3rd flDetails
divide one classroom into 3 seperate rooms/new door on gym and provide disable access bthrm @ 3rd fl | $25,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Pacific Auxiliary Fire Alarm (7), Plant Construction Co, Lp (6), Pribuss Engineering Inc (4), Herrero Builders Incorporated (3), Fisher Development Inc (2), Allied Fire Protection, Automatic Fire Sprinklers Inc., Clayton Timbrell & Co, Legacy Mechanical & Energy Services, Inc, Occidental Express, Rapid Fire Safety&Security Llc Dba Pafa, The Lawson Roofing Co Inc., Thomas Swan Sign Co Inc, W C S S Dba Solid Build Construction
- Architects
- Jennifer Tulley (4), Mark Miller (2), Peter Pfau (2), Dwight Alan Long, Judy Chi, Kris W. Johnson, Matthew Pietras
- Engineers
- Stephen Shafeer (2), Zack Kardon (2), Alan Charles Burr, Alex Filatov, Hormoz Janssens, Mike Maguire
- Authorized agent-otherss
- Justin Tang, Matthew Pietras
- Pmt consultant/expediters
- James C. Yorita
Find contractors for work like this