Block 0040, lot 017
295 Bay St
- City’s use
- Commercial Office
- Built
- 1968
- Stories
- 4
- Rooms
- 8 bathrooms
- Building
- 35,590 sq ft
- Lot
- 15,503 sq ft
- Zoning
- C2
- Construction type
- A
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
90 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jan 6, 2026 | Completed final sign-off Jan 2026 | 295 Bay St | B N Builders Inc | revision to bpa#: 202510016476 at the request of field inspector to document infill of storefront and floor for compliant slope.Details
revision to bpa#: 202510016476 at the request of field inspector to document infill of storefront and floor for compliant slope. | |
| Dec 8, 2025 | Completed final sign-off Jan 2026 | 295 Bay St | Phoenix Life Safety Inc Dba Life Safety | relocate and add new notification appliance to meet code for new architectual layout. adding 5 notification. t.i ref #202510016476Details
relocate and add new notification appliance to meet code for new architectual layout. adding 5 notification. t.i ref #202510016476 | $15,000 |
| Nov 19, 2025 | Completed final sign-off Jan 2026 | 295 Bay St | Rodda Electric Inc | 1-2/fl- ref 202510016476- replace (e) lighting and lighting controls equipment in buildling like for like. provide and install (n) receptacles in building and (n) floor boxes and poke thru devices.Details
1-2/fl- ref 202510016476- replace (e) lighting and lighting controls equipment in buildling like for like. provide and install (n) receptacles in building and (n) floor boxes and poke thru devices. | $400,000 |
| Nov 14, 2025 | Completed final sign-off Jan 2026 | 295 Bay St | Westates Mechanical Corporation Inc | tenant improvement: remove/replace 6 sprinklers. plug 14 pendents 1st floor 2 2nd floor 12 ref #2025-1001-6476Details
tenant improvement: remove/replace 6 sprinklers. plug 14 pendents 1st floor 2 2nd floor 12 ref #2025-1001-6476 | $3,000 |
| Oct 29, 2025 | Completed final sign-off Nov 2025 | 295 Bay St | Statewide Roofing Inc. | re roofing: no hot works.Details
re roofing: no hot works. | $147,930 |
| Oct 27, 2025 | Completed final sign-off Apr 2026 | 295 Bay St | B N Builders Inc | interior only work. new communicating stair, new millwork, slab infill at l1 & l2.Details
interior only work. new communicating stair, new millwork, slab infill at l1 & l2. | $200,000 |
| Oct 1, 2025 | Completed final sign-off Jan 2026 | 295 Bay St | B N Builders Inc | improvements to ground floor and 2nd floor: new flooring, paint, interior wall repair, ceiling repair and replacement, stairs and ramps at existing slab steps, railing at above, new partial height walls at open workspace and meeting rooms. new millwork and appliances at ground floor. interior onlyDetails
improvements to ground floor and 2nd floor: new flooring, paint, interior wall repair, ceiling repair and replacement, stairs and ramps at existing slab steps, railing at above, new partial height walls at open workspace and meeting rooms. new millwork and appliances at ground floor. interior only | $1,500,000 |
| Sep 2, 2025 | In progress filed Sep 2025, not yet issued | 295 Bay St | Aaa Restaurant Fire Control Llc | 1/f: relocate 1 existing sprinkler head and add 1 new sprinkler head.Details
1/f: relocate 1 existing sprinkler head and add 1 new sprinkler head. | $10,000 |
| Aug 13, 2024 | In progress issued Aug 2024 | 295 Bay St | Everon Llc | voluntary fire alarm system replacement: replace 1 facu & 1 remote annunctator, reuse all e) initialing devices & notifivation applicances. no change to sequencesDetails
voluntary fire alarm system replacement: replace 1 facu & 1 remote annunctator, reuse all e) initialing devices & notifivation applicances. no change to sequences | $3,000 |
| Jun 16, 2022 | Never finaled issued Jun 2022, no final | 295 Bay St | Tandem Electric, Inc. | remove four building signs "goodwill" from the exterior. remove low voltage wiring to nearestjunction box.Details
remove four building signs "goodwill" from the exterior. remove low voltage wiring to nearestjunction box. | $2,000 |
| Oct 22, 2020 | Completed final sign-off Mar 2021 | 295 Bay St | Jon K Takata Corp Dba Restoration Mgmt | drywall repair from water damage from 3/f. drywall repair all 3 floors in water damage areas. repair drying holes for venting.Details
drywall repair from water damage from 3/f. drywall repair all 3 floors in water damage areas. repair drying holes for venting. | $108,500 |
| Oct 10, 2019 | Expired or cancelled withdrawn Jan 2020 | 295 Bay St | change of use to a new distillery & event core & shell upgrades to (e) 4 story type 2-b bldg envelope. provding new openings for access to retail & loading dock componets & replacing (e) glazing & doors. new interior t.i. to provide (n) distiling space,event & tasting rooms, commerial kitchen.Details
change of use to a new distillery & event core & shell upgrades to (e) 4 story type 2-b bldg envelope. provding new openings for access to retail & loading dock componets & replacing (e) glazing & doors. new interior t.i. to provide (n) distiling space,event & tasting rooms, commerial kitchen. | $3,193,097 | |
| Oct 2, 2019 | Expired or cancelled withdrawn Jan 2020 | 295 Bay St | strengthening of existinb building foundation to support loads for future ti at an existing reinforced masoning building.Details
strengthening of existinb building foundation to support loads for future ti at an existing reinforced masoning building. | $100,000 | |
| Sep 26, 2019 | Expired or cancelled cancelled Jan 2026 | 295 Bay St | interior non-structural demo per ab-017Details
interior non-structural demo per ab-017 | $25,000 | |
| Jun 14, 2017 | Never finaled issued Oct 2017, no final | 295 Bay St | no work. change of occupancy type of the 4th floor from type b office to type a-3 increasing the occupant load of 4th floor to 204 occupants. no new work, this is only a change of occupancy type. n/a maherDetails
no work. change of occupancy type of the 4th floor from type b office to type a-3 increasing the occupant load of 4th floor to 204 occupants. no new work, this is only a change of occupancy type. n/a maher | ||
| May 11, 2017 | Completed final sign-off Jul 2017 | 295 Bay St | Lifeguard Fire Protection Inc. | new fire sprinker in area of work as shown on planDetails
new fire sprinker in area of work as shown on plan | $50,000 |
| Jan 20, 2017 | Never finaled issued Feb 2017, no final | 295 Bay St | Corporate Sign Systems | 9' tall contilevered l shape sign to be installed on face of 295 bay street. extends 24" over side walk. 10' from sidewalk to bottom. sign reads "donations" change in structural attachment to bldg. changing from anchors in grout to through bolt. ref app#20161142551. n/a for maherDetails
9' tall contilevered l shape sign to be installed on face of 295 bay street. extends 24" over side walk. 10' from sidewalk to bottom. sign reads "donations" change in structural attachment to bldg. changing from anchors in grout to through bolt. ref app#20161142551. n/a for maher | |
| Jan 20, 2017 | Never finaled issued Feb 2017, no final | 295 Bay St | Corporate Sign Systems | 9' tall contilevered l shape sign to be installed on face of 295 bay street. extends 28 1/2" over side walk. 8' from sidewalk to bottom. sign reads "goodwill store" change in structural attachment to bldg. changing from anchors in grout to through bolt. ref app#20161142554. n/a for maherDetails
9' tall contilevered l shape sign to be installed on face of 295 bay street. extends 28 1/2" over side walk. 8' from sidewalk to bottom. sign reads "goodwill store" change in structural attachment to bldg. changing from anchors in grout to through bolt. ref app#20161142554. n/a for maher | |
| Dec 29, 2016 | Never finaled issued Aug 2017, no final | 295 Bay St | Triton Tower Inc | at & t mobility new roof top cellsite. install 12 panel antenas in frp screen and equipment cabinets on roof top platform. n/a for maher ordinance no.155-13.Details
at & t mobility new roof top cellsite. install 12 panel antenas in frp screen and equipment cabinets on roof top platform. n/a for maher ordinance no.155-13. | $250,000 |
| Dec 20, 2016 | Never finaled issued Dec 2016, no final | 295 Bay St | Corporate Sign Systems | evacuation maps constructed & installed.Details
evacuation maps constructed & installed. | $600 |
| Dec 13, 2016 | Expired or cancelled withdrawn Oct 2019 | 295 Bay St | Opi Commercial Builders | revision to p/a#201602119416. addition of exterior high pressure laminate panel system at entry of building.Details
revision to p/a#201602119416. addition of exterior high pressure laminate panel system at entry of building. | $119,000 |
| Nov 14, 2016 | Expired or cancelled cancelled Jan 2026 | 295 Bay St | Corporate Sign Systems | install non electricl projecting wall sign - single face maher naDetails
install non electricl projecting wall sign - single face maher na | $500 |
| Nov 14, 2016 | Expired or cancelled cancelled Mar 2017 | 295 Bay St | Corporate Sign Systems | install electrical projecting wall sign - double faced. maher naDetails
install electrical projecting wall sign - double faced. maher na | $2,000 |
| Nov 14, 2016 | Never finaled issued Nov 2016, no final | 295 Bay St | Corporate Sign Systems | install electrical projecting wall sign - single faced. maher naDetails
install electrical projecting wall sign - single faced. maher na | $8,000 |
| Nov 14, 2016 | Never finaled issued Nov 2016, no final | 295 Bay St | Corporate Sign Systems | install electrical projecting wall sign - single faced. maher naDetails
install electrical projecting wall sign - single faced. maher na | $1,500 |
| Nov 14, 2016 | Never finaled issued Nov 2016, no final | 295 Bay St | Corporate Sign Systems | install electrical projecting wall sign - single faced. maher naDetails
install electrical projecting wall sign - single faced. maher na | $4,000 |
| Nov 14, 2016 | Never finaled issued Nov 2016, no final | 295 Bay St | Corporate Sign Systems | install electrical projecting wall sign - double faced. maher naDetails
install electrical projecting wall sign - double faced. maher na | $2,000 |
| Oct 24, 2016 | Never finaled issued Oct 2016, no final | 295 Bay St | street spaceDetails
street space | ||
| Oct 6, 2016 | Completed final sign-off Oct 2019 | 295 Bay St | Opi Commercial Builders | revision to pa#201602119416, add exterior metal canopies at retail entry & drop-off location, extend (e) covered exterior hallway along side of bldg. enclouse (e) stair between g/f retail & 2/f office, add new (111) door between lobby & office. n/a ordinance #155-13Details
revision to pa#201602119416, add exterior metal canopies at retail entry & drop-off location, extend (e) covered exterior hallway along side of bldg. enclouse (e) stair between g/f retail & 2/f office, add new (111) door between lobby & office. n/a ordinance #155-13 | $38,000 |
| Sep 22, 2016 | Completed final sign-off Nov 2016 | 295 Bay St | H C I Systems Inc | hci systems inc. shall install 12 new notification appliances throughout tenant space. all strobes shall be synchronized and tied into (e) power supply. these are as built field changes: ref 201512144987Details
hci systems inc. shall install 12 new notification appliances throughout tenant space. all strobes shall be synchronized and tied into (e) power supply. these are as built field changes: ref 201512144987 | |
| Aug 29, 2016 | Expired or cancelled withdrawn Oct 2019 | 295 Bay St | revision 201602119416, exterior modifications only comprised of addition of decorative metal panel cladding at main entry corner of building and new steel canopy at retail entry. extension of covered exist walkway hall along west side of buildingDetails
revision 201602119416, exterior modifications only comprised of addition of decorative metal panel cladding at main entry corner of building and new steel canopy at retail entry. extension of covered exist walkway hall along west side of building | $52,500 | |
| Aug 25, 2016 | Never finaled issued Aug 2016, no final | 295 Bay St | street spaceDetails
street space | ||
| Aug 24, 2016 | Never finaled issued Aug 2016, no final | 295 Bay St | Lifeguard Fire Protection Inc. | existing fire sprinkler system will be modified to suit existing and new rooms. fire protection requirements based on their occupancy and hazard. ref pa 2015-1214-4987Details
existing fire sprinkler system will be modified to suit existing and new rooms. fire protection requirements based on their occupancy and hazard. ref pa 2015-1214-4987 | $10,000 |
| Jul 27, 2016 | Expired or cancelled withdrawn Aug 2016 | 295 Bay St | Lifeguard Fire Protection Inc. | add 28 fire sprinkler heads and relocate 11 (e) due to new layoutDetails
add 28 fire sprinkler heads and relocate 11 (e) due to new layout | $10,000 |
| Jul 22, 2016 | Completed final sign-off Sep 2017 | 295 Bay St | revision to pa 201604124527 arch and structural scope included. fire/life safety/mep under sep permit maher naDetails
revision to pa 201604124527 arch and structural scope included. fire/life safety/mep under sep permit maher na | $83,000 | |
| Jul 7, 2016 | Completed final sign-off Oct 2016 | 295 Bay St | Silicon Valley Mechanical Inc | floors: 1-4, mechanical work for t.i. permit 201604124527; relocate thermostats and diffusers; maher n/aDetails
floors: 1-4, mechanical work for t.i. permit 201604124527; relocate thermostats and diffusers; maher n/a | $20,000 |
| Jun 21, 2016 | Never finaled issued Jun 2016, no final | 295 Bay St | street spaceDetails
street space | ||
| Jun 14, 2016 | Never finaled issued Jun 2016, no final | 295 Bay St | New Age Electric Inc | revision to pa#201601298335 electrical plans for change first floor from office space t.i. to retail/warehouse. t.i. pa#201604124527. n/a for maher.Details
revision to pa#201601298335 electrical plans for change first floor from office space t.i. to retail/warehouse. t.i. pa#201604124527. n/a for maher. | $604,000 |
| Jun 6, 2016 | Expired or cancelled cancelled Aug 2023 | 295 Bay St | Lifeguard Fire Protection Inc. | relocate 39 fire sprinkler heads to suit new walls layout for all floors. ref pa #201512144987. n/a maher ordinanceDetails
relocate 39 fire sprinkler heads to suit new walls layout for all floors. ref pa #201512144987. n/a maher ordinance | $8,000 |
| May 10, 2016 | Completed final sign-off Sep 2017 | 295 Bay St | Opi Commercial Builders | modifications to existing exterior canopy under permit 201602119416; maher n/aDetails
modifications to existing exterior canopy under permit 201602119416; maher n/a | $20,000 |
| Apr 15, 2016 | Completed final sign-off Feb 2017 | 295 Bay St | H C I Systems Inc | 1 thru 3rd flrs: install 13 new notification appliances and relocate 3 horns/strobes, all new notification appliances shall be tied into an (e) power supply. maher naDetails
1 thru 3rd flrs: install 13 new notification appliances and relocate 3 horns/strobes, all new notification appliances shall be tied into an (e) power supply. maher na | $6,000 |
| Apr 12, 2016 | Completed final sign-off Sep 2017 | 295 Bay St | Opi Commercial Builders | interior t.i. of all 4 floors, office, and retail at ground floor. structural upgrades. mep under seperate permit. n/a for maher.Details
interior t.i. of all 4 floors, office, and retail at ground floor. structural upgrades. mep under seperate permit. n/a for maher. | $1,864,830 |
| Apr 4, 2016 | Completed final sign-off Oct 2016 | 295 Bay St | Opi Commercial Builders | revision to app#201510068992. additional wall demo on all floors. sawcut for new door install. some walls originally to be demoed well stay. n/a for maher.Details
revision to app#201510068992. additional wall demo on all floors. sawcut for new door install. some walls originally to be demoed well stay. n/a for maher. | $2,500 |
| Feb 19, 2016 | Expired or cancelled cancelled Aug 2023 | 295 Bay St | Lifeguard Fire Protection Inc. | add 26 sprinkler heads to new walls maher naDetails
add 26 sprinkler heads to new walls maher na | $10,000 |
| Feb 11, 2016 | Expired or cancelled cancelled Jan 2026 | 295 Bay St | non electric signDetails
non electric sign | $2,500 | |
| Feb 11, 2016 | Completed final sign-off Sep 2017 | 295 Bay St | Opi Commercial Builders | exterior remodel consist of new exterior glazing along north and west elevations in existing openings. demo existing entrance signage at main entry and addition of new canopy above main building entry. ref 201512144907Details
exterior remodel consist of new exterior glazing along north and west elevations in existing openings. demo existing entrance signage at main entry and addition of new canopy above main building entry. ref 201512144907 | $575,000 |
| Jan 29, 2016 | Never finaled issued Mar 2016, no final | 295 Bay St | New Age Electric Inc, Opi Commercial Builders | safely perform commercial electrical work on 4 flr levels,new led light fixture w/controls,power,plug,switches in office spaces for goodwill store operations here in sf, ref. 201512144987; title 24; maher n/aDetails
safely perform commercial electrical work on 4 flr levels,new led light fixture w/controls,power,plug,switches in office spaces for goodwill store operations here in sf, ref. 201512144987; title 24; maher n/a | $125,415 |
| Dec 14, 2015 | Never finaled issued Dec 2015, no final | 295 Bay St | Opi Commercial Builders | interior tenant improvement on all four floors, previous demo pa #201510068992. mep & life safety/sprinkler deferred under separate permit. n/a maher ordinanceDetails
interior tenant improvement on all four floors, previous demo pa #201510068992. mep & life safety/sprinkler deferred under separate permit. n/a maher ordinance | $1,864,830 |
| Dec 4, 2015 | Expired or cancelled cancelled Jan 2026 | 295 Bay St | tenant improvement of all 4 floors, including replacement of existing exterior windows with new insulated glazing. mep & life safety/sprinklers under separate permit. n/a maher ordinanceDetails
tenant improvement of all 4 floors, including replacement of existing exterior windows with new insulated glazing. mep & life safety/sprinklers under separate permit. n/a maher ordinance | $2,864,830 | |
| Oct 6, 2015 | Never finaled issued Oct 2015, no final | 295 Bay St | Opi Commercial Builders | demo of interior walls and finishes per ab - 017. maher naDetails
demo of interior walls and finishes per ab - 017. maher na | $45,000 |
| May 2, 2014 | Expired or cancelled withdrawn Dec 2016 | 295 Bay St | at&t mobility -12 panel antennas ( 6" frp penthouse) (3 behind frp chimneys) (3 mounted to lower railing) & related ground mounted radio equipment inside new t.i. room. compliance with ordinance #155-13 not requiredDetails
at&t mobility -12 panel antennas ( 6" frp penthouse) (3 behind frp chimneys) (3 mounted to lower railing) & related ground mounted radio equipment inside new t.i. room. compliance with ordinance #155-13 not required | $145,000 | |
| Jul 2, 2010 | Never finaled issued Jul 2010, no final | 295 Bay St | Grace Roofing & Construction | reroofingDetails
reroofing | $119,400 |
| May 4, 2010 | Never finaled issued May 2010, no final | 295 Bay St | street spaceDetails
street space | ||
| Mar 5, 2010 | Completed final sign-off Aug 2010 | 295 Bay St | Har Bro Of No. California | approx. 2300 sq ft of drywall to be replaced on office dividing pony walls. water damage as a result of sprinklers going off.Details
approx. 2300 sq ft of drywall to be replaced on office dividing pony walls. water damage as a result of sprinklers going off. | $15,000 |
| Mar 4, 2010 | Never finaled issued Mar 2010, no final | 295 Bay St | street space permitDetails
street space permit | ||
| Jan 27, 2010 | Never finaled issued Jan 2010, no final | 295 Bay St | street spaceDetails
street space | ||
| Dec 29, 2009 | Never finaled issued Dec 2009, no final | 295 Bay St | street spaceDetails
street space | ||
| Apr 7, 2009 | Never finaled issued Apr 2009, no final | 295 Bay St | Diversified Fire Products | to obtain final inspection for work approved under pa#200707187144. all work is complete.Details
to obtain final inspection for work approved under pa#200707187144. all work is complete. | |
| Jul 18, 2007 | Expired or cancelled expired Mar 2009 | 295 Bay St | Diversified Fire Products | fire alarm t.i. for 295 bay - fm 200 system.Details
fire alarm t.i. for 295 bay - fm 200 system. | $74,750 |
| Mar 1, 2007 | Completed final sign-off Apr 2007 | 295 Bay St | Golden Bear Fire Protect. | add new offices sprinkler, relocate issu sprinkler & add 3. add 1 ssp sprinkler. 1st & 3rd floor t.i.Details
add new offices sprinkler, relocate issu sprinkler & add 3. add 1 ssp sprinkler. 1st & 3rd floor t.i. | $850 |
| Feb 7, 2007 | Completed final sign-off Apr 2007 | 295 Bay St | oti-1 (rev.)Details
oti-1 (rev.) | $10,000 | |
| Dec 15, 2006 | Expired or cancelled expired Mar 2009 | 295 Bay St | viz llc oti-1 3rd floor add 3 new partitions to divide existing open office area and enclose 1 open office el me ls spDetails
viz llc oti-1 3rd floor add 3 new partitions to divide existing open office area and enclose 1 open office el me ls sp | $27,000 | |
| Dec 5, 2006 | Expired or cancelled expired Mar 2009 | 295 Bay St | oti-1 1st floor el, spDetails
oti-1 1st floor el, sp | $12,000 | |
| Feb 8, 2005 | Completed final sign-off Jul 2005 | 295 Bay St | Golden Bear Fire Protect. | install 2 sprinkle under 4th fl deck.Details
install 2 sprinkle under 4th fl deck. | $750 |
| Nov 17, 2004 | Completed final sign-off Jul 2005 | 295 Bay St | exterior alteration at ground floor to restore storefront to original configuration. work alsoDetails
exterior alteration at ground floor to restore storefront to original configuration. work also | $25,000 | |
| Nov 17, 2004 | Completed final sign-off May 2005 | 295 Bay St | new exterior deck off 4th floor break room. accessibitoy under pa# 2004/07/02/7954.Details
new exterior deck off 4th floor break room. accessibitoy under pa# 2004/07/02/7954. | $45,000 | |
| Oct 19, 2004 | Completed final sign-off Jul 2005 | 295 Bay St | Sprig Electric (Archkey Solutions) | installation of fire alarm system on all floors.Details
installation of fire alarm system on all floors. | $23,277 |
| Sep 8, 2004 | Completed final sign-off Jul 2005 | 295 Bay St | Golden Bear Fire Protect. | add and relocate fire spinklersDetails
add and relocate fire spinklers | $15,875 |
| Aug 9, 2004 | Never finaled issued Aug 2004, no final | 295 Bay St | street spaceDetails
street space | ||
| Jul 22, 2004 | Completed final sign-off Jul 2004 | 295 Bay St | revision to pa 20000111784, to correct the language.Details
revision to pa 20000111784, to correct the language. | ||
| Jul 2, 2004 | Completed final sign-off Mar 2005 | 295 Bay St | int. t.i for 4-story office bldg. work includes (n) partitions doors, millwork (n) lighting & mech.Details
int. t.i for 4-story office bldg. work includes (n) partitions doors, millwork (n) lighting & mech. | $775,000 | |
| Jun 29, 2004 | Completed final sign-off May 2005 | 295 Bay St | structural improvements in advance of t.i work under separate permit. t.i will contain required acceDetails
structural improvements in advance of t.i work under separate permit. t.i will contain required acce | $75,000 | |
| May 26, 2004 | Completed final sign-off Nov 2004 | 295 Bay St | Enterprise Roofing Service Inc | reroofingDetails
reroofing | $56,913 |
| May 19, 2004 | Completed final sign-off Jul 2005 | 295 Bay St | interior non-stru demo of (e) tiin preparation for (n)t.i. under sep permit to be sub within 60 daysDetails
interior non-stru demo of (e) tiin preparation for (n)t.i. under sep permit to be sub within 60 days | $5,500 | |
| Sep 9, 2002 | Expired or cancelled cancelled Jan 2005 | 295 Bay St | install unmanned wireless telecommunications facility includes placing 6 antennas facade mounted toDetails
install unmanned wireless telecommunications facility includes placing 6 antennas facade mounted to | $65,000 | |
| Mar 5, 2002 | Expired or cancelled cancelled Dec 2002 | 295 Bay St | erect sign for non electtic, wall, single facedDetails
erect sign for non electtic, wall, single faced | $1,200 | |
| Feb 15, 2001 | Expired or cancelled expired Aug 2002 | 295 Bay St | rev. to appl#200011085238 install (n) fire blocking & nov combustable insulation below (n) terracedDetails
rev. to appl#200011085238 install (n) fire blocking & nov combustable insulation below (n) terraced | $17,000 | |
| Feb 14, 2001 | Expired or cancelled expired Feb 2002 | 295 Bay St | street spaceDetails
street space | ||
| Feb 12, 2001 | Expired or cancelled expired Jun 2001 | 295 Bay St | transfer work scope from appl#20000111784 to 200011085238 includes: entry door, ada guard/handrailDetails
transfer work scope from appl#20000111784 to 200011085238 includes: entry door, ada guard/handrail | ||
| Jan 24, 2001 | Expired or cancelled expired Feb 2002 | 295 Bay St | title 24 lighting compliance on all floors per app #200011085238Details
title 24 lighting compliance on all floors per app #200011085238 | $19,750 | |
| Jan 11, 2001 | Expired or cancelled expired Aug 2002 | 295 Bay St | add fire alarm devicwes to (e)f fire alarm system for entire bldgDetails
add fire alarm devicwes to (e)f fire alarm system for entire bldg | $15,000 | |
| Nov 8, 2000 | Expired or cancelled expired Aug 2002 | 295 Bay St | interior tenant improvement including (n) wall,(n) finishes,(n) platform to provide a level flr. allDetails
interior tenant improvement including (n) wall,(n) finishes,(n) platform to provide a level flr. all | $200,000 | |
| Nov 8, 2000 | Completed final sign-off Feb 2001 | 2290 Powell St | revision to existing permit 200010122805-sheet a-2 onlyDetails
revision to existing permit 200010122805-sheet a-2 only | $2,000 | |
| Oct 12, 2000 | Completed final sign-off Feb 2001 | 295 Bay St | ada upgrade to (e) toilets located on the 3rd & 4th flrsDetails
ada upgrade to (e) toilets located on the 3rd & 4th flrs | $30,000 | |
| Sep 6, 2000 | Completed final sign-off Feb 2001 | 295 Bay St | Dpw Inc. | sprinkler on 1st & 2nd floor of extg theatherDetails
sprinkler on 1st & 2nd floor of extg theather | $42,000 |
| Jul 21, 2000 | Completed final sign-off Jun 2001 | 295 Bay St | correct type i const to type ii 1 hrDetails
correct type i const to type ii 1 hr | ||
| May 24, 2000 | Expired or cancelled expired May 2001 | 295 Bay St | street space useDetails
street space use | ||
| May 8, 2000 | Completed final sign-off Sep 2000 | 295 Bay St | soft demo. no structural work.Details
soft demo. no structural work. | $8,000 | |
| Mar 15, 2000 | Expired or cancelled withdrawn Mar 2000 | 295 Bay St | tentant improvement renovation to theaterDetails
tentant improvement renovation to theater | $591,920 | |
| Jan 11, 2000 | Completed final sign-off Jun 2001 | 295 Bay St | change theatre to ofice on ground floor, ground floor to become two levels, 2nd & 3rd office useDetails
change theatre to ofice on ground floor, ground floor to become two levels, 2nd & 3rd office use | $600,000 |
Find contractors for work like this