12 permits since 2000 (engineer on 12 permits): 9 completed, 3 in progress.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. The discipline is read from the letters before the number, as the Board for Professional Engineers, Land Surveyors, and Geologists lists them (its license types, read Oct 16, 2026), and for a C number from whether the permits list the license as an architect or as an engineer. How to read these records
Worked with
Every other licensed party on the same permits, by the role the city lists them under, with how many of those permits each is on.
- Contractors
- The Whiting-Turner Contracting Company (3), Kaiser Foundation Health Plan Inc (2), Mar Con Builders Inc Dba Mar Con Co (2), Tradequip Corporation (2), Swinerton Builders
- Architects
- Jason C Brabo (4), Ken Yamauchi (4), Mehrnoush Arsanjani, Nichols Rooth Architects, Steve Witte
- Engineers
- John Thompson (3), Harold A Hougham (2), Braden Roach Bill, Brian Reil, Mehrangiz Ansari, Robert K Tjoe;E, Soli Sorabji
- Designers
- Ronald Demartini
Where they worked
- Single-family 0
- Multi-family (2-family, apartments) 0
- Commercial 3
- Other or unknown 9
One dot per permit, coloured by the building type the city or the assessor gives it. A dark circle is several permits close together: click it to zoom in.
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| May 28, 2026 | In progress filed May 2026, not yet issued | 2190 Ofarrell St | Kaiser Foundation Health Plan Inc | modernization of 2 existing traction elevators, including new machinery and controllers, to comply with current codes, to serve the parking garage. new ventilation for (e) elevator machine room - new split system. new pit and elevator machine room lighting.Details
modernization of 2 existing traction elevators, including new machinery and controllers, to comply with current codes, to serve the parking garage. new ventilation for (e) elevator machine room - new split system. new pit and elevator machine room lighting. | $2,623,126 |
| Apr 29, 2026 | In progress filed Apr 2026, not yet issued | 2241 Geary Bl | Kaiser Foundation Health Plan Inc | modernization of 2 existing traction elevators, including new machinery and controllers, to comply with current codes, to serve the parking garage. new ventilation for (e) elevator machine room - new split system. new pit and elevator machine room lighting.Details
modernization of 2 existing traction elevators, including new machinery and controllers, to comply with current codes, to serve the parking garage. new ventilation for (e) elevator machine room - new split system. new pit and elevator machine room lighting. | $2,356,955 |
| Jul 10, 2025 | Completed final sign-off Jul 2025 | 2238 Geary Bl | The Whiting-Turner Contracting Company | revision pa # 202112204707 & 202412197138. revise (e) fa system. remove all vesda references & devices for elevators 7 & 8. break, splice, connect, install and extend wiring as needed. verify (e) devices are in good condition. preform protest and submit documentation to ahs before final inspection.Details
revision pa # 202112204707 & 202412197138. revise (e) fa system. remove all vesda references & devices for elevators 7 & 8. break, splice, connect, install and extend wiring as needed. verify (e) devices are in good condition. preform protest and submit documentation to ahs before final inspection. | $60,000 |
| Sep 19, 2023 | Completed final sign-off Aug 2025 | 240 Shotwell St | Tradequip Corporation | renovation of (e) 1820 sq.ft. oshpd-3 dental area. within (e) oshpd clinic including a (n) reception. (n) dental operatories,(n) sterile & lab space & (n) admin team area. (n) electrical panel, (n) lighting, & replacement of (e) rooftop mechanical units w/ (n) attic installed ductwork.Details
renovation of (e) 1820 sq.ft. oshpd-3 dental area. within (e) oshpd clinic including a (n) reception. (n) dental operatories,(n) sterile & lab space & (n) admin team area. (n) electrical panel, (n) lighting, & replacement of (e) rooftop mechanical units w/ (n) attic installed ductwork. | $523,000 |
| Jul 25, 2023 | In progress issued Mar 2024 | 240 Shotwell St | Tradequip Corporation | priority process per ab004 - replacement of the mechanical units on the roof & attic space (non oshpd-3) that supply air to the 2nd flr admin offices. new electrical panel, corrective work & new structural supports at the roof.Details
priority process per ab004 - replacement of the mechanical units on the roof & attic space (non oshpd-3) that supply air to the 2nd flr admin offices. new electrical panel, corrective work & new structural supports at the roof. | $400,000 |
| Nov 1, 2022 | Completed final sign-off Jun 2025 | 4836 Mission St | new 9,670 sqft ground floor tenant improvement for the mission neighborhood health center (mnhc): 11 exam room primary care facilities. 6 operatory dental clinics. administrative space. base pa# 201903195605 s.Details
new 9,670 sqft ground floor tenant improvement for the mission neighborhood health center (mnhc): 11 exam room primary care facilities. 6 operatory dental clinics. administrative space. base pa# 201903195605 s. | $1,100,000 | |
| Dec 20, 2021 | Completed final sign-off Aug 2025 | 2238 Geary Bl | The Whiting-Turner Contracting Company | revision to pa#2021-0312-6502 and 2021-0830-7389. required redesign of ventilation requirement fr level b-5 elevator machine rm based on a revision of heat loads from elevator manufacturer (fc-1 and cu-1). add'l constructability comments from gc related to bedesign. added access control sheets toDetails
revision to pa#2021-0312-6502 and 2021-0830-7389. required redesign of ventilation requirement fr level b-5 elevator machine rm based on a revision of heat loads from elevator manufacturer (fc-1 and cu-1). add'l constructability comments from gc related to bedesign. added access control sheets to | $45,000 |
| Mar 12, 2021 | Completed final sign-off Jul 2025 | 2238 Geary Bl | The Whiting-Turner Contracting Company | modernization of 2 existing hydraulic elevators and 6 traction elevators new air handling units to service elevator machine room and sprinklers to be removed top of hoistways to comply with cbc 2019.Details
modernization of 2 existing hydraulic elevators and 6 traction elevators new air handling units to service elevator machine room and sprinklers to be removed top of hoistways to comply with cbc 2019. | $300,000 |
| Sep 10, 2018 | Completed final sign-off Nov 2019 | 909 Hyde St | Mar Con Builders Inc Dba Mar Con Co | expansion of 1 restroom (one wall to be moved) new plumbing, fixtures. lighting & finishes in restroom. modification of (e) drinking fountains for accessible rated water height reqs. new signage & door schedule maher naDetails
expansion of 1 restroom (one wall to be moved) new plumbing, fixtures. lighting & finishes in restroom. modification of (e) drinking fountains for accessible rated water height reqs. new signage & door schedule maher na | $50,000 |
| Sep 10, 2018 | Completed final sign-off Nov 2019 | 1199 Bush St | Mar Con Builders Inc Dba Mar Con Co | expansion of 1 restroom (one wall to be moved) new plumbing, fixtures. lighting & finishes. in two restroom. modification of (e) drinking fountains for accessible water flow reqs, new suite signage on all floors, additional pull-latch to elevate cab. reverse swing of one (e) door maher naDetails
expansion of 1 restroom (one wall to be moved) new plumbing, fixtures. lighting & finishes. in two restroom. modification of (e) drinking fountains for accessible water flow reqs, new suite signage on all floors, additional pull-latch to elevate cab. reverse swing of one (e) door maher na | $50,000 |
| Jun 21, 2011 | Completed final sign-off Nov 2011 | 333 Bush St | Swinerton Builders | at 8th fl: build out of new partitions, ceiling, lighting, plumbing for standard tenant improvement. mechanical under separate permit.Details
at 8th fl: build out of new partitions, ceiling, lighting, plumbing for standard tenant improvement. mechanical under separate permit. | $750,000 |
| May 19, 2011 | Completed final sign-off Apr 2012 | 2238 Geary Bl | provide electrical & mechancial upgrade to tr rooms to support (n) it equipment. this includes the installation of (1) (n) ups, (n) battery back-up, (n) hvac equipment, (n) electrical outlets & (n) ground bus bars.Details
provide electrical & mechancial upgrade to tr rooms to support (n) it equipment. this includes the installation of (1) (n) ups, (n) battery back-up, (n) hvac equipment, (n) electrical outlets & (n) ground bus bars. | $475,000 |