Bill Guan
- Listed as
- architect, authorized agent-others, designer, engineer, lessee, pmt consultant/expediter
- Firm
- Xie Associates
- Based in
- San Francisco
- On San Francisco permits
- May 2006 to Sep 2026
1,149 permits since 2000 (architect on 981 permits, engineer on 76 permits, authorized agent-others on 48 permits, designer on 44 permits, pmt consultant/expediter on 2 permits, lessee on 1 permit): 768 completed, 132 in progress, 123 never finaled, 126 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
Showing the 100 most recent of 1,149.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 30, 2026 | In progress filed Sep 2026, not yet issued | 267 Bright St | new adu per ca govt code. at 1/f: modify (e) floor space with 1 new bedroom and bathroom, kitchen and laundry.Details
new adu per ca govt code. at 1/f: modify (e) floor space with 1 new bedroom and bathroom, kitchen and laundry. | $85,000 | |
| Sep 25, 2026 | In progress filed Sep 2026, not yet issued | 94 Ney St | 2/fl- enclosed (e) porch space and extending porch coverDetails
2/fl- enclosed (e) porch space and extending porch cover | $12,000 | |
| Sep 21, 2026 | In progress filed Sep 2026, not yet issued | 180 11th Av | unit #6, 4th fl - remodel (e) closet to bedroom with new window, remodel (e) bath and stack up washer/dryer. new bathroom, new dishwasher and floor finish at kitchen. approximately 750 sfDetails
unit #6, 4th fl - remodel (e) closet to bedroom with new window, remodel (e) bath and stack up washer/dryer. new bathroom, new dishwasher and floor finish at kitchen. approximately 750 sf | $89,000 | |
| Sep 18, 2026 | In progress filed Sep 2026, not yet issued | 720 Masonic Av | erect new type 5b 3 stories 2-unit + adu residence.Details
erect new type 5b 3 stories 2-unit + adu residence. | $450,000 | |
| Sep 11, 2026 | In progress filed Sep 2026, not yet issued | 650 Joost Av | rebuild partial exterior front stairs and landing in kind.Details
rebuild partial exterior front stairs and landing in kind. | $5,000 | |
| Sep 10, 2026 | In progress issued Sep 2026 | 1956 Fell St | O'reilly Construction | 2nd floor, remove existing laundry equipment, install new shower, vanity and toilet, no wall stud demolition or construction.Details
2nd floor, remove existing laundry equipment, install new shower, vanity and toilet, no wall stud demolition or construction. | $18,000 |
| Sep 9, 2026 | In progress filed Sep 2026, not yet issued | 1956 Fell St | 2nd flr. 1956 fell st. remodel (e) laundry to full bathroom w/stack-up washer and dryerDetails
2nd flr. 1956 fell st. remodel (e) laundry to full bathroom w/stack-up washer and dryer | $20,000 | |
| Sep 4, 2026 | In progress issued Oct 2026 | 258 Harvard St | Renovix Inc | 1st flr: remodel (e) floor space to media , bathroom, wet bar and laundry.2nd flr: remodel (e) kitchen, bath, and infill bathroom lightwell, new mini splitter hvac system.Details
1st flr: remodel (e) floor space to media , bathroom, wet bar and laundry.2nd flr: remodel (e) kitchen, bath, and infill bathroom lightwell, new mini splitter hvac system. | $98,700 |
| Aug 31, 2026 | In progress filed Aug 2026, not yet issued | 2600 Bryant St | to comply to planning notice of enforcement 2023-011363 enf at (e) vacant commerical spaces, replace (e) storefront and transom window; replace ceramic bulk head tile.Details
to comply to planning notice of enforcement 2023-011363 enf at (e) vacant commerical spaces, replace (e) storefront and transom window; replace ceramic bulk head tile. | $30,000 | |
| Aug 31, 2026 | Completed final sign-off Sep 2026 | 195 Eureka St | Allied Teamwork Construction Co | revision to pa# 202510217820 & 202006299335: provide wood step next to bedroom window, comply w/ eero.Details
revision to pa# 202510217820 & 202006299335: provide wood step next to bedroom window, comply w/ eero. | |
| Aug 27, 2026 | In progress filed Aug 2026, not yet issued | 286 Crescent Av | revision to approved permit #202605151399. 1/f, provide new sliding door, to rear. 2/f, remove wall at living room; new sliding door at rear wall, replace all windows.Details
revision to approved permit #202605151399. 1/f, provide new sliding door, to rear. 2/f, remove wall at living room; new sliding door at rear wall, replace all windows. | $23,000 | |
| Aug 27, 2026 | In progress filed Aug 2026, not yet issued | 678 15th Av | at 2/f unit, replace (e) rear windows with (n) sliding door w/concrete landing and steps to access rear yard.Details
at 2/f unit, replace (e) rear windows with (n) sliding door w/concrete landing and steps to access rear yard. | $2,500 | |
| Aug 25, 2026 | In progress filed Aug 2026, not yet issued | 734 Elizabeth St | full interior remodel for entre house per plan. new garage at front yard with roll-up door and new driveway. rear horizontal addition at 2/f and 3/f.Details
full interior remodel for entre house per plan. new garage at front yard with roll-up door and new driveway. rear horizontal addition at 2/f and 3/f. | $350,000 | |
| Aug 21, 2026 | In progress filed Aug 2026, not yet issued | 260 Minerva St | comply to nov #202656272: new adu per california gov't code section 65852.2. 1/f, modify (e) floor space into jadu (260a) include new bedroom, home office, bathroom, kitchen & laundry.Details
comply to nov #202656272: new adu per california gov't code section 65852.2. 1/f, modify (e) floor space into jadu (260a) include new bedroom, home office, bathroom, kitchen & laundry. | $130,000 | |
| Aug 18, 2026 | In progress issued Sep 2026 | 1725 16th Av | K & J General Construction | interior remodel, at 1st flr, remodel (e) floor space to (n)bedorooms, bathrooms, wetbar, and laundry at 2nd flr. remodel kitchen, bathroom and dining, new pantry, powder room, and bathroom, new inerior stair. ab112Details
interior remodel, at 1st flr, remodel (e) floor space to (n)bedorooms, bathrooms, wetbar, and laundry at 2nd flr. remodel kitchen, bathroom and dining, new pantry, powder room, and bathroom, new inerior stair. ab112 | $235,000 |
| Aug 14, 2026 | In progress issued Aug 2026 | 913 Pacific Av | Xinrong Construction Inc | revision to pa# 202510278204. at 2nd floor unit #913 pacific ave, relocate new bathroom per plan. change bedroom to home office.Details
revision to pa# 202510278204. at 2nd floor unit #913 pacific ave, relocate new bathroom per plan. change bedroom to home office. | $1,000 |
| Aug 7, 2026 | In progress issued Aug 2026 | 30 Elmhurst Dr | Pro Design Build And Construction Inc | at 1st floor: remodel existing floor space to bedroom, bath, family, and laundry; remodel kitchen and dining. at 2nd floor remodel existing bath to 2 new bathrooms. remodel existing master bathroom.Details
at 1st floor: remodel existing floor space to bedroom, bath, family, and laundry; remodel kitchen and dining. at 2nd floor remodel existing bath to 2 new bathrooms. remodel existing master bathroom. | $98,000 |
| Aug 7, 2026 | In progress issued Sep 2026 | 622 24th Av | at 2nd floor: remodel/relocate kitchen and dining. remove wall and install post and beam; new powder room and closet. at 3rd floor: remodel existing bath and add new bathroom.Details
at 2nd floor: remodel/relocate kitchen and dining. remove wall and install post and beam; new powder room and closet. at 3rd floor: remodel existing bath and add new bathroom. | $98,000 | |
| Aug 3, 2026 | Completed final sign-off Sep 2026 | 3086 Balboa St | Great Ocean Construction Inc. | to comply with nov #202659083. remove existing fire damaged stair and provide new stair to access rear yard and garage.Details
to comply with nov #202659083. remove existing fire damaged stair and provide new stair to access rear yard and garage. | $5,000 |
| Jul 29, 2026 | In progress filed Jul 2026, not yet issued | 65 Dunsmuir St | 1st floor: remodel existing floor space to bedroom, media, wet bar & laundry & bathrooms. 2nd floor: remodel existing kitchen & dining room, new powder room & new bathroom; remove walls and install post & beam system; and new interior stair. ab112Details
1st floor: remodel existing floor space to bedroom, media, wet bar & laundry & bathrooms. 2nd floor: remodel existing kitchen & dining room, new powder room & new bathroom; remove walls and install post & beam system; and new interior stair. ab112 | $217,000 | |
| Jul 22, 2026 | In progress issued Aug 2026 | 18 Talbert St | Mz Construction Company | 1st floor: remodel existing floor space to 2 new bedrooms, 2 new bathrooms, and laundry.Details
1st floor: remodel existing floor space to 2 new bedrooms, 2 new bathrooms, and laundry. | $114,000 |
| Jul 20, 2026 | In progress issued Aug 2026 | 44 Stonecrest Dr | Great Ocean Construction Inc. | 1/fl- remodel and relocate (e) kitchen, bathroom, and remove walls at dining area. replace rear small deck in kind. (n) laundry. 2/fl- remodel (e) bathrooms, replace all (e) windows in kind visible from street.Details
1/fl- remodel and relocate (e) kitchen, bathroom, and remove walls at dining area. replace rear small deck in kind. (n) laundry. 2/fl- remodel (e) bathrooms, replace all (e) windows in kind visible from street. | $137,000 |
| Jul 20, 2026 | In progress issued Aug 2026 | 66 Theresa St | K & J General Construction | revision 202603318611- (n) sliding door and window at 1st floor bedroom. 2/fl- (n) rear deck and sliding door. replace all windows in kindDetails
revision 202603318611- (n) sliding door and window at 1st floor bedroom. 2/fl- (n) rear deck and sliding door. replace all windows in kind | $19,500 |
| Jul 17, 2026 | In progress filed Jul 2026, not yet issued | 2242 32nd Av | 1st fl/ remodel existing 1st floor space to bedroom amd bathroom. add (n) 1-story addition at rear for (n) family at 2nd floor: remodel/relocate existing kitchen, bathroom and infill south lightwell, new bathroom and roof deck with stairs.Details
1st fl/ remodel existing 1st floor space to bedroom amd bathroom. add (n) 1-story addition at rear for (n) family at 2nd floor: remodel/relocate existing kitchen, bathroom and infill south lightwell, new bathroom and roof deck with stairs. | $250,000 | |
| Jul 16, 2026 | In progress filed Jul 2026, not yet issued | 1622 19th Av | revision to pa#202410152985. provide underpin to existing foundation per plan. identify new foundation location per plan.Details
revision to pa#202410152985. provide underpin to existing foundation per plan. identify new foundation location per plan. | $5,000 | |
| Jul 8, 2026 | In progress filed Jul 2026, not yet issued | 1165 Holloway Av | 1/f:remodel/excavate (e) space to bedrooms, bathrooms, home office and family. new west side lightwell. 2/f: full interior remodel for entire flr per plan, new stair to 1st and 3rd flr. remodel (e) attic space to new 3/f w/ bedrooms and bathrooms with dormers.Details
1/f:remodel/excavate (e) space to bedrooms, bathrooms, home office and family. new west side lightwell. 2/f: full interior remodel for entire flr per plan, new stair to 1st and 3rd flr. remodel (e) attic space to new 3/f w/ bedrooms and bathrooms with dormers. | $550,000 | |
| Jun 30, 2026 | In progress issued Jul 2026 | 62 Aquavista Wy | Pro Design Build And Construction Inc | revision to 202512010673 at 1st/f change bath layout, relocate closet per plan, new patio. 2nd/f: change kitchen & bath configuration per plan, replace all e) windows and add new skylightsDetails
revision to 202512010673 at 1st/f change bath layout, relocate closet per plan, new patio. 2nd/f: change kitchen & bath configuration per plan, replace all e) windows and add new skylights | $14,000 |
| Jun 29, 2026 | In progress issued Aug 2026 | 3253 Mission St | replace e storefront and doors, remove e wood post w new steel beam and post. change wet bar layout per plans.Details
replace e storefront and doors, remove e wood post w new steel beam and post. change wet bar layout per plans. | $15,000 | |
| Jun 25, 2026 | In progress filed Jun 2026, not yet issued | 24 Fairmount St | comply w/ nov #202292145, 202658134, 202312869, 202656770, 202292503: new adu per california government code section 65852.2 at 1/f, modify (e) unconditioned space into adu (24b), include new bedrooms, bathroom, dining, & kitchen. add new windows to side and rear.Details
comply w/ nov #202292145, 202658134, 202312869, 202656770, 202292503: new adu per california government code section 65852.2 at 1/f, modify (e) unconditioned space into adu (24b), include new bedrooms, bathroom, dining, & kitchen. add new windows to side and rear. | $129,800 | |
| Jun 24, 2026 | In progress filed Jun 2026, not yet issued | 1771 16th Av | new adu per state program.1/f: new conditioned space, rear 1 story addition. 2/f: repalce rear windows and new roof deck on 3/f. remodel/relcoate master bath, new door and new deck. legalize (e) front roof deck and door.Details
new adu per state program.1/f: new conditioned space, rear 1 story addition. 2/f: repalce rear windows and new roof deck on 3/f. remodel/relcoate master bath, new door and new deck. legalize (e) front roof deck and door. | $279,600 | |
| Jun 24, 2026 | In progress filed Jun 2026, not yet issued | 772 Delta St | comply to nov: 20207091(constructing a structure in backyard without a permit):-new exit passageway and modify/relocate existing stair for new exitDetails
comply to nov: 20207091(constructing a structure in backyard without a permit):-new exit passageway and modify/relocate existing stair for new exit | $20,000 | |
| Jun 22, 2026 | In progress issued Jul 2026 | 678 15th Av | Ryz Construction Inc | 2nd/f unit: remodel/relocate e) kitchen & dinning, new common bathroom, remodel e) bath & new laundry. no exterior workDetails
2nd/f unit: remodel/relocate e) kitchen & dinning, new common bathroom, remodel e) bath & new laundry. no exterior work | $53,000 |
| Jun 12, 2026 | In progress issued Jun 2026 | 40 Exeter St | revision to pa# 202601063281. at 1st floor: replace existing rear deteriorated foundation. at 2nd floor: add new powder room.Details
revision to pa# 202601063281. at 1st floor: replace existing rear deteriorated foundation. at 2nd floor: add new powder room. | $5,000 | |
| Jun 8, 2026 | In progress filed Jun 2026, not yet issued | 2111 Market St | route new ducts from (e) heat pump to new rooms; new lighting plan w/t-24. ref#: 202602065492Details
route new ducts from (e) heat pump to new rooms; new lighting plan w/t-24. ref#: 202602065492 | $5,000 | |
| Jun 8, 2026 | In progress filed Jun 2026, not yet issued | 100 Chaves Av | 1st flr: remodel (e) flr space to home office, bedroom, laundry and game room w/wetbar. replace (e) exterior rear step. 2nd flr: remodel (kitchen and bathroom, and (n) master bathroom).Details
1st flr: remodel (e) flr space to home office, bedroom, laundry and game room w/wetbar. replace (e) exterior rear step. 2nd flr: remodel (kitchen and bathroom, and (n) master bathroom). | $175,000 | |
| Jun 2, 2026 | In progress filed Jun 2026, not yet issued | 772 Delta St | erect a new detached one dwelling,one story no basement adu @ rear of main house.type 5-b comply to nov: 20207091(constructing a structure in backyard without a permit)Details
erect a new detached one dwelling,one story no basement adu @ rear of main house.type 5-b comply to nov: 20207091(constructing a structure in backyard without a permit) | $50,000 | |
| Jun 1, 2026 | In progress issued Aug 2026 | 400 Cordova St | Hungto Co Incorporation | 1/f. replace all exterior deterioated foundation in kind; add new bathroom and wet bar at (e) space, and remodel (e) bathroom.Details
1/f. replace all exterior deterioated foundation in kind; add new bathroom and wet bar at (e) space, and remodel (e) bathroom. | $120,000 |
| May 20, 2026 | In progress issued Jul 2026 | 622 24th Av | 1st/f: remodel e) fl space to n) home office, media rm, bath & laundry. wet bar.Details
1st/f: remodel e) fl space to n) home office, media rm, bath & laundry. wet bar. | $123,000 | |
| May 15, 2026 | In progress issued Jun 2026 | 286 Crescent Av | K & J General Construction | residential remodel. add media & family room, bedroom and bath. and laundry. 2nd fl. (n) wet bar, remodel (e) kitchen, new powder room. 3rd floor remodel (e) bath & add (n) bath.Details
residential remodel. add media & family room, bedroom and bath. and laundry. 2nd fl. (n) wet bar, remodel (e) kitchen, new powder room. 3rd floor remodel (e) bath & add (n) bath. | $198,000 |
| May 7, 2026 | In progress filed May 2026, not yet issued | 911 Pacific Av | replace all windows in kind- see plansDetails
replace all windows in kind- see plans | $30,000 | |
| May 7, 2026 | In progress issued Jun 2026 | 867 34th Av | Wing Construction Co. | 1st floor - remodel (e) flr to laundry, full bath, (n) corridor & wet bar. 2nd floor - remodel (e) kitchen, new rear deck and (n) sliding door @ (e) opening.Details
1st floor - remodel (e) flr to laundry, full bath, (n) corridor & wet bar. 2nd floor - remodel (e) kitchen, new rear deck and (n) sliding door @ (e) opening. | $45,000 |
| May 1, 2026 | Completed final sign-off Aug 2026 | 600 Kearny St | Acer-G Engineering | tenant improvement. (e) cafe merge with adjacent tenant space and modify to dining space. new accessible all gender restroom, and provide new opening from kitchen to dining.Details
tenant improvement. (e) cafe merge with adjacent tenant space and modify to dining space. new accessible all gender restroom, and provide new opening from kitchen to dining. | $30,000 |
| Apr 17, 2026 | In progress issued May 2026 | 515 29th St | Amador General Construction Inc | at 2nd floor, remodel (e) kitchenDetails
at 2nd floor, remodel (e) kitchen | $25,000 |
| Mar 31, 2026 | In progress issued Apr 2026 | 66 Theresa St | K & J General Construction | 1st flr: remodel (e) floor space to 1 master suite, media, wetbar and laundry. at 2nd flr: remodel (e) kitchen and dining and powder room. 3rd flr remodel (e) bathroom and add new bathroom.Details
1st flr: remodel (e) floor space to 1 master suite, media, wetbar and laundry. at 2nd flr: remodel (e) kitchen and dining and powder room. 3rd flr remodel (e) bathroom and add new bathroom. | $198,000 |
| Mar 25, 2026 | In progress issued Sep 2026 | 630 40th Av | Great Ocean Construction Inc. | relocate top unit to 1st floor, and merge 2nd, and 3rd floors as one unit (side two-story). side two-story addition to expand floor area at first and 2nd floors, roof deck deck; full remodel all three floors per plans; replace all windows. in-kind.Details
relocate top unit to 1st floor, and merge 2nd, and 3rd floors as one unit (side two-story). side two-story addition to expand floor area at first and 2nd floors, roof deck deck; full remodel all three floors per plans; replace all windows. in-kind. | $398,000 |
| Mar 23, 2026 | In progress issued May 2026 | 1205 10th Av | 1st fl unit 3. remodel and expand e floor space at basement to new kitchen, new bath, spiral stair. remodel e bath and remodel e living to bedroom and e kitchen to full bathDetails
1st fl unit 3. remodel and expand e floor space at basement to new kitchen, new bath, spiral stair. remodel e bath and remodel e living to bedroom and e kitchen to full bath | $126,000 | |
| Mar 23, 2026 | In progress filed Mar 2026, not yet issued | 2213 Bryant St | new adu per state govt code 65852.2 at first floor. modify (e) space into adu (2213a bryant st). include new bedroom, bathroom and kitchen.Details
new adu per state govt code 65852.2 at first floor. modify (e) space into adu (2213a bryant st). include new bedroom, bathroom and kitchen. | $118,000 | |
| Mar 18, 2026 | In progress issued May 2026 | 3112 Balboa St | unit 2 and 4: remodel/relocate kitchen and bath. remodel (e) space to 2 new bedrooms and new bathroom. new mini split heat pump. no exterior work. remove washer/dryer and laundry sink at 1st floor.Details
unit 2 and 4: remodel/relocate kitchen and bath. remodel (e) space to 2 new bedrooms and new bathroom. new mini split heat pump. no exterior work. remove washer/dryer and laundry sink at 1st floor. | $135,000 | |
| Mar 13, 2026 | In progress filed Mar 2026, not yet issued | 2334 Francisco St | revision to approved pa# 202505206859. 1/f, reconfigure kitchen layout per plan. 2/f: reconfigure wetbar, bath, laundry and master bath per plan. 3/f: reconfigure bedroom layout and relocate kitchen and dining, relocate skylights.Details
revision to approved pa# 202505206859. 1/f, reconfigure kitchen layout per plan. 2/f: reconfigure wetbar, bath, laundry and master bath per plan. 3/f: reconfigure bedroom layout and relocate kitchen and dining, relocate skylights. | $1,000 | |
| Mar 11, 2026 | In progress issued Mar 2026 | 45 Dalewood Wy | Acer-G Engineering | remodel existing kitchen and bathrooms; remove wall at dining; new closet at entry.Details
remodel existing kitchen and bathrooms; remove wall at dining; new closet at entry. | $89,000 |
| Mar 10, 2026 | In progress issued Apr 2026 | 337 Jules Av | to comply w/ nov# 202544786, new adu (337-a) per ca government code section 65852.2. convert (e) one story detached garage to adu (337-a) with bedroom, bath & kitchen. 485 sf.Details
to comply w/ nov# 202544786, new adu (337-a) per ca government code section 65852.2. convert (e) one story detached garage to adu (337-a) with bedroom, bath & kitchen. 485 sf. | $92,875 | |
| Mar 9, 2026 | In progress filed Mar 2026, not yet issued | 1730 44th Av | 1 new adu (ca state program) on 1/f. modifty (e) conditioned space into adu (1730a 44th ave) including (e) bedrooms, (e) bath & (n) kitchen. rear new spiral stair from 2/f to yard for yard access.Details
1 new adu (ca state program) on 1/f. modifty (e) conditioned space into adu (1730a 44th ave) including (e) bedrooms, (e) bath & (n) kitchen. rear new spiral stair from 2/f to yard for yard access. | $60,000 | |
| Feb 25, 2026 | In progress issued Apr 2026 | 3710 Webster St | Pro Design Build And Construction Inc | 1/f: remodel (e) family floor space to new bedroom, new bathroom, webar. relocate laundry.Details
1/f: remodel (e) family floor space to new bedroom, new bathroom, webar. relocate laundry. | $75,000 |
| Feb 25, 2026 | Expired or cancelled withdrawn May 2026 | 913 Pacific Av | revision to permit 202510278204. clarify scope of work to include removing existing finishes to walls and ceiling to 2nd and 3rd floor 2 units (units 913 and 915). replace all windows in kind.Details
revision to permit 202510278204. clarify scope of work to include removing existing finishes to walls and ceiling to 2nd and 3rd floor 2 units (units 913 and 915). replace all windows in kind. | $50,600 | |
| Feb 20, 2026 | In progress issued Mar 2026 | 150 France Av | at 1st flr, remodel (e) floor space to two new bedroom, new bathroom, media and wet bar.Details
at 1st flr, remodel (e) floor space to two new bedroom, new bathroom, media and wet bar. | $123,000 | |
| Feb 13, 2026 | Completed final sign-off Jun 2026 | 716 Masonic Av | revision to pa# 202505126253: relocate adu furnace inside adu per plan. remove window.Details
revision to pa# 202505126253: relocate adu furnace inside adu per plan. remove window. | $500 | |
| Feb 6, 2026 | In progress issued Mar 2026 | 2111 Market St | Shao Fat Construction Inc | tenant improvement remodel (e) office to massage office w/ new therapy tooms, break room, restroom. mep under separate permit.Details
tenant improvement remodel (e) office to massage office w/ new therapy tooms, break room, restroom. mep under separate permit. | $50,000 |
| Jan 30, 2026 | In progress issued Jun 2026 | 1438 Van Dyke Av | Ke Construction Co. | revision to bpa#202211075966, reconfigure front stair to basement adu and reconfigure from bath & utility room layout, relocate new steps @rear lightwell; replace interior posts and footingsDetails
revision to bpa#202211075966, reconfigure front stair to basement adu and reconfigure from bath & utility room layout, relocate new steps @rear lightwell; replace interior posts and footings | $100 |
| Jan 28, 2026 | In progress issued Jun 2026 | 271 23rd Av | Acer-G Engineering | revision to permit 202508294266. at 2nd floor, remove wall at hall way.Details
revision to permit 202508294266. at 2nd floor, remove wall at hall way. | $5,000 |
| Jan 28, 2026 | In progress issued May 2026 | 40 Exeter St | new dwelling unit (adu) per california code section 65852.2, 1/f modify (e) space into adu (40a exeter st) includes (n) bedroom, (n) bath and (n) kitchen. new retaining wall at rear yard for adu windows. remove (e) interior stair.Details
new dwelling unit (adu) per california code section 65852.2, 1/f modify (e) space into adu (40a exeter st) includes (n) bedroom, (n) bath and (n) kitchen. new retaining wall at rear yard for adu windows. remove (e) interior stair. | $116,000 | |
| Jan 28, 2026 | Completed final sign-off Aug 2026 | 6427 California St | Great Ocean Construction Inc. | revision to pa 202405152200 @ 2nd fl - reconfigure front closet & powder room layout; (e) front door and window to remain @ the same location. no change to plumbing fixturesDetails
revision to pa 202405152200 @ 2nd fl - reconfigure front closet & powder room layout; (e) front door and window to remain @ the same location. no change to plumbing fixtures | |
| Jan 27, 2026 | In progress issued Apr 2026 | 647 24th Av | Zhuo Zhang Construction Inc | revision to 202511240355. remodel e 1st fl to family, bathroom, bedroom, new 1 level rear deck, replace 3 rear and side windowsDetails
revision to 202511240355. remodel e 1st fl to family, bathroom, bedroom, new 1 level rear deck, replace 3 rear and side windows | $135,000 |
| Jan 27, 2026 | In progress filed Jan 2026, not yet issued | 4220 California St | remodel existing office spaces into 1 single family dwelling at first and 2nd floor remodel space to kitchen, living, bedrooms and bathroomsDetails
remodel existing office spaces into 1 single family dwelling at first and 2nd floor remodel space to kitchen, living, bedrooms and bathrooms | $157,000 | |
| Jan 26, 2026 | In progress issued Feb 2026 | 1327 Church St | at 3/f, remove (e) closet at bedroom and install (n) sliding door for closet at other bedroom.Details
at 3/f, remove (e) closet at bedroom and install (n) sliding door for closet at other bedroom. | $3,500 | |
| Jan 23, 2026 | Completed final sign-off Aug 2026 | 359 31st Av | C & H Home Construction | 2/f: remove walls between dining/living and kitchen. 3/f: remodel (e) kitchen and remove walls between dining/living and kitchen.Details
2/f: remove walls between dining/living and kitchen. 3/f: remodel (e) kitchen and remove walls between dining/living and kitchen. | $70,000 |
| Jan 21, 2026 | Completed final sign-off Jun 2026 | 2679 Alemany Bl | San Francico Rg Solution | 1st/f: remodel e) floor space to family rm, bedroom, & bathroom. 2nd/f: remodel e) baths & kitchenDetails
1st/f: remodel e) floor space to family rm, bedroom, & bathroom. 2nd/f: remodel e) baths & kitchen | $158,000 |
| Jan 16, 2026 | Completed final sign-off Apr 2026 | 173 Harold Av | High Level Construction Co | 1st fl: add wetbar at (e) playroom and remodel part of (e) garage to new media room with new bathroomDetails
1st fl: add wetbar at (e) playroom and remodel part of (e) garage to new media room with new bathroom | $65,000 |
| Jan 15, 2026 | In progress issued Aug 2026 | 407 Teresita Bl | Brendan J Uniacke Construction | full remodel (e) 3 story bldg. (n) cantilever decks w/ sliding doors. infill (e) lightwell and replace front window & exterior wall finishes. remodel 1st flr space to (n) family w/ bathroom & wetbar. 2nd: create master suite and laundry. 3rd: remodel kitchen bathroom, lightwell infill. and skylightsDetails
full remodel (e) 3 story bldg. (n) cantilever decks w/ sliding doors. infill (e) lightwell and replace front window & exterior wall finishes. remodel 1st flr space to (n) family w/ bathroom & wetbar. 2nd: create master suite and laundry. 3rd: remodel kitchen bathroom, lightwell infill. and skylights | $450,000 |
| Jan 13, 2026 | In progress issued May 2026 | 459 Valley St | Zhuo Zhang Construction Inc | rear horizontal addition @ basement, 1st floor and 2nd floor. new roof decks and rear 1-level deck. full interior remodel for the entire house per plan. new garage at 1st floor with roll up door and new driveway. replace all front window and doorsDetails
rear horizontal addition @ basement, 1st floor and 2nd floor. new roof decks and rear 1-level deck. full interior remodel for the entire house per plan. new garage at 1st floor with roll up door and new driveway. replace all front window and doors | $450,000 |
| Jan 9, 2026 | In progress issued Jan 2026 | 911 Pacific Av | Shuwen Construction Co | 1st/f unit (911 pacific av) remodel e) kitchen & bathroom, add new bathroom & furnace. infill 2 windows.Details
1st/f unit (911 pacific av) remodel e) kitchen & bathroom, add new bathroom & furnace. infill 2 windows. | $89,000 |
| Jan 6, 2026 | In progress issued Jan 2026 | 200 Cayuga Av | All Best Buildrs.Inc./All Trusty Bldrs. | 1st fl: remodel (e) kitchen, laundry, bathrooms and new wetbar. 2nd fl: remodel (e) bathroom. add new bath and skylights.Details
1st fl: remodel (e) kitchen, laundry, bathrooms and new wetbar. 2nd fl: remodel (e) bathroom. add new bath and skylights. | $188,900 |
| Dec 30, 2025 | Completed final sign-off Jul 2026 | 522 26th Av | revision to pa #2025-0702-0068: at 2nd fl, relocate washer/dryer from bathroom to living areaDetails
revision to pa #2025-0702-0068: at 2nd fl, relocate washer/dryer from bathroom to living area | ||
| Dec 19, 2025 | In progress filed Dec 2025, not yet issued | 1574 35th Av | 1/fl remodel (e) bedroom and bathroom, add (n) family room and wet bar at 2nd floor. remodel (e) kitchen and bathroom. add (n) bathroom and office. (n) infill lightwells and replace (e) interior stairsDetails
1/fl remodel (e) bedroom and bathroom, add (n) family room and wet bar at 2nd floor. remodel (e) kitchen and bathroom. add (n) bathroom and office. (n) infill lightwells and replace (e) interior stairs | $192,300 | |
| Dec 17, 2025 | Completed final sign-off Jul 2026 | 678 23rd Av | Yiu Cheong Construction Co Inc | revision 202503031449- add (n) 2x skylights at living room visible from street.Details
revision 202503031449- add (n) 2x skylights at living room visible from street. | $5,000 |
| Dec 17, 2025 | In progress issued Jan 2026 | 2067 Quesada Av | Newsontec General | revision 201505196632-s1- add (n) walk in and full bathroom at media room, relocate laundry to garageDetails
revision 201505196632-s1- add (n) walk in and full bathroom at media room, relocate laundry to garage | $20,000 |
| Dec 15, 2025 | In progress issued Jan 2026 | 2829 Laguna St | Kalix Inc Dbalara Construction | 2/fl-remodel (e) kitchen , bathroom and add (n) foyer for unit 2829 lagunaDetails
2/fl-remodel (e) kitchen , bathroom and add (n) foyer for unit 2829 laguna | $55,000 |
| Dec 8, 2025 | Expired or cancelled cancelled Apr 2026 | 4935 Anza St | add 3 adu on 1st florr of the apartment.Details
add 3 adu on 1st florr of the apartment. | $280,000 | |
| Dec 2, 2025 | In progress filed Dec 2025, not yet issued | 4735 Mission St | change of use from retail (m) to restuarant (b). t.i. remodel e) office/retail to restuarant w/ new cashier, dining, kitchen equipments, fixtures, finishesDetails
change of use from retail (m) to restuarant (b). t.i. remodel e) office/retail to restuarant w/ new cashier, dining, kitchen equipments, fixtures, finishes | $80,000 | |
| Dec 1, 2025 | In progress issued Apr 2026 | 271 23rd Av | Acer-G Engineering | new dwelling unit adu per ca government code section 65852.2 at 1/f modify (e) unconditioned space into adu (271a) includes new bedrooms, bathroom, dining and kitchen.Details
new dwelling unit adu per ca government code section 65852.2 at 1/f modify (e) unconditioned space into adu (271a) includes new bedrooms, bathroom, dining and kitchen. | $159,000 |
| Dec 1, 2025 | Completed final sign-off Jun 2026 | 3086 Balboa St | Great Ocean Construction Inc. | at 2nd fl, interior remodel, reodel (e) kitchen, bathroom, new laundry and remodel (e) living to bedroom.Details
at 2nd fl, interior remodel, reodel (e) kitchen, bathroom, new laundry and remodel (e) living to bedroom. | $87,000 |
| Dec 1, 2025 | In progress issued Jan 2026 | 62 Aquavista Wy | Pro Design Build And Construction Inc | 1/f: remodel (e) space to laundry/wetbar, family bathrooms and bedrooms. 2/f: remodel (e) kitchen and bathroom. interior remodel only.Details
1/f: remodel (e) space to laundry/wetbar, family bathrooms and bedrooms. 2/f: remodel (e) kitchen and bathroom. interior remodel only. | $187,000 |
| Nov 24, 2025 | In progress issued Dec 2025 | 24 Fairmount St | Bay C T Construction Inc. | revision 202505096209 and 202311080452 at 2nd floor change bathroom fixture layout and 3rd and 2nd floor add (n) windows at (e) rear bedroomsDetails
revision 202505096209 and 202311080452 at 2nd floor change bathroom fixture layout and 3rd and 2nd floor add (n) windows at (e) rear bedrooms | $3,400 |
| Nov 24, 2025 | Completed final sign-off Jun 2026 | 716 Masonic Av | revision 202506178905- 2nd and 3rd floor change home office and study to bedrooms and change kitchen layout per plans. ref permits 202504094028 & 202504240979Details
revision 202506178905- 2nd and 3rd floor change home office and study to bedrooms and change kitchen layout per plans. ref permits 202504094028 & 202504240979 | ||
| Nov 24, 2025 | In progress issued Dec 2025 | 647 24th Av | Zhuo Zhang Construction Inc | 1st floor (n) wall and (n) interior stair at 2nd floor, remodel (e) kitchen and bathroom and bedroom at 3rd floor. remodel (e) bathroom and add (n) laundry and bathroomDetails
1st floor (n) wall and (n) interior stair at 2nd floor, remodel (e) kitchen and bathroom and bedroom at 3rd floor. remodel (e) bathroom and add (n) laundry and bathroom | $187,000 |
| Nov 24, 2025 | Completed final sign-off Apr 2026 | 2831 Bryant St | O'reilly Construction | rebuild (e) exterior front stair and landing and (n) handrailsDetails
rebuild (e) exterior front stair and landing and (n) handrails | $18,000 |
| Nov 18, 2025 | In progress issued Nov 2025 | 5828 California St | Yiu Cheong Construction Co Inc | revision to pa #202505146492. replace rear pop-up home office foundation in kind. change retaining wall hight to reflect existing condition.Details
revision to pa #202505146492. replace rear pop-up home office foundation in kind. change retaining wall hight to reflect existing condition. | $5,000 |
| Nov 15, 2025 | In progress issued Jun 2026 | 450 Urbano Dr | Simply Building Inc | new dwelling unit (adu unit 450a) per california government code section 65852.2 at rear yard constrcut a 1-story attached adu with bedrooms, baths, kitchen and deck, 991 sf.Details
new dwelling unit (adu unit 450a) per california government code section 65852.2 at rear yard constrcut a 1-story attached adu with bedrooms, baths, kitchen and deck, 991 sf. | $258,000 |
| Nov 14, 2025 | Completed final sign-off Jan 2026 | 2064 Union St | Shao Fat Construction Inc | 2/f: change of use from (e) office to massage therapy office with new therapy rooms, fixtures, and finishes. mep deferred.Details
2/f: change of use from (e) office to massage therapy office with new therapy rooms, fixtures, and finishes. mep deferred. | $15,000 |
| Nov 13, 2025 | Completed final sign-off Apr 2026 | 1711 Haight St | O'reilly Construction | add existing vacant commercial space (1715 haight st.) to (e) adjacent commercial space (1711 haight st.) no exterior changes. new massage rooms and lighting, (e) hvac systemDetails
add existing vacant commercial space (1715 haight st.) to (e) adjacent commercial space (1711 haight st.) no exterior changes. new massage rooms and lighting, (e) hvac system | $50,000 |
| Nov 10, 2025 | Completed final sign-off May 2026 | 800 26th Av | Acer-G Engineering | at 1/f: ref (e) east foundation in kind per plan. add structural sheathing to that wallDetails
at 1/f: ref (e) east foundation in kind per plan. add structural sheathing to that wall | $5,000 |
| Nov 10, 2025 | In progress filed Nov 2025, not yet issued | 1686 24th Av | 2/f: remodel (e) master bathroom to new walk in closet.Details
2/f: remodel (e) master bathroom to new walk in closet. | $20,000 | |
| Nov 4, 2025 | In progress issued Nov 2025 | 647 24th Av | remove interior wall finishes to install insulation install 5/8 inch gypsum-x board after insulation completed. finish and paint. all non structural workDetails
remove interior wall finishes to install insulation install 5/8 inch gypsum-x board after insulation completed. finish and paint. all non structural work | $30,000 | |
| Nov 4, 2025 | In progress issued Dec 2025 | 526 05th Av | Guardian Remodeling Construction | 1/f: remodel (e) space to bedroom, full bathroom and family room, and new stair to 2/f and 3/f. 2/f and 3/f: remodel (e) kitchen and bathroom. add new bathroom on 2/f.Details
1/f: remodel (e) space to bedroom, full bathroom and family room, and new stair to 2/f and 3/f. 2/f and 3/f: remodel (e) kitchen and bathroom. add new bathroom on 2/f. | $178,000 |
| Nov 4, 2025 | Completed final sign-off Jul 2026 | 3893 24th St | Shao Fat Construction Inc | ti remodel (e) retail space to (n) massage therapy rooms, reception, all gender restroom, fixtures, and finishes.Details
ti remodel (e) retail space to (n) massage therapy rooms, reception, all gender restroom, fixtures, and finishes. | $50,000 |
| Oct 27, 2025 | In progress issued Nov 2025 | 913 Pacific Av | Ren Construction Inc | units 913 and 915- 2 & 3/fl- remodel (e) kitchen and bathrooms, add (n) bathroom to each unit and (n) furnaceDetails
units 913 and 915- 2 & 3/fl- remodel (e) kitchen and bathrooms, add (n) bathroom to each unit and (n) furnace | $110,786 |
| Oct 23, 2025 | In progress filed Oct 2025, not yet issued | 89 Farallones St | comply to nov#202536989 & 202536877. new dwelling unit(adu)(48a) per government code section 65852.2 at 1st floor, new unit included new bedroom, bathroom, home office and kitchen. legalize existing deck and stairs as yard access. legalize rear 1-story addition.Details
comply to nov#202536989 & 202536877. new dwelling unit(adu)(48a) per government code section 65852.2 at 1st floor, new unit included new bedroom, bathroom, home office and kitchen. legalize existing deck and stairs as yard access. legalize rear 1-story addition. | $75,000 | |
| Oct 21, 2025 | In progress issued Nov 2025 | 130 Meadowbrook Dr | Simply Building Inc | 1st fl: remodel e 1st fl space to laundry/wetbar, family and remodel e master suite. 2nd fl remodel e kitchen, bath, int stair and new bath. replace all e windows, infill south lightwellDetails
1st fl: remodel e 1st fl space to laundry/wetbar, family and remodel e master suite. 2nd fl remodel e kitchen, bath, int stair and new bath. replace all e windows, infill south lightwell | $187,000 |
| Oct 21, 2025 | Completed final sign-off Jul 2026 | 1 Marview Wy | O'reilly Construction | at 1/f: remodel (e) 1/f spacew to family and remodel (e) master ste. at 2/f: remodel (e) kitchen and bathroom. work per plan.Details
at 1/f: remodel (e) 1/f spacew to family and remodel (e) master ste. at 2/f: remodel (e) kitchen and bathroom. work per plan. | $178,565 |
| Oct 21, 2025 | Completed final sign-off Sep 2026 | 195 Eureka St | Allied Teamwork Construction Co | revision to pa 202006299335 to reflect correct (e) garage size it takes up full width of lot and adjust floor plan per plansDetails
revision to pa 202006299335 to reflect correct (e) garage size it takes up full width of lot and adjust floor plan per plans | |
| Oct 7, 2025 | Completed final sign-off Feb 2026 | 129 Meadowbrook Dr | Chen Herman Construction | at 1st fl, remodel ground floor to add family room and new closets. bedroom and full bath existing.Details
at 1st fl, remodel ground floor to add family room and new closets. bedroom and full bath existing. | $50,000 |