31 permits since 2000 (engineer on 29 permits, architect on 2 permits): 20 completed, 3 never finaled, 8 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jan 21, 2025 | Completed final sign-off Oct 2025 | 31 Cityview Wy | Rt Quality Construction Services Inc, Global Construction Services Inc | kitchen remodel & structural modification relocate gas line to service stove new location, bring kitchen to electrical codeDetails
kitchen remodel & structural modification relocate gas line to service stove new location, bring kitchen to electrical code | $45,000 |
| Jun 21, 2024 | Never finaled issued Jan 2020, no final | 905 Ashbury St | mandatory soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4.Details
mandatory soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4. | $120,000 | |
| Feb 22, 2022 | Completed final sign-off Jul 2024 | 260 Townsend St | Famand Inc Dba Indoor Environmental Serv | install 2 piece water cooled scroll chiller at basement level replace like for like indoor boilers at rooftop mechanical room. replace like for like cooling tower at rooftop level. includes (4) pumps (2) expansion tanks at rooftop.Details
install 2 piece water cooled scroll chiller at basement level replace like for like indoor boilers at rooftop mechanical room. replace like for like cooling tower at rooftop level. includes (4) pumps (2) expansion tanks at rooftop. | $532,368 |
| Jun 8, 2021 | Expired or cancelled withdrawn Jul 2023 | 550 18th Av | garage conversion: adding 388 sf of new conditioned space: new living rm & bathroom @ garage level. sprinkler permit separated.Details
garage conversion: adding 388 sf of new conditioned space: new living rm & bathroom @ garage level. sprinkler permit separated. | $100,000 | |
| Mar 22, 2021 | Completed final sign-off Apr 2022 | 1501 Quesada Av | enlarge deck 30in less on grade to sidewalk and add electric outlet on exterior. enlarge deck entrance doorway to deck from kitchen. reinforce support beams on existing overheng room. new deck landing and stair configuration per planas.Details
enlarge deck 30in less on grade to sidewalk and add electric outlet on exterior. enlarge deck entrance doorway to deck from kitchen. reinforce support beams on existing overheng room. new deck landing and stair configuration per planas. | $50,000 | |
| Nov 20, 2020 | Completed final sign-off Apr 2021 | 1322 Funston Av | removal of central post under kitchen balcony. replce corner posts & cross beamDetails
removal of central post under kitchen balcony. replce corner posts & cross beam | $2,000 | |
| Sep 14, 2020 | Completed final sign-off Apr 2021 | 1465 South Van Ness Av | Todd Felix Costanza | replace front stairs, to comply with his nov #202043661 dated 8/17/2020Details
replace front stairs, to comply with his nov #202043661 dated 8/17/2020 | $30,000 |
| Aug 20, 2020 | Expired or cancelled cancelled Jan 2026 | 1744 Palou Av | to replace damaged posts, replace garage door, rails, & door. all replacements to be "in-like-kind" only. call inspector @ start of sDetails
to replace damaged posts, replace garage door, rails, & door. all replacements to be "in-like-kind" only. call inspector @ start of s | $18,000 | |
| Feb 21, 2020 | Expired or cancelled withdrawn Nov 2020 | 2506 28th Av | add a deck to the rear of the building 2nd floor with stair to gain access to the rear yard. adu under pa# 202001272826.Details
add a deck to the rear of the building 2nd floor with stair to gain access to the rear yard. adu under pa# 202001272826. | $20,000 | |
| Jan 27, 2020 | Expired or cancelled withdrawn Nov 2020 | 2506 28th Av | add adu per ord# 95-17. convert the 1st floor to a 2 bedroom, 1 bathroom and 1 kitchen/dining room. lower the floor to gain the required ceiling height.Details
add adu per ord# 95-17. convert the 1st floor to a 2 bedroom, 1 bathroom and 1 kitchen/dining room. lower the floor to gain the required ceiling height. | $80,000 | |
| Nov 5, 2019 | Completed final sign-off Dec 2020 | 2667 18th Av | add 2 solar powered skylights side by side in the dining rm, each 45 1/2 9inch by 46 1/2 inDetails
add 2 solar powered skylights side by side in the dining rm, each 45 1/2 9inch by 46 1/2 in | $5,580 | |
| Oct 3, 2019 | Completed final sign-off Jun 2020 | 2102 Baker St | unit 2100 - replace 2 posts and 1 beam ref pa 2019-0702-4976.to comply with complaint 201986471 & 201980581Details
unit 2100 - replace 2 posts and 1 beam ref pa 2019-0702-4976.to comply with complaint 201986471 & 201980581 | $5,000 | |
| Sep 20, 2019 | Never finaled issued Sep 2019, no final | 1804 Ellis St | Axis Construction | revision to app#201905100346. local shearwall analysis at east elevation due to dry rot repair. n/a for maherDetails
revision to app#201905100346. local shearwall analysis at east elevation due to dry rot repair. n/a for maher | $15,000 |
| Aug 14, 2019 | Never finaled issued Nov 2019, no final | 144 Belgrave Av | Capomastro Group:Acalifornia Corp. | enlarge kitchen, relocate laundry, relocate e master bath to e master closet and visa versa relocate master bedroom door revision 201907307335Details
enlarge kitchen, relocate laundry, relocate e master bath to e master closet and visa versa relocate master bedroom door revision 201907307335 | $25,000 |
| Aug 8, 2019 | Completed final sign-off Jul 2020 | 1828 29th Av | kitchen remodel. remove wall between dining room and kitchen.Details
kitchen remodel. remove wall between dining room and kitchen. | $30,000 | |
| May 22, 2019 | Completed final sign-off Sep 2020 | 260 Clara St | Axis Construction | voluntary shear wall repairs and upgrade according to engineer plans. work not visible from the street. interior shear walls and rear exterior shear wall.Details
voluntary shear wall repairs and upgrade according to engineer plans. work not visible from the street. interior shear walls and rear exterior shear wall. | $185,750 |
| Nov 29, 2018 | Completed final sign-off Dec 2019 | 367 Moscow St | Home Quality Remodeling | full kitchen remodel removing a load bearing wall like for loke full bathroom remodelDetails
full kitchen remodel removing a load bearing wall like for loke full bathroom remodel | $40,000 |
| Nov 7, 2018 | Completed final sign-off Jun 2019 | 69 Teddy Av | Gmbc Construction Inc | remove load-bearing wall and installing header, raise a headrDetails
remove load-bearing wall and installing header, raise a headr | $30,000 |
| Oct 3, 2018 | Expired or cancelled cancelled Jan 2026 | 1139 Lake St | revision to structural and architectural plans due to (1) removal of proposed new windows to comply wiht permit # 2018-0802-6222 (2) on-site conditions requiring changesposts and footing associated with permit# 2017-0324-2302, (3) arch changes based on on-site conditions.Details
revision to structural and architectural plans due to (1) removal of proposed new windows to comply wiht permit # 2018-0802-6222 (2) on-site conditions requiring changesposts and footing associated with permit# 2017-0324-2302, (3) arch changes based on on-site conditions. | ||
| Aug 7, 2018 | Expired or cancelled cancelled Jan 2026 | 929 Oak St | soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4.Details
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4. | $120,000 | |
| Aug 2, 2018 | Completed final sign-off Feb 2019 | 1240 21st Av | Sft Construction Corp | soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4.Details
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4. | $80,000 |
| May 17, 2018 | Completed final sign-off Jun 2020 | 576 28th St | revision to pa 2016-1026-1224 change hardy frames to simpson moment frames, change deck joist orientation due to (e) grade being lowered found in design changed to accomodate elevated slab with perimeter foundation. changed beam @ living rm ceiling to w8 from psl 14" to allow max heigt at ceilingDetails
revision to pa 2016-1026-1224 change hardy frames to simpson moment frames, change deck joist orientation due to (e) grade being lowered found in design changed to accomodate elevated slab with perimeter foundation. changed beam @ living rm ceiling to w8 from psl 14" to allow max heigt at ceiling | ||
| May 1, 2018 | Completed final sign-off Apr 2019 | 1755 Filbert St | Good Neighbor Construction | unit #2: non-loading bearing wall at first floor and shearwall analysis.Details
unit #2: non-loading bearing wall at first floor and shearwall analysis. | $5,000 |
| Jan 31, 2018 | Completed final sign-off May 2018 | 1995 Turk St | Green Metro Inc | demo non load bearing wall btw kitchen/dining. modifu load bearing wall at kitchen, new kitchen cabinets. elec outlets for kit., living rm, bedrooms. (sep ele permit) close (e) dooreway to turn (e) living tn to bedroom 2. close (e) doorway btw bath & closet- bldg has no fire alarms orDetails
demo non load bearing wall btw kitchen/dining. modifu load bearing wall at kitchen, new kitchen cabinets. elec outlets for kit., living rm, bedrooms. (sep ele permit) close (e) dooreway to turn (e) living tn to bedroom 2. close (e) doorway btw bath & closet- bldg has no fire alarms or | $50,000 |
| Dec 26, 2017 | Completed final sign-off Feb 2018 | 1322 Funston Av | make attic a storage space: add 2 x 10 joists to attic floor. add a ladder.Details
make attic a storage space: add 2 x 10 joists to attic floor. add a ladder. | $9,000 | |
| Sep 15, 2017 | Expired or cancelled withdrawn Jul 2022 | 874 Fell St | comply w/ nov #201990001: structural engineering design for soft story retrofit of the buildng. the target story retrofit is through the addition of plywood shear walls and simpson moment frame. basement improvement to allow 9' ceiling height.Details
comply w/ nov #201990001: structural engineering design for soft story retrofit of the buildng. the target story retrofit is through the addition of plywood shear walls and simpson moment frame. basement improvement to allow 9' ceiling height. | $20,000 | |
| Aug 31, 2017 | Completed final sign-off Jul 2020 | 625 Cole St | Olive Remodeling | soft story retrofit per sfebc chapter 4d, 2016 cebc appendix a-4.Details
soft story retrofit per sfebc chapter 4d, 2016 cebc appendix a-4. | $20,000 |
| Jun 1, 2017 | Completed final sign-off Apr 2018 | 1750 Sutter St | Synerforce Construction | at (e) 3-story bldg w/ (e) footprint: repair the damaged (e) deck in unit #305 - remove all (e) deck & guardrails. replace any decayed sheating & framing members. install all (n) rim joists & blocking. no change-same location & same size.Details
at (e) 3-story bldg w/ (e) footprint: repair the damaged (e) deck in unit #305 - remove all (e) deck & guardrails. replace any decayed sheating & framing members. install all (n) rim joists & blocking. no change-same location & same size. | $4,500 |
| Jan 12, 2017 | Completed final sign-off Mar 2018 | 643 Mangels Av | (all following structural const plans to be done by lic engineer). horiz & basement add @ rear/lower level. remodel(e)interior main level, add(n)staircase. (n)master bed/bath suite @ lower level. build out basement level w/(2)(n)bedrooms & (1)(n)bathroom. stepped structure @ rear w/(2)roof decksDetails
(all following structural const plans to be done by lic engineer). horiz & basement add @ rear/lower level. remodel(e)interior main level, add(n)staircase. (n)master bed/bath suite @ lower level. build out basement level w/(2)(n)bedrooms & (1)(n)bathroom. stepped structure @ rear w/(2)roof decks | $125,000 | |
| Oct 20, 2016 | Expired or cancelled cancelled Aug 2018 | 1220 Bowdoin St | deck demolition, build a new deck. to comply with n.o.v. #201628851, item #2, dated 8/15/2016Details
deck demolition, build a new deck. to comply with n.o.v. #201628851, item #2, dated 8/15/2016 | $15,000 | |
| Aug 15, 2016 | Completed final sign-off Oct 2016 | 2002 03rd St | B Kohl Construction | wall demolition & new interior wall, hardwood flooring, tile, toilets,new 30a/240v circuit for dryer, lighting realication, 6 new receptacles, 2 new switches.Details
wall demolition & new interior wall, hardwood flooring, tile, toilets,new 30a/240v circuit for dryer, lighting realication, 6 new receptacles, 2 new switches. | $25,000 |