Prasanth N. Tanikella
- Listed as
- engineer
- Firm
- Zenith Engineers
- Based in
- Hayward
- On San Francisco permits
- Jan 2017 to Oct 2024
22 permits since 2000 (engineer on 22 permits): 16 completed, 2 in progress, 3 never finaled, 1 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Oct 15, 2024 | In progress issued Oct 2024 | 1342 Revere Av | revision to pa #202011309880 & 202304115461. rebuilding the demolition portion of the existing main building in the rear of the building.Details
revision to pa #202011309880 & 202304115461. rebuilding the demolition portion of the existing main building in the rear of the building. | $20,000 | |
| Jun 21, 2024 | Never finaled issued Jan 2020, no final | 905 Ashbury St | mandatory soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4.Details
mandatory soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4. | $120,000 | |
| Nov 17, 2023 | Completed final sign-off Sep 2024 | 360 Missouri St | Reliable Construction Inc | replacement of (e) rear egress stair like-to-likeDetails
replacement of (e) rear egress stair like-to-like | $35,000 |
| Nov 13, 2023 | In progress filed Nov 2023, not yet issued | 3615 Clement St | (e) rear deck at 2nd floor has dry rot in columns and beams. the columns, beams will be replaced. joists will be revised. new foundation. new knee braces.Details
(e) rear deck at 2nd floor has dry rot in columns and beams. the columns, beams will be replaced. joists will be revised. new foundation. new knee braces. | $25,000 | |
| Nov 13, 2023 | Completed final sign-off Feb 2024 | 760 San Jose Av | Reliable Construction Inc | existing stiar at the front of the building is damaged due to a vehicle collision. the existing brick stair will be full demolished and rebuilt using wood construction, in kind. revision to bpa#202310178836Details
existing stiar at the front of the building is damaged due to a vehicle collision. the existing brick stair will be full demolished and rebuilt using wood construction, in kind. revision to bpa#202310178836 | $25,000 |
| Nov 2, 2017 | Completed final sign-off Jul 2019 | 1270 Church St | Sederap's Drywall Inc. | add (2) additional dwelling units on the ground floor per ordinance 162-16. sprinklers deferred.Details
add (2) additional dwelling units on the ground floor per ordinance 162-16. sprinklers deferred. | $80,000 |
| Nov 2, 2017 | Completed final sign-off Jul 2019 | 1270 Church St | Sederap's Drywall Inc. | voluntary seismic upgrade soft story for strengthening per ab-094.in connection with adu permit # 201711022974 sDetails
voluntary seismic upgrade soft story for strengthening per ab-094.in connection with adu permit # 201711022974 s | $25,000 |
| Sep 20, 2017 | Completed final sign-off Nov 2019 | 3317 Washington St | Trinity Building Co Llc | kitchen remodel, update finishes, add exterior door at rear. install (n) washer/dryer. (n) int. doors, (n) enlarged skylight, make rear level 3 guardrail code complaint (36" to 42"). maher naDetails
kitchen remodel, update finishes, add exterior door at rear. install (n) washer/dryer. (n) int. doors, (n) enlarged skylight, make rear level 3 guardrail code complaint (36" to 42"). maher na | $90,000 |
| Sep 15, 2017 | Completed final sign-off Jul 2019 | 1243 Broadway | De Brus Construction Inc | soft story retrofit per sfebc chapter 4d per engineering criteria 2016 cebc appendix a-4.Details
soft story retrofit per sfebc chapter 4d per engineering criteria 2016 cebc appendix a-4. | $90,000 |
| Sep 15, 2017 | Expired or cancelled withdrawn Jul 2022 | 874 Fell St | comply w/ nov #201990001: structural engineering design for soft story retrofit of the buildng. the target story retrofit is through the addition of plywood shear walls and simpson moment frame. basement improvement to allow 9' ceiling height.Details
comply w/ nov #201990001: structural engineering design for soft story retrofit of the buildng. the target story retrofit is through the addition of plywood shear walls and simpson moment frame. basement improvement to allow 9' ceiling height. | $20,000 | |
| Sep 15, 2017 | Never finaled issued Jan 2022, no final | 1860 Turk St | Metro General Construction Inc | soft story retrofit per sfebc chapter 4d per engineering criteria 2016 cebc appendix a-4. comply with nov #201990442Details
soft story retrofit per sfebc chapter 4d per engineering criteria 2016 cebc appendix a-4. comply with nov #201990442 | $75,000 |
| Sep 15, 2017 | Completed final sign-off Sep 2020 | 1245 Broadway | De Brus Construction Inc | soft story retrofit per sfebc chapter 4d per engineering criteria 2016 cebc appendix a-4.Details
soft story retrofit per sfebc chapter 4d per engineering criteria 2016 cebc appendix a-4. | $90,000 |
| Sep 11, 2017 | Completed final sign-off Nov 2020 | 1376 Mcallister St | Bryan J. Valverde Co | soft story retrofit per sfebc chapter 4d, 2016 cebc appendix a-4, through addition of plywood shear walls at basement (north face, west face and middle of bldg.)Details
soft story retrofit per sfebc chapter 4d, 2016 cebc appendix a-4, through addition of plywood shear walls at basement (north face, west face and middle of bldg.) | $60,000 |
| Sep 11, 2017 | Completed final sign-off Nov 2020 | 1384 Mcallister St | Bryan J. Valverde Co | soft story retrofit per sfebc chapter 4d, 2016 cebc appendix a-4, through addition of plywood shear walls at basement (north face, west face and middle of building).Details
soft story retrofit per sfebc chapter 4d, 2016 cebc appendix a-4, through addition of plywood shear walls at basement (north face, west face and middle of building). | $60,000 |
| Sep 11, 2017 | Completed final sign-off Aug 2019 | 1868 Page St | Hammock Construction | soft story retrofit per sfebc chapter 4d, 2016 cebc appendix a-4, through addition of moment frame. not visable from street.Details
soft story retrofit per sfebc chapter 4d, 2016 cebc appendix a-4, through addition of moment frame. not visable from street. | $100,000 |
| Sep 11, 2017 | Completed final sign-off Oct 2019 | 237 Eureka St | Stronghold Builders Inc | soft story retrofit per sfebc chapter 4d, 2016 cebc appendix a-4, through addition of plywood shear walls and simpson steel strong wall shear wall.Details
soft story retrofit per sfebc chapter 4d, 2016 cebc appendix a-4, through addition of plywood shear walls and simpson steel strong wall shear wall. | $12,000 |
| Jul 31, 2017 | Completed final sign-off May 2019 | 2350 Market St | Seismic Retrofitters Inc. | temporary slope excavation in-lieu of required temporary shoring for the excavation to install new retaining walls. less than 50 cy of soil to be removed.Details
temporary slope excavation in-lieu of required temporary shoring for the excavation to install new retaining walls. less than 50 cy of soil to be removed. | $30,000 |
| Jul 27, 2017 | Completed final sign-off Dec 2017 | 283 Oak Park Dr | Amer Braz Construction | revision to pa #2016-0912-7460 - infill the area under the 2nd floor dining room at the rear. move 1st floor rear exterior wall to align with 2nd floor rear exterior wall.Details
revision to pa #2016-0912-7460 - infill the area under the 2nd floor dining room at the rear. move 1st floor rear exterior wall to align with 2nd floor rear exterior wall. | $10,000 |
| Jul 25, 2017 | Never finaled issued Jul 2017, no final | 942 Divisadero St | #401: removing existing two bearing walls in interior space between kitchen & living rm.Details
#401: removing existing two bearing walls in interior space between kitchen & living rm. | $2,000 | |
| Jun 1, 2017 | Completed final sign-off Apr 2018 | 1750 Sutter St | Synerforce Construction | at (e) 3-story bldg w/ (e) footprint: repair the damaged (e) deck in unit #305 - remove all (e) deck & guardrails. replace any decayed sheating & framing members. install all (n) rim joists & blocking. no change-same location & same size.Details
at (e) 3-story bldg w/ (e) footprint: repair the damaged (e) deck in unit #305 - remove all (e) deck & guardrails. replace any decayed sheating & framing members. install all (n) rim joists & blocking. no change-same location & same size. | $4,500 |
| Mar 17, 2017 | Completed final sign-off Jul 2017 | 520 Foerster St | demo and replace front stairs using (e) dimensions, replacing previous stucco guardrails and terrazzo w/iron raining and terra cotta tile. replace in kind.Details
demo and replace front stairs using (e) dimensions, replacing previous stucco guardrails and terrazzo w/iron raining and terra cotta tile. replace in kind. | $8,040 | |
| Jan 13, 2017 | Completed final sign-off Dec 2017 | 283 Oak Park Dr | Amer Braz Construction | revision app# 201609127460 - missing structural drawings. interior remodel to eliminate (e) ceiling in some parts; replacing (e) roof rafter ties & collar ties; add new staircase from 1st fl to 2nd fl. no structural interior remodel of partition walls. mininor structural strengthening.Details
revision app# 201609127460 - missing structural drawings. interior remodel to eliminate (e) ceiling in some parts; replacing (e) roof rafter ties & collar ties; add new staircase from 1st fl to 2nd fl. no structural interior remodel of partition walls. mininor structural strengthening. |