10 permits since 2000 (architect on 9 permits, designer on 1 permit): 10 completed.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Oct 16, 2017 | Completed final sign-off Jan 2018 | 50 California St | Skyline Construction | 35th fl - selective demo of non structural partitions, doors, glazing, hardware, millwork, lighting, ceiling grid & tile, electrical & finishes. new non-structrual partitions, doors, hardware, glazing, finishes & relocation of (e) lighting & electrical. no structural. mep under separate permit.Details
35th fl - selective demo of non structural partitions, doors, glazing, hardware, millwork, lighting, ceiling grid & tile, electrical & finishes. new non-structrual partitions, doors, hardware, glazing, finishes & relocation of (e) lighting & electrical. no structural. mep under separate permit. | $110,234 |
| Apr 27, 2016 | Completed final sign-off Sep 2016 | 275 Battery St | Gci, Inc | 25th flr: demo of non structural partitions, installation of non structural partitions, new acoustical ceiling grid tile & rework of (e) & new lighting & finishes. mep/fire/life saftey under sep permit. no change to occupancy are area. maher naDetails
25th flr: demo of non structural partitions, installation of non structural partitions, new acoustical ceiling grid tile & rework of (e) & new lighting & finishes. mep/fire/life saftey under sep permit. no change to occupancy are area. maher na | $439,516 |
| Oct 3, 2012 | Completed final sign-off Feb 2013 | 400 02nd St | Peacock Construction Inc | 3rd floor:office tenant improvement:minor demo of non structural partitions. new partitions and millwork. new lighting. m e p on seperate permit. sprinklers on seperate permit.Details
3rd floor:office tenant improvement:minor demo of non structural partitions. new partitions and millwork. new lighting. m e p on seperate permit. sprinklers on seperate permit. | $470,000 |
| Mar 22, 2012 | Completed final sign-off Jul 2012 | 1 Embarcadero Center | Gci, Inc | #1050- demolition of non load bearing partitions, ceiling & finishes. new non load bearing partitions, ceiling & finishes for partial renovationDetails
#1050- demolition of non load bearing partitions, ceiling & finishes. new non load bearing partitions, ceiling & finishes for partial renovation | $408,800 |
| Sep 16, 2011 | Completed final sign-off Mar 2012 | 50 California St | R.M.R. Construction Company | remove hazardous materials from unoccupied space, full floor. demolish non structural partitions, elec, plumbing, ceiling. construct restrooms, elevator lobby. space shall remain unoccupied after completion of workDetails
remove hazardous materials from unoccupied space, full floor. demolish non structural partitions, elec, plumbing, ceiling. construct restrooms, elevator lobby. space shall remain unoccupied after completion of work | $120,000 |
| May 26, 2011 | Completed final sign-off Aug 2013 | 633 Battery St | Hathaway Dinwiddie Co. | tenant improvement to existing office space. remove existing finiahes, lighting, mech. new non-structural partitions lighting and mechDetails
tenant improvement to existing office space. remove existing finiahes, lighting, mech. new non-structural partitions lighting and mech | $700,000 |
| Jun 29, 2009 | Completed final sign-off Oct 2009 | 275 Battery St | Hathaway Dinwiddie Co. | demolition & construction of 1 non-structural partition. relocation of a strobe light switch, fire extinguisher cab & t-stat. carpet & paint. no increase in area. no change in occupancy or use.Details
demolition & construction of 1 non-structural partition. relocation of a strobe light switch, fire extinguisher cab & t-stat. carpet & paint. no increase in area. no change in occupancy or use. | $4,950 |
| Feb 5, 2008 | Completed final sign-off Oct 2008 | 291 Geary St | Matrix Seismic Corp | 1st floor east bldg: demolition of partion non-bearing walls including cabient, carpet, store front, etc.Details
1st floor east bldg: demolition of partion non-bearing walls including cabient, carpet, store front, etc. | $10,000 |
| Sep 28, 2006 | Completed final sign-off Feb 2007 | 1 Embarcadero Center | Gci, Inc | 15th floor - build-back 1-hour rated elevator lobby and corridors. havac, mechanical, electrical, plumbing. men's & women's restroom are fully complaint - prior permit appl #200608048578.Details
15th floor - build-back 1-hour rated elevator lobby and corridors. havac, mechanical, electrical, plumbing. men's & women's restroom are fully complaint - prior permit appl #200608048578. | $114,000 |
| Sep 8, 2004 | Completed final sign-off Mar 2005 | 1 Embarcadero Center | Swinerton Builders | two 8'tall by 15' wide window cuts at west side, ec-1, lobby level.Details
two 8'tall by 15' wide window cuts at west side, ec-1, lobby level. | $150,000 |