97 permits since 2000 (architect on 92 permits, authorized agent-others on 5 permits, engineer on 2 permits): 62 completed, 11 in progress, 14 never finaled, 10 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 10, 2026 | In progress filed Sep 2026, not yet issued | 1719 Pine St | Ccf Construction, Llc | convert (e) 1/f storage areas into 1 new adu.Details
convert (e) 1/f storage areas into 1 new adu. | $175,000 |
| Apr 6, 2026 | In progress issued Jun 2026 | 45 Alton Av | Kingfish Construction Llc. | convert (e) closet into full bathroom., remodel (e) bathroom to (n) bathroom / (n) layoutDetails
convert (e) closet into full bathroom., remodel (e) bathroom to (n) bathroom / (n) layout | $29,500 |
| Apr 6, 2026 | In progress issued Jun 2026 | 2310 48th Av | Kingfish Construction Llc. | remove portion of wall between (e) dining and living room, (n) post and beam per structural. remodel (e) kitchen.Details
remove portion of wall between (e) dining and living room, (n) post and beam per structural. remodel (e) kitchen. | $45,000 |
| Jan 8, 2026 | Completed final sign-off Feb 2026 | 4027 Noriega St | Ccf Construction, Llc | mechanical deferred for permit pa #202406215035Details
mechanical deferred for permit pa #202406215035 | $3,000 |
| Dec 19, 2025 | Completed final sign-off Apr 2026 | 651 Cole St | Ccf Construction, Llc | remove two (e) front balconies and replace with (e) patio doors with new windows within the same opening.Details
remove two (e) front balconies and replace with (e) patio doors with new windows within the same opening. | $15,000 |
| Dec 19, 2025 | In progress issued Jan 2026 | 199 Edgewood Av | Kingfish Construction Llc. | interior alteration. 1st fl: remove (e) spiral stairs, replace with new. new layout. existing kitchen & bath remodel. replace (e) rear patio door with new, same opening. 2nd fl: remodel (e) half bath & bath into (n) master bath. (n) full half bath. remodel (e) den & master bedroom.Details
interior alteration. 1st fl: remove (e) spiral stairs, replace with new. new layout. existing kitchen & bath remodel. replace (e) rear patio door with new, same opening. 2nd fl: remodel (e) half bath & bath into (n) master bath. (n) full half bath. remodel (e) den & master bedroom. | $200,000 |
| Oct 16, 2025 | In progress issued Mar 2026 | 454 14th St | Refresh And Build Inc | raise (e)2nd fl of bldg/increase height of 1st fl.convert(e)1st fl to 1 new residential unit.remodel(e)2nd fl unit,fill in(e)light well;(n)two-story addition/extension to back of(e)building;replace rear deck & stairs with new.Details
raise (e)2nd fl of bldg/increase height of 1st fl.convert(e)1st fl to 1 new residential unit.remodel(e)2nd fl unit,fill in(e)light well;(n)two-story addition/extension to back of(e)building;replace rear deck & stairs with new. | $250,000 |
| Oct 3, 2025 | Completed final sign-off Apr 2026 | 173 Warren Dr | Kingfish Construction Llc. | new first floor fill in addition, walk in closet, under existing second floor.Details
new first floor fill in addition, walk in closet, under existing second floor. | $28,000 |
| Aug 15, 2025 | In progress filed Aug 2025, not yet issued | 2081 47th Av | revision to pa #202507100506. remove proposed skylight from scope. existing centerline beam to remain.Details
revision to pa #202507100506. remove proposed skylight from scope. existing centerline beam to remain. | ||
| May 12, 2025 | Completed final sign-off Sep 2025 | 15 Cityview Wy | Refresh And Build Inc | 2/f bath remodel: replace all (e) fixtures and finishes in kind at same locations. change tub to shower, change (e) bath partition from full ht to partial ht w/ glazing above; remove (e) window in kind at same location and opening.Details
2/f bath remodel: replace all (e) fixtures and finishes in kind at same locations. change tub to shower, change (e) bath partition from full ht to partial ht w/ glazing above; remove (e) window in kind at same location and opening. | $30,000 |
| Feb 7, 2025 | Completed final sign-off Apr 2026 | 45 Alton Av | Kingfish Construction Llc. | interior alteration of (e) 2nd fl. kitchen & bath. replace 1 (e) rear window in same opening widthDetails
interior alteration of (e) 2nd fl. kitchen & bath. replace 1 (e) rear window in same opening width | $55,000 |
| Nov 15, 2024 | Completed final sign-off Nov 2025 | 3647 Taraval St | Ccf Construction, Llc | unit 3647-to comply with nov 202424603 to repair fire damage within unit. replace all (e) interior finishes w/(n) in kind, drywall on walls, ceiling, flooring, lighting, bath and kitchen fixtures and cabinets, doors, windows (facing front) and skylight. no layout change.Details
unit 3647-to comply with nov 202424603 to repair fire damage within unit. replace all (e) interior finishes w/(n) in kind, drywall on walls, ceiling, flooring, lighting, bath and kitchen fixtures and cabinets, doors, windows (facing front) and skylight. no layout change. | $100,000 |
| Nov 15, 2024 | In progress issued Apr 2025 | 1487 44th Av | Kingfish Construction Llc. | comply with nov #202429020 rebuild (e) rear exterior deck & stairs in kind. replace (e) rear wall shingles. first fl: replace (e) rear doors & windows. (n) interior finishes, fixtures, cabinets in kind. repair (e) interior south framed wall per structural.Details
comply with nov #202429020 rebuild (e) rear exterior deck & stairs in kind. replace (e) rear wall shingles. first fl: replace (e) rear doors & windows. (n) interior finishes, fixtures, cabinets in kind. repair (e) interior south framed wall per structural. | $40,000 |
| Oct 3, 2024 | In progress issued Oct 2024 | 454 14th St | Refresh And Build Inc | first floor strutural work. lower (e) floor level , (n) concrete slab and foundation upgrade.Details
first floor strutural work. lower (e) floor level , (n) concrete slab and foundation upgrade. | $50,000 |
| Sep 24, 2024 | In progress filed Sep 2024, not yet issued | 30 Raleigh St | lot b: to erect a 2-story, type vb, single family dwelling, 1-unit building.Details
lot b: to erect a 2-story, type vb, single family dwelling, 1-unit building. | $600,000 | |
| Sep 12, 2024 | In progress issued May 2025 | 217 Gold Mine Dr | Jin Qing Construction Corp., A-1 Dynamic Builders Inc. | (n) partial lightwell infill additions at first & second floors. interior remodel entire (e) house. lowering of (e) dining and (e) kitchen floor areas. add (n) exterior windows, doors, & skylights. add (n) exterior staircase.Details
(n) partial lightwell infill additions at first & second floors. interior remodel entire (e) house. lowering of (e) dining and (e) kitchen floor areas. add (n) exterior windows, doors, & skylights. add (n) exterior staircase. | $300,000 |
| Aug 20, 2024 | Completed final sign-off Feb 2026 | 4027 Noriega St | Ccf Construction, Llc | to abate nov 202419488- change of use for first floor (e) retail space to fitness gym to include: alteration of (e) hardware, addition of (4) skylights, add exit passageway, replace (e) entry doors w/(n) accessible door. alteration to (e) men's restroom to accessible restroom. mep deffered.Details
to abate nov 202419488- change of use for first floor (e) retail space to fitness gym to include: alteration of (e) hardware, addition of (4) skylights, add exit passageway, replace (e) entry doors w/(n) accessible door. alteration to (e) men's restroom to accessible restroom. mep deffered. | $78,000 |
| Apr 30, 2024 | Completed final sign-off Dec 2024 | 1879 43rd Av | Kingfish Construction Llc. | interior alteration and addition: convert portion of (e) unconditioned space at first floor into conditioned bedroom, full bath, and den. (n) windows and door facing back yard.Details
interior alteration and addition: convert portion of (e) unconditioned space at first floor into conditioned bedroom, full bath, and den. (n) windows and door facing back yard. | $75,000 |
| Feb 7, 2024 | In progress filed Feb 2024, not yet issued | 61 Buena Vista Tr | interior alteration on 1st floor: convert extg office and entertanment rooms into 1 new bedroom, new doors into extg den and extg lightwell. add new wetbar in extg media room.Details
interior alteration on 1st floor: convert extg office and entertanment rooms into 1 new bedroom, new doors into extg den and extg lightwell. add new wetbar in extg media room. | $20,000 | |
| Feb 5, 2024 | Completed final sign-off Mar 2024 | 1033 Taraval St | Lozano Landscape Construction And Mainte | to comply w/ nov# 202316748; south wall exterior and underlying to be removed to (e) studs and replaced in-kind, repair or replace dry rot and infill (e) openings to matchDetails
to comply w/ nov# 202316748; south wall exterior and underlying to be removed to (e) studs and replaced in-kind, repair or replace dry rot and infill (e) openings to match | $5,000 |
| Oct 31, 2023 | Completed final sign-off Mar 2024 | 61 Buena Vista Tr | Blue Wood Construction Inc. | unit 61, interior alteration, remove (e) spiral staircase, (n) staircase @ (n)location, remove (e) interior wall @ 2/f, enlarge unit 59 from square footage taken from unit 61, replace (e) sliding door with (n) in same opening at back of bldg.Details
unit 61, interior alteration, remove (e) spiral staircase, (n) staircase @ (n)location, remove (e) interior wall @ 2/f, enlarge unit 59 from square footage taken from unit 61, replace (e) sliding door with (n) in same opening at back of bldg. | $20,000 |
| Oct 23, 2023 | Completed final sign-off Jan 2025 | 783 06th Av | Y&L Constructon And Remodeling | first flr remodel (e) half bath to full bath, remodel (e) laundry area to wet bar, replace (e) playroom with (n) doors, add two (n) windows at back of building. adding a secondary kitchen at the ground floor for an existing two family dwelling unit. ground floor is common.Details
first flr remodel (e) half bath to full bath, remodel (e) laundry area to wet bar, replace (e) playroom with (n) doors, add two (n) windows at back of building. adding a secondary kitchen at the ground floor for an existing two family dwelling unit. ground floor is common. | $25,000 |
| Jul 12, 2023 | Completed final sign-off Dec 2025 | 24 Retiro Wy | Sft Construction Corp | inter remodel of all 3 (e) flrs: unit 24 1/f-convert (e)unconditioned areas to new conditioned areas to inc den, full bath & closet. new tradesman alley dr, enlarge & relocate e garage dr. 2/f- remodel kitchen & full bath, add n half bath, enlarge e wall opnings new kitchen windows. unit 26 remodelDetails
inter remodel of all 3 (e) flrs: unit 24 1/f-convert (e)unconditioned areas to new conditioned areas to inc den, full bath & closet. new tradesman alley dr, enlarge & relocate e garage dr. 2/f- remodel kitchen & full bath, add n half bath, enlarge e wall opnings new kitchen windows. unit 26 remodel | $350,000 |
| Jul 10, 2023 | Completed final sign-off Apr 2024 | 230 Irving St | Kingfish Construction Llc. | revision to pa# 202305198186, remodel existing bath & closet w/ new layout and finishes.Details
revision to pa# 202305198186, remodel existing bath & closet w/ new layout and finishes. | |
| Jul 3, 2023 | Completed final sign-off Jun 2025 | 1236 07th Av | Refresh And Build Inc | revision to pa#202211035841. relocate full bath on 2nd fl.Details
revision to pa#202211035841. relocate full bath on 2nd fl. | |
| Jun 9, 2023 | Completed final sign-off Jun 2023 | 66 Cumberland St | revision to pa 201712085880 & 202203220559 (recommencement permit to 201712085880)Details
revision to pa 201712085880 & 202203220559 (recommencement permit to 201712085880) | ||
| May 25, 2023 | Expired or cancelled withdrawn May 2024 | 59 Buena Vista Tr | new interior stairway connecting 3/f & attic (e)flr area; 3/f: remodel (e)family rm, dining, kitchen, full bath, new half bath, laundry, pantry; attic: new roof dormers, convert (e)flr area to roof deck, remodel sewing rm to entertainment rm, (e)social rm to bedroom/home office, (2)new full baths,Details
new interior stairway connecting 3/f & attic (e)flr area; 3/f: remodel (e)family rm, dining, kitchen, full bath, new half bath, laundry, pantry; attic: new roof dormers, convert (e)flr area to roof deck, remodel sewing rm to entertainment rm, (e)social rm to bedroom/home office, (2)new full baths, | $200,000 | |
| Apr 19, 2023 | Completed final sign-off Apr 2023 | 38 Allston Wy | L H Gao Construction Inc. | rev to pa# 202207259226, to correct scope of work to remodel 2 (e) bathrooms with new fixture and finishes in same location on 1st & 2nd flrs. no work on ground flr/basement.Details
rev to pa# 202207259226, to correct scope of work to remodel 2 (e) bathrooms with new fixture and finishes in same location on 1st & 2nd flrs. no work on ground flr/basement. | |
| Nov 3, 2022 | Completed final sign-off Jun 2025 | 1236 07th Av | Refresh And Build Inc | 1st fl-remodel flr areas and convert (e) unconditioned into (n) conditioned areas to incl - 2 bedrms, 2 full baths, family rm, wet bar & laundry; remove (e) int'r wall @ front entry for (n) interior connection between flrs of unit; create (n) passageway. relocate (e) gas meters & electrical panel;Details
1st fl-remodel flr areas and convert (e) unconditioned into (n) conditioned areas to incl - 2 bedrms, 2 full baths, family rm, wet bar & laundry; remove (e) int'r wall @ front entry for (n) interior connection between flrs of unit; create (n) passageway. relocate (e) gas meters & electrical panel; | $150,000 |
| Oct 21, 2022 | Completed final sign-off Aug 2023 | 3139 Santiago St | Kingfish Construction Llc. | 2/f: interior alteration, no structural, (e) kitchen remodel w/layout change, (e) full b ath remodel w/layout change, removal of (e) nonbearing wall between kitchen/dining/living roomDetails
2/f: interior alteration, no structural, (e) kitchen remodel w/layout change, (e) full b ath remodel w/layout change, removal of (e) nonbearing wall between kitchen/dining/living room | $35,000 |
| Sep 2, 2022 | Completed final sign-off Aug 2024 | 1562 15th Av | Kingfish Construction Llc. | lower flr: convert (e) storage area into (n) dining/living, kitchen and half bath, remove (e) and replace with (n) stairs connecting foyer to lower floor , remove (e) exterior rear deck and stairs (n) rear exterior doors, (n) foyer closet. upper flr: add (n) closet and full bath to (e) family rm (n)Details
lower flr: convert (e) storage area into (n) dining/living, kitchen and half bath, remove (e) and replace with (n) stairs connecting foyer to lower floor , remove (e) exterior rear deck and stairs (n) rear exterior doors, (n) foyer closet. upper flr: add (n) closet and full bath to (e) family rm (n) | $150,000 |
| Jul 25, 2022 | Completed final sign-off Apr 2023 | 38 Allston Wy | L H Gao Construction Inc. | 1/f:remove (e) interior non-load bearing wall between kitchen and dining. remodel (e) kitchen. remodel all (e) bathrooms with new fixture and finishes in same location.Details
1/f:remove (e) interior non-load bearing wall between kitchen and dining. remodel (e) kitchen. remodel all (e) bathrooms with new fixture and finishes in same location. | $80,000 |
| Jun 14, 2022 | Completed final sign-off Dec 2022 | 1958 30th Av | Good Neighbor Construction | (e) 2nd fl remodel: bath & kitchen, roofing and framing above the bathtub, enlarge wall opening btw living and kitchen, remove fireplace.Details
(e) 2nd fl remodel: bath & kitchen, roofing and framing above the bathtub, enlarge wall opening btw living and kitchen, remove fireplace. | $45,000 |
| Jan 14, 2022 | Completed final sign-off Nov 2022 | 2341 27th Av | Ryan Construction | 1/f: convert portion of (e) storage space into conditioned spaces to include 1 new bedroom, 1 new bath, 1 new laundry area, new window to replace (e) same opening, new (e) double doors to replace (e) single door and window @ rear of houseDetails
1/f: convert portion of (e) storage space into conditioned spaces to include 1 new bedroom, 1 new bath, 1 new laundry area, new window to replace (e) same opening, new (e) double doors to replace (e) single door and window @ rear of house | $45,000 |
| Oct 4, 2021 | Never finaled issued Apr 2022, no final | 2646 45th Av | Kingfish Construction Llc. | new exterior deck & stairway from back of existing house. remove 1 exsiting window, enlarge opening & replace with 1 new door (not visible from street)Details
new exterior deck & stairway from back of existing house. remove 1 exsiting window, enlarge opening & replace with 1 new door (not visible from street) | $15,000 |
| Sep 30, 2021 | Completed final sign-off Dec 2021 | 350 Hermann St | D N Construction | replace exterior metal guardrails with wood guardrails on entry stairwayDetails
replace exterior metal guardrails with wood guardrails on entry stairway | $10,000 |
| Jun 9, 2021 | Completed final sign-off Nov 2021 | 2247 38th Av | Kingfish Construction Llc. | 1/f; remove/replace (e) interior stairway. convert part of (e) storage area into new hall 1. 2/f; remodel (e) kitchen. remove (e) interior wall b/t (e) kitchen and (e) dining. remove (e) interior wall b/t (e) game room and (e) office. add new interior hall 2. new window in (e) office.Details
1/f; remove/replace (e) interior stairway. convert part of (e) storage area into new hall 1. 2/f; remodel (e) kitchen. remove (e) interior wall b/t (e) kitchen and (e) dining. remove (e) interior wall b/t (e) game room and (e) office. add new interior hall 2. new window in (e) office. | $60,000 |
| Apr 2, 2021 | Completed final sign-off Jan 2022 | 592 South Van Ness Av | Refresh And Build Inc | interior alteration: remove some (e) interior walls & add (n) interior walls per plan. alter (e) bedroom and (e) kitchen.convert(e) living room into (n) bedroom,convert (e) bedroom into living/dining. convert(e)dining room into bedbroom 2 & den.(e)utility room to be removed, relocate washer & dryer.Details
interior alteration: remove some (e) interior walls & add (n) interior walls per plan. alter (e) bedroom and (e) kitchen.convert(e) living room into (n) bedroom,convert (e) bedroom into living/dining. convert(e)dining room into bedbroom 2 & den.(e)utility room to be removed, relocate washer & dryer. | $95,000 |
| Mar 26, 2021 | Completed final sign-off Nov 2024 | 2496 43rd Av | Spe Construction Inc. | new vertical addition to (e) 2-story sfd. 3rd story: 2 new bedrooms, 2 full baths, entertainment/living room 2 & study. new pneumatic elevator. new exterior roof terrace & cantilevered balcony. new internal staircase from 2nd to 3rd floor. convert partial (e) 1st floor to caregiver suite, bedroom,Details
new vertical addition to (e) 2-story sfd. 3rd story: 2 new bedrooms, 2 full baths, entertainment/living room 2 & study. new pneumatic elevator. new exterior roof terrace & cantilevered balcony. new internal staircase from 2nd to 3rd floor. convert partial (e) 1st floor to caregiver suite, bedroom, | $750,000 |
| Jan 29, 2021 | Completed final sign-off Nov 2022 | 1822 43rd Av | interior alteration: 1/f: convert (e) storage rms into bedrm, bath, and walk-in closet. convert (e) entry into conditioned foyer. 2/f: r/r (e) kitchen appliances, countertop, and finishes with new. new kitchen layout. remove wall b/t kitchen/dining and (e) living, new framing. mep as related.Details
interior alteration: 1/f: convert (e) storage rms into bedrm, bath, and walk-in closet. convert (e) entry into conditioned foyer. 2/f: r/r (e) kitchen appliances, countertop, and finishes with new. new kitchen layout. remove wall b/t kitchen/dining and (e) living, new framing. mep as related. | $90,000 | |
| Jan 25, 2021 | Never finaled issued Jul 2023, no final | 194 Howth St | new 2-story addition to rear of existing house,1st floor of addtion and portion and portion of existing 1st floor to be converted to new adu per ordinance # 2nd floor of addition for exiting residence,interior alteration of existing 1st floor.Details
new 2-story addition to rear of existing house,1st floor of addtion and portion and portion of existing 1st floor to be converted to new adu per ordinance # 2nd floor of addition for exiting residence,interior alteration of existing 1st floor. | $300,000 | |
| Oct 24, 2020 | Expired or cancelled withdrawn Apr 2023 | 1778 48th Av | convert portion of 1/f into new bedroom,bathroom,den;r/r 1/f back windows and door;(n)fire rated drywall on (e) garage walls and celing.remove portion of 9e) wall on 2/f between kitchen/dining and living.remove portion of (e) walls on 2/f adj to stairs;relocate (e) ext. stairs.structural work.Details
convert portion of 1/f into new bedroom,bathroom,den;r/r 1/f back windows and door;(n)fire rated drywall on (e) garage walls and celing.remove portion of 9e) wall on 2/f between kitchen/dining and living.remove portion of (e) walls on 2/f adj to stairs;relocate (e) ext. stairs.structural work. | $65,000 | |
| Oct 24, 2020 | Never finaled issued Jan 2021, no final | 128 Montcalm St | interior remodel: bath #1 remove/replace all (e) fixures & finishes w/ new. bath #2: remove/replace all (e) fixures & finishes w/ new, (n) ayout per plans, replace (e) windows, (n) window header. bedroom #3: remove wall as req'd for new layout. reforcing framing for (n) soaking tub.Details
interior remodel: bath #1 remove/replace all (e) fixures & finishes w/ new. bath #2: remove/replace all (e) fixures & finishes w/ new, (n) ayout per plans, replace (e) windows, (n) window header. bedroom #3: remove wall as req'd for new layout. reforcing framing for (n) soaking tub. | $35,000 | |
| Oct 24, 2020 | Completed final sign-off Mar 2021 | 2341 27th Av | Kingfish Construction Llc. | interior remodel: kitchen - remove/replace (e) appliances, countertop, cabinets, and wall/ceiling finishes w/ (n) layout. bath - remove/replace (e) fixtures & wall/ceiling finishes w/ new layout. interior stairs: remove/replace w/ new. remove (e) hall closet. remodel (e) pantry.Details
interior remodel: kitchen - remove/replace (e) appliances, countertop, cabinets, and wall/ceiling finishes w/ (n) layout. bath - remove/replace (e) fixtures & wall/ceiling finishes w/ new layout. interior stairs: remove/replace w/ new. remove (e) hall closet. remodel (e) pantry. | $65,000 |
| Oct 24, 2020 | Never finaled issued Feb 2021, no final | 467 Joost Av | Kingfish Construction Llc. | convert portion of (e) 1/f into conditioned spaces -entertainment room, 3 bedrooms, 2 bathrooms. new drywall and insulation in (e) garage. new rear deck and stairs. r/r rear window and door with new size and locations. structural work.Details
convert portion of (e) 1/f into conditioned spaces -entertainment room, 3 bedrooms, 2 bathrooms. new drywall and insulation in (e) garage. new rear deck and stairs. r/r rear window and door with new size and locations. structural work. | $50,000 |
| Oct 15, 2020 | Completed final sign-off Jun 2021 | 2007 41st Av | Kingfish Construction Llc. | interior alteration: kitchen: remove & replace (e) appliances, countertop, cabinets, and finishes w/(n). (n) layout. remove portion of (e) wall between (e) kitchen/dining and (e) living room. (n) framing per structural. mech, plumb, elec. related to scope of work. legalize den and full bath on gf.Details
interior alteration: kitchen: remove & replace (e) appliances, countertop, cabinets, and finishes w/(n). (n) layout. remove portion of (e) wall between (e) kitchen/dining and (e) living room. (n) framing per structural. mech, plumb, elec. related to scope of work. legalize den and full bath on gf. | $40,000 |
| Oct 14, 2020 | Completed final sign-off Jan 2022 | 1955 Turk St | L H Gao Construction Inc. | interior alteration: remove & replace kitchen appliances, countertops cabinets, and finishes. (n) layout. convert (e) laundry utilities & bedroom closets into (n) full bath & closets. convert (e) wc into (n) closet. remove replace (e) fixtures & finishes in bathroom. add (n) toilet in (e) bathroom.Details
interior alteration: remove & replace kitchen appliances, countertops cabinets, and finishes. (n) layout. convert (e) laundry utilities & bedroom closets into (n) full bath & closets. convert (e) wc into (n) closet. remove replace (e) fixtures & finishes in bathroom. add (n) toilet in (e) bathroom. | $55,000 |
| Dec 24, 2019 | Completed final sign-off Feb 2020 | 269 Clinton Pk | Argueta And Ruano Construction Inc | interior alteration: convert existing walk-in closet into new bathroom. mpe work as related to new bathroom.Details
interior alteration: convert existing walk-in closet into new bathroom. mpe work as related to new bathroom. | $5,000 |
| Dec 17, 2019 | Expired or cancelled cancelled Jul 2022 | 38 Allston Wy | addition/extension of 3rd flr and 2nd flr kitchen. interior alterations.Details
addition/extension of 3rd flr and 2nd flr kitchen. interior alterations. | $250,000 | |
| Dec 12, 2019 | Completed final sign-off Sep 2020 | 475 Roosevelt Wy | J5 Real Estate Development Co | interior remodel: kitchen, add 1 new bath & closets. remove existing walls & doors. replcae 5 windows in-like-kind. structural work per structural. mep related to scopeDetails
interior remodel: kitchen, add 1 new bath & closets. remove existing walls & doors. replcae 5 windows in-like-kind. structural work per structural. mep related to scope | $40,000 |
| Oct 25, 2019 | Completed final sign-off Aug 2020 | 1554 Jackson St | L H Gao Construction Inc. | 2nd flr - interior remodel of unit 1554 (e) kitchen & bath. add 1 (n) bath & add (n) laundry closet. remove and replace (e) flooring. remove & replace (e) wall & ceiling finishes.Details
2nd flr - interior remodel of unit 1554 (e) kitchen & bath. add 1 (n) bath & add (n) laundry closet. remove and replace (e) flooring. remove & replace (e) wall & ceiling finishes. | $65,000 |
| Oct 17, 2019 | Never finaled filed Oct 2019, never issued | 651 Minna St | one studio adu per ord# 162-16. the 5th unit under legalizetion pa# 2019-1017-4766.Details
one studio adu per ord# 162-16. the 5th unit under legalizetion pa# 2019-1017-4766. | $20,000 | |
| Oct 17, 2019 | Never finaled filed Oct 2019, never issued | 651 Minna St | legalizing (1) illegal unit under ordinance #43-14Details
legalizing (1) illegal unit under ordinance #43-14 | $20,000 | |
| Feb 14, 2019 | Completed final sign-off Dec 2020 | 619 Belvedere St | 1st fl: legalize (e) space behind garage into house office, remove (e) stove, sink & bathtub in (e) space; convert (e) kitchen to laundry room, convert (e) full bath to half bath, relocate (e) washer & dryer, (n) handrails.Details
1st fl: legalize (e) space behind garage into house office, remove (e) stove, sink & bathtub in (e) space; convert (e) kitchen to laundry room, convert (e) full bath to half bath, relocate (e) washer & dryer, (n) handrails. | $15,000 | |
| Jan 28, 2019 | Completed final sign-off Jul 2019 | 2440 Green St | L H Gao Construction Inc. | interior remodel of (e) unit. addition of full bath & closet in (e) bedroom spaceDetails
interior remodel of (e) unit. addition of full bath & closet in (e) bedroom space | $12,000 |
| Jan 28, 2019 | Completed final sign-off Dec 2020 | 176 Gold Mine Dr | Brendan Waters Construction Inc | replace rear (e) balconies in-like-kind. (n) structural posts to reinforce (e) balconies in back of building/property.Details
replace rear (e) balconies in-like-kind. (n) structural posts to reinforce (e) balconies in back of building/property. | $25,000 |
| Dec 11, 2018 | Expired or cancelled cancelled Jun 2025 | 374 Delano Av | per adu ordinance# 95-17: convert (e) conditioned 1st floor into new adu with new kitchen. 2 bedrooms, 1 bath. ** maher: n/a **Details
per adu ordinance# 95-17: convert (e) conditioned 1st floor into new adu with new kitchen. 2 bedrooms, 1 bath. ** maher: n/a ** | $30,000 | |
| Nov 1, 2018 | Completed final sign-off Nov 2019 | 746 Lyon St | Flmc Development Corp Dba Adamo Campagna | convert e 3 story single family residential into 2 units. remodel 1st fl, remove e interior staircase connecting 1st/2nd fl. remove e back staircase. mep, structural related to scopeDetails
convert e 3 story single family residential into 2 units. remodel 1st fl, remove e interior staircase connecting 1st/2nd fl. remove e back staircase. mep, structural related to scope | $25,000 |
| Oct 2, 2018 | Completed final sign-off Oct 2020 | 329 Chicago Wy | Green California Builders Inc, Etna Enterprises | addition of 316 sq ft to back of existing house, bedroom and bathDetails
addition of 316 sq ft to back of existing house, bedroom and bath | $80,000 |
| Sep 21, 2018 | Never finaled issued Apr 2019, no final | 2242 48th Av | Kingfish Construction Llc. | add units per ordinance# 95-17. convert areas of (e) 1st floor into (n) adu unit (1 bedroom & 1 bath).Details
add units per ordinance# 95-17. convert areas of (e) 1st floor into (n) adu unit (1 bedroom & 1 bath). | $30,000 |
| Sep 21, 2018 | Never finaled issued Oct 2018, no final | 194 Howth St | L H Gao Construction Inc. | interior remodel: kitchen, bathroom, bedroom, interior staircase, (n0 laundry closet. removal of (e) wall btw liv & fam rmDetails
interior remodel: kitchen, bathroom, bedroom, interior staircase, (n0 laundry closet. removal of (e) wall btw liv & fam rm | $70,000 |
| Jul 27, 2018 | Completed final sign-off Nov 2019 | 189 Commonwealth Av | Kobuksan Construction | int. remodel unit #1: (e) kitchen converted to (n) bedroom, (e) bath converted to (n) kitchen, (e) den converted to (n) bath., (n) closet between (e) bathroom & (e) living room. mep and structural work per scope/plan.Details
int. remodel unit #1: (e) kitchen converted to (n) bedroom, (e) bath converted to (n) kitchen, (e) den converted to (n) bath., (n) closet between (e) bathroom & (e) living room. mep and structural work per scope/plan. | $80,000 |
| Jul 27, 2018 | Completed final sign-off Feb 2019 | 1 Country Club Dr | Kingfish Construction Llc. | (n) 1 story exterior stair case on side of bldg. of (e) deck.Details
(n) 1 story exterior stair case on side of bldg. of (e) deck. | $8,000 |
| Jul 27, 2018 | Completed final sign-off Nov 2018 | 2751 Greenwich St | Kingfish Construction Llc. | (n) exterior back deck, staircase, and elevated walkway/bridge rear of building.Details
(n) exterior back deck, staircase, and elevated walkway/bridge rear of building. | $25,000 |
| Jul 10, 2018 | Completed final sign-off Nov 2018 | 1942 Vicente St | L H Gao Construction Inc. | interior remodel: convert (e) dining room into (n) bedroom; create (n) opening into (e) kitchen.Details
interior remodel: convert (e) dining room into (n) bedroom; create (n) opening into (e) kitchen. | $10,000 |
| Jun 11, 2018 | Expired or cancelled withdrawn Aug 2018 | 1229 Vallejo St | Cornerstone Dba Ag Construction | unit a - remove (e) kitchen and convert (e) storage space into kitchenDetails
unit a - remove (e) kitchen and convert (e) storage space into kitchen | $20,000 |
| May 8, 2018 | Completed final sign-off Feb 2019 | 269 Clinton Pk | Argueta And Ruano Construction Inc | moving kitchen from current room to new location in condo(living room) removing load bearing wall at front of the house.Details
moving kitchen from current room to new location in condo(living room) removing load bearing wall at front of the house. | $45,000 |
| Apr 25, 2018 | Expired or cancelled cancelled Jan 2026 | 1347 Hayes St | convert (e) grnd flr into 1 guest bedroom, media rm, office convert 1/2 bath to new 1/2 bath & laundry. mep as necessaryDetails
convert (e) grnd flr into 1 guest bedroom, media rm, office convert 1/2 bath to new 1/2 bath & laundry. mep as necessary | $25,000 | |
| Mar 9, 2018 | Completed final sign-off Nov 2018 | 1631 43rd Av | Kingfish Construction Llc. | interior remolel, convert part of e gr fl into habitable space to include mastr bdrm, master bath, laundry closet, new patio door and window, new ext deck, stairs. mpe and sturctural work for remodel and deckDetails
interior remolel, convert part of e gr fl into habitable space to include mastr bdrm, master bath, laundry closet, new patio door and window, new ext deck, stairs. mpe and sturctural work for remodel and deck | $60,000 |
| Feb 16, 2018 | Completed final sign-off Jun 2018 | 1229 Vallejo St | Cornerstone Dba Ag Construction | ground floor horizontal fill in. remove 3 fire places on 2,3,4 floors, at family rooms. structural strengthening. (n) storage spaces in (e) garage.Details
ground floor horizontal fill in. remove 3 fire places on 2,3,4 floors, at family rooms. structural strengthening. (n) storage spaces in (e) garage. | $60,000 |
| Dec 22, 2017 | Completed final sign-off May 2018 | 1531 Sanchez St | Kingfish Construction Llc. | 1531: bathroom remodel, mech, plmg, elec related work. 1533: bathroom remodel, mech, plmg, & elec. related work. close exg door, new door opening.Details
1531: bathroom remodel, mech, plmg, elec related work. 1533: bathroom remodel, mech, plmg, & elec. related work. close exg door, new door opening. | $20,000 |
| Oct 25, 2017 | Expired or cancelled withdrawn Jan 2018 | 1531 Sanchez St | interior remodel litchen & bath, relcoated elect, plbg & mech struct. @ #1533. removal of (e) mechancial chase in bath . repair (e) bath @ #1531.Details
interior remodel litchen & bath, relcoated elect, plbg & mech struct. @ #1533. removal of (e) mechancial chase in bath . repair (e) bath @ #1531. | $40,000 | |
| Jul 25, 2017 | Completed final sign-off Jan 2018 | 590 South Van Ness Av | Argueta And Ruano Construction Inc | 3rd floor unit interior remodel: ktichen, bath, bedroom, relocate living room & bedroom, one (n) bath, one (n) bedroom, one (n) playroom. remove & replace interior finishes & doors, remove & replace (e) windows in same openings. mech, elec & plbg struct work as related to remodel. n/a maherDetails
3rd floor unit interior remodel: ktichen, bath, bedroom, relocate living room & bedroom, one (n) bath, one (n) bedroom, one (n) playroom. remove & replace interior finishes & doors, remove & replace (e) windows in same openings. mech, elec & plbg struct work as related to remodel. n/a maher | $55,000 |
| Jul 7, 2017 | Never finaled issued Jun 2018, no final | 652 Clayton St | Bay Pro Property Solutions Inc | conversion of (e) unconditioned 1st floor garage & storage space of a 4 story building into a new conditioned adu per ordinance# 162-16. mep work & structural work related to new unit. adu part of building. seismic upgrade ref pa# 2017/07/07/1198. sprinkler 13rDetails
conversion of (e) unconditioned 1st floor garage & storage space of a 4 story building into a new conditioned adu per ordinance# 162-16. mep work & structural work related to new unit. adu part of building. seismic upgrade ref pa# 2017/07/07/1198. sprinkler 13r | $50,000 |
| May 2, 2017 | Completed final sign-off Oct 2017 | 2496 43rd Av | R P Construction Inc. | interior remodel of (e) family dwelling - remodel bath and install (n) dumbwaiterDetails
interior remodel of (e) family dwelling - remodel bath and install (n) dumbwaiter | $35,000 |
| Apr 26, 2017 | Completed final sign-off Nov 2018 | 66 Cumberland St | upper unit: interior remodel of (e) to include: kitchen, bathroom, closets, (n) bedroom in (e) space. (n) bathroom in (e) space. (e) bedrooms, mechanical, plumbing & electrical work related to remodel, sptructural work, window replacement.Details
upper unit: interior remodel of (e) to include: kitchen, bathroom, closets, (n) bedroom in (e) space. (n) bathroom in (e) space. (e) bedrooms, mechanical, plumbing & electrical work related to remodel, sptructural work, window replacement. | $150,000 | |
| Oct 31, 2016 | Completed final sign-off Apr 2018 | 1 Country Club Dr | Kingfish Construction Llc. | conversion of (e) unconditioned lower floor garage & storage space into (n) conditioned accessory dwelling unit.Details
conversion of (e) unconditioned lower floor garage & storage space into (n) conditioned accessory dwelling unit. | $35,000 |
| May 18, 2016 | Completed final sign-off Nov 2019 | 746 Lyon St | Flmc Development Corp Dba Adamo Campagna | horizontal & vertical addition. 1st flr: remodel of (e) spaces into (n) habitable /conditioned spaces. (n) infll addition/extension. (n) back stairs. 2nd flr remodel (e) kitchen (n) finishes,(n) windows & door. 3rd flr (n) rear addition/extension (n) exterior deck (n) stairs roof: (n) roof deck.Details
horizontal & vertical addition. 1st flr: remodel of (e) spaces into (n) habitable /conditioned spaces. (n) infll addition/extension. (n) back stairs. 2nd flr remodel (e) kitchen (n) finishes,(n) windows & door. 3rd flr (n) rear addition/extension (n) exterior deck (n) stairs roof: (n) roof deck. | $200,000 |
| Feb 4, 2016 | Completed final sign-off Nov 2016 | 284 Day St | Goffo Construction Inc | interior remodel, 1st floor: interior remodel of (e) unconditioned areas into habitable/conditioned legal spaces & rooms; 2nd floor: interior remodel of entire (e) floor. structural, mechanical, plumbing & electrical work related to interior remodel.Details
interior remodel, 1st floor: interior remodel of (e) unconditioned areas into habitable/conditioned legal spaces & rooms; 2nd floor: interior remodel of entire (e) floor. structural, mechanical, plumbing & electrical work related to interior remodel. | $85,000 |
| Apr 21, 2014 | Completed final sign-off Jul 2016 | 504 Arlington St | Kingfish Construction Llc. | (n) second floor horizontal extension to the back of (e) house: (n) 1 bedroom, 1 bath and 1 laundryDetails
(n) second floor horizontal extension to the back of (e) house: (n) 1 bedroom, 1 bath and 1 laundry | $40,000 |
| Oct 21, 2013 | Expired or cancelled expired Jan 2018 | 72 Ney St | conversion of existing hall closet into half bath on second floor, remodel of existing roof with "dormer" over new half bath.Details
conversion of existing hall closet into half bath on second floor, remodel of existing roof with "dormer" over new half bath. | $10,000 | |
| Sep 12, 2013 | Completed final sign-off Dec 2013 | 712 Bryant St | unit 6 - interior remodel on 2nd floor.electrical and plumbing on seperate permit.Details
unit 6 - interior remodel on 2nd floor.electrical and plumbing on seperate permit. | $30,000 | |
| Jul 18, 2013 | Completed final sign-off Jun 2014 | 150 Gellert Dr | C & L Construction And Remodeling | kitchen remodel, demolition work, interior wall removal. structural work related to area of remodel, mechanical, plumbing & electrical work related to area of remodel. half bath remodel.Details
kitchen remodel, demolition work, interior wall removal. structural work related to area of remodel, mechanical, plumbing & electrical work related to area of remodel. half bath remodel. | $55,000 |
| May 7, 2013 | Completed final sign-off Aug 2013 | 635 38th Av | L H Gao Construction Inc. | 1) create bathroom in extg house 2)remodel of extg bathroom,3)remodel ceiling finish in bedroom one. 4)create bedroom closet within extg house, 5)plmg work related to bathrooms. 6) electrical work related to bathrooms, 7)replace extg tube and knob receptacle wiring in all extg bedrooms.Details
1) create bathroom in extg house 2)remodel of extg bathroom,3)remodel ceiling finish in bedroom one. 4)create bedroom closet within extg house, 5)plmg work related to bathrooms. 6) electrical work related to bathrooms, 7)replace extg tube and knob receptacle wiring in all extg bedrooms. | $20,000 |
| Apr 23, 2013 | Completed final sign-off Oct 2013 | 1565 Dolores St | Bay Build Design Inc | convert and remodel extg conditions/habitable space (study) into bedroom: add interior partition wall, add door, close off existingg exterior door, add closet, relocate one light switch.Details
convert and remodel extg conditions/habitable space (study) into bedroom: add interior partition wall, add door, close off existingg exterior door, add closet, relocate one light switch. | $2,500 |
| Apr 24, 2012 | Never finaled issued Jun 2012, no final | 1960 Hayes St | L H Gao Construction Inc. | unit #1 -interior remodel only-demolition of (e) den, storage space, 2 bathrooms, closets, kitchen & concrete guardrail. install new framing, finishes, new ceiling framing & finishes. new den, storage space, 2 bathrooms, closets, kitchen. new lighting, plubming & guardrailDetails
unit #1 -interior remodel only-demolition of (e) den, storage space, 2 bathrooms, closets, kitchen & concrete guardrail. install new framing, finishes, new ceiling framing & finishes. new den, storage space, 2 bathrooms, closets, kitchen. new lighting, plubming & guardrail | $65,000 |
| Mar 1, 2012 | Never finaled issued Mar 2012, no final | 51 Encanto Av | L H Gao Construction Inc. | 1/f- convert (e) unconditioned space to conditioned bedroom & bath. 2/f- remodel (e) kitchen, remove staircase, (n) staircase, (n) windows, remove (e) sunroom, (n) deck, demolition work, structural, electrical & mechancialDetails
1/f- convert (e) unconditioned space to conditioned bedroom & bath. 2/f- remodel (e) kitchen, remove staircase, (n) staircase, (n) windows, remove (e) sunroom, (n) deck, demolition work, structural, electrical & mechancial | $75,000 |
| Apr 19, 2011 | Completed final sign-off Aug 2011 | 635 38th Av | L H Gao Construction Inc. | kitchen alteration/remodel.remove extg finishes, appliances and fixtures. new finishes, appliances and fixtures. new lighting, replace extg windows and door with new windows (not visible from street)Details
kitchen alteration/remodel.remove extg finishes, appliances and fixtures. new finishes, appliances and fixtures. new lighting, replace extg windows and door with new windows (not visible from street) | $25,000 |
| Dec 15, 2010 | Completed final sign-off May 2011 | 1960 Hayes St | C L O Construction | kitchen remodel in unit 7 only. approx. 72 sq. ft. new fixtures, new lighs, new finishes w/i kitchen, new cabinets, new counter top, remove (e) non-load bearing wall, new flooring.Details
kitchen remodel in unit 7 only. approx. 72 sq. ft. new fixtures, new lighs, new finishes w/i kitchen, new cabinets, new counter top, remove (e) non-load bearing wall, new flooring. | $20,000 |
| Nov 30, 2010 | Never finaled issued Dec 2012, no final | 2115 Taraval St | R P Construction Inc. | to demolish 2 stories, 2 units residential & retail building.Details
to demolish 2 stories, 2 units residential & retail building. | $6,000 |
| Jul 14, 2010 | Never finaled issued Dec 2012, no final | 2115 Taraval St | R P Construction Inc. | to erect 4 stories, 2 units, mixed use building.Details
to erect 4 stories, 2 units, mixed use building. | $500,000 |
| Dec 4, 2009 | Never finaled issued Jan 2010, no final | 345 El Camino Del Mar | Dickson Construction | new habitable & ocuupiable spaces on (e) ground floor: family rom, bedroom, hallway, storage & closets. new windows & doors at back, new lights, electrical & plumbing.Details
new habitable & ocuupiable spaces on (e) ground floor: family rom, bedroom, hallway, storage & closets. new windows & doors at back, new lights, electrical & plumbing. | $30,000 |
| Oct 3, 2008 | Completed final sign-off Dec 2009 | 237 Whitney St | 1)remove extg rear wndw and 1 door. platform ladder support.2) new door system and plat form support. 3)new header over door systemDetails
1)remove extg rear wndw and 1 door. platform ladder support.2) new door system and plat form support. 3)new header over door system | $8,000 | |
| Jul 20, 2007 | Expired or cancelled expired Nov 2008 | 1765 Vallejo St | Plath & Company Inc | to comply with notices of violation #200006204, 200236493, 200560581; refer to pa# 200706224873. dry rot repair. replacing all in-like-kind work at front facade only.Details
to comply with notices of violation #200006204, 200236493, 200560581; refer to pa# 200706224873. dry rot repair. replacing all in-like-kind work at front facade only. | $20,000 |
| Jul 20, 2006 | Completed final sign-off Jan 2008 | 1438 Jackson St | Dawson - Clinton Gen Contr Corp | remove (e) wood siding + (e) alum wdws. (n) wood sding +(n) stove base. (n) wdw bays. (n) roof access "penthouse". (n) roof terrace -non combustible trellis, pavers, planters, spa, cooktop.Details
remove (e) wood siding + (e) alum wdws. (n) wood sding +(n) stove base. (n) wdw bays. (n) roof access "penthouse". (n) roof terrace -non combustible trellis, pavers, planters, spa, cooktop. | $80,000 |
| Jan 18, 2006 | Expired or cancelled expired Mar 2008 | 1563 Dolores St | lwr level: remove some int walls, new int walls, new stairs, structural work, window and doors, new bath, furnace, waterheater, lights. 2nd lvl: removal o some int walls, relocate bath, new lights, removal of window, new door and windowsDetails
lwr level: remove some int walls, new int walls, new stairs, structural work, window and doors, new bath, furnace, waterheater, lights. 2nd lvl: removal o some int walls, relocate bath, new lights, removal of window, new door and windows | $60,000 | |
| Jul 28, 2005 | Completed final sign-off Jan 2006 | 2496 43rd Av | bathrm remodel, of wnd level, familyrm remodelof gound level, bathrm remodel of ground level,Details
bathrm remodel, of wnd level, familyrm remodelof gound level, bathrm remodel of ground level, | $45,000 |