Julio Nieto Valle

License
950730
Contractor
About the Contractors State License Board
State contractor license record
Listed as
contractor, designer
Firm
Nieto Valle Construction
Based in
Hayward
On San Francisco permits
Mar 2014 to Aug 2025

24 permits since 2000 (contractor on 24 permits, designer on 1 permit): 24 completed.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. The discipline is read from the letters before the number, as the Board for Professional Engineers, Land Surveyors, and Geologists lists them (its license types, read Oct 16, 2026), and for a C number from whether the permits list the license as an architect or as an engineer. Their ranked record as a contractor is on their contractor page. How to read these records

Worked with

Every other licensed party on the same permits, by the role the city lists them under, with how many of those permits each is on.

Architects
Kevin L. Fuller (2)
Engineers
Thor Matteson (5), Chris Piolo (2), Tek Pe (2), Antoine Samra, Antoine Samra, Bill Daley, Colin Blaney, Dennis Fagent, Engin Yagmur, Ryan Bogart

Where they worked

One dot per permit, coloured by the building type the city or the assessor gives it. A dark circle is several permits close together: click it to zoom in.

Most recent permits

FiledOutcomeAddressContractorWork described on the permitDeclared cost
Aug 20, 2025Completed
final sign-off Nov 2025
248 Cumberland StNieto Valle Constructioninstall a (n) shear wall between line b&d. install a new 4x4 x20' strut along line b w/ 2x block over strut between joists. add a new shear wall between back end of bay window and line #4. supplement beam to post connection along line d in the middle of garage.
Details
Permit
202508203473
Permit issued
Aug 20, 2025
Final sign-off
Nov 10, 2025

install a (n) shear wall between line b&d. install a new 4x4 x20' strut along line b w/ 2x block over strut between joists. add a new shear wall between back end of bay window and line #4. supplement beam to post connection along line d in the middle of garage.

Open the permit page

$22,801
Nov 30, 2023Completed
final sign-off Oct 2024
195 Portola DrNieto Valle Constructionto comply w/ nov #202303480. deconstruction to satisfy & conformance w/ the notice of violation (complaint #202303480) for work conducted without permit. remove all work performed on the exterior at the westside of the house.
Details
Permit
202311301698
Permit issued
Dec 12, 2023
Final sign-off
Oct 18, 2024

to comply w/ nov #202303480. deconstruction to satisfy & conformance w/ the notice of violation (complaint #202303480) for work conducted without permit. remove all work performed on the exterior at the westside of the house.

Open the permit page

$11,200
Aug 2, 2023Completed
final sign-off Jan 2024
3739 20th StNieto Valle Constructionvoluntary strengthening of a portion of e dwelling and is not intened to bring the structure up to current code requirements for new construction.
Details
Permit
202308023534
Permit issued
Aug 2, 2023
Final sign-off
Jan 5, 2024

voluntary strengthening of a portion of e dwelling and is not intened to bring the structure up to current code requirements for new construction.

Open the permit page

$25,320
Oct 17, 2022Completed
final sign-off Jan 2023
199 Burnside AvNieto Valle Constructionrevision to 2022-0602-5431. relocate proposed shear wall on line a from the south end to the north end. no change to shear wall length.
Details
Permit
202210174469
Permit issued
Oct 17, 2022
Final sign-off
Jan 3, 2023

revision to 2022-0602-5431. relocate proposed shear wall on line a from the south end to the north end. no change to shear wall length.

Open the permit page

Jun 30, 2022Completed
final sign-off Oct 2022
459 Potrero AvNieto Valle Constructionvoluntary seismic retrofit as per plan set (a). sill plate anchorage. work does not represent a complete seismic retrofit of the entire bldg.
Details
Permit
202206307507
Permit issued
Jun 30, 2022
Final sign-off
Oct 12, 2022

voluntary seismic retrofit as per plan set (a). sill plate anchorage. work does not represent a complete seismic retrofit of the entire bldg.

Open the permit page

$18,480
Jun 22, 2022Completed
final sign-off Nov 2022
723 Guerrero StNieto Valle Constructionmodification of (e) overhang supports for voluntary seismic retrofit.
Details
Permit
202206226801
Permit issued
Jun 22, 2022
Final sign-off
Nov 15, 2022

modification of (e) overhang supports for voluntary seismic retrofit.

Open the permit page

$21,411
Jun 2, 2022Completed
final sign-off Jan 2023
199 Burnside AvNieto Valle Constructionvoluntary engineered seismic retrofit to comply with the brace and bolt program.this permit is for work to be performed in general confromance w/ california existing building code(cebc), appendix ch.a3(sfbc ab-108)
Details
Permit
202206025431
Permit issued
Jun 2, 2022
Final sign-off
Jan 3, 2023

voluntary engineered seismic retrofit to comply with the brace and bolt program.this permit is for work to be performed in general confromance w/ california existing building code(cebc), appendix ch.a3(sfbc ab-108)

Open the permit page

$94,124
Oct 27, 2021Completed
final sign-off Jul 2022
254 Page StNieto Valle Constructionstructural work only. voluntary strengthening in the crawlspace. adding ply shear walls with foundation and new posts with concrete pad footings.
Details
Permit
202110271251
Permit issued
Nov 12, 2021
Final sign-off
Jul 15, 2022

structural work only. voluntary strengthening in the crawlspace. adding ply shear walls with foundation and new posts with concrete pad footings.

Open the permit page

$70,000
Mar 10, 2021Completed
final sign-off Sep 2021
1239 22nd AvNieto Valle Constructionvoluntary strengthening of 1st floor.
Details
Permit
202103106259
Permit issued
Apr 16, 2021
Final sign-off
Sep 28, 2021

voluntary strengthening of 1st floor.

Open the permit page

$103,750
Aug 30, 2019Completed
final sign-off Aug 2020
1948 Washington StNieto Valle Constructionseismic retrofit at the 1st story as triggered by the mandatory soft story ord. designed per 2016 cebc appx a4 (sfebc chapter 4d)
Details
Permit
201908300300
Permit issued
Sep 10, 2019
Final sign-off
Aug 4, 2020

seismic retrofit at the 1st story as triggered by the mandatory soft story ord. designed per 2016 cebc appx a4 (sfebc chapter 4d)

Open the permit page

$70,000
Sep 18, 2018Completed
final sign-off May 2019
2 Castro StNieto Valle Constructionrevision to 201712196846 details 8 & 5 on s5.1 - rebar and holddowns on concrete grade beam. detail 11 on s8.1 - studs welded into (e) i beam column m,aher na
Details
Permit
201809180691
Permit issued
Sep 19, 2018
Final sign-off
May 15, 2019

revision to 201712196846 details 8 & 5 on s5.1 - rebar and holddowns on concrete grade beam. detail 11 on s8.1 - studs welded into (e) i beam column m,aher na

Open the permit page

Sep 6, 2018Completed
final sign-off May 2019
2 Castro StNieto Valle Constructionrevision to pa 2017-1219-6846, detail 9s8.1 shear clips only. detail 10s8.1 framing field condition different from original detail. cmst straps reduce to 3 locations
Details
Permit
201809069310
Permit issued
Sep 6, 2018
Final sign-off
May 15, 2019

revision to pa 2017-1219-6846, detail 9s8.1 shear clips only. detail 10s8.1 framing field condition different from original detail. cmst straps reduce to 3 locations

Open the permit page

Jun 1, 2018Completed
final sign-off Sep 2018
830 Broderick StNieto Valle Constructionrevision to 201709158484. new shearwalls, footers, stem walls. maher na
Details
Permit
201806010707
Permit issued
Jun 4, 2018
Final sign-off
Sep 21, 2018

revision to 201709158484. new shearwalls, footers, stem walls. maher na

Open the permit page

$50,000
Dec 19, 2017Completed
final sign-off Jul 2019
2 Castro StNieto Valle Constructionto comply with nov 201719241 seismic retrofit. 2016 cebc appendix a-4
Details
Permit
201712196846
Permit issued
Apr 2, 2018
Final sign-off
Jul 1, 2019

to comply with nov 201719241 seismic retrofit. 2016 cebc appendix a-4

Open the permit page

$40,000
Sep 15, 2017Completed
final sign-off Sep 2018
830 Broderick StNieto Valle Constructionsoft story seismic retrofit based on 2016 ibc appendix 4a. no exterior work. ** maher: n/a **
Details
Permit
201709158484
Permit issued
Jan 22, 2018
Final sign-off
Sep 21, 2018

soft story seismic retrofit based on 2016 ibc appendix 4a. no exterior work. ** maher: n/a **

Open the permit page

$60,000
Sep 15, 2017Completed
final sign-off Feb 2022
557 Capp StNieto Valle Constructionseismic upgrade in accordance per sfebc chapter 4-d. 2016 cebc appendix a-4.
Details
Permit
201709158450
Permit issued
Feb 24, 2021
Final sign-off
Feb 23, 2022

seismic upgrade in accordance per sfebc chapter 4-d. 2016 cebc appendix a-4.

Open the permit page

$150,000
May 10, 2017Completed
final sign-off Sep 2017
1920 Jefferson StNieto Valle Constructionrevision to 201601157276 double the thickness of one shear wall to accomodate utilities
Details
Permit
201705106211
Permit issued
Jun 19, 2017
Final sign-off
Sep 29, 2017

revision to 201601157276 double the thickness of one shear wall to accomodate utilities

Open the permit page

Dec 29, 2016Completed
final sign-off Apr 2018
235 Buchanan StNieto Valle Constructions.f.soft story retrofit program per sfbc ch 34b,vinstall steel moment frame & plywood shear panels. 2012 iebc appendix a-4.
Details
Permit
201612296194
Permit issued
Nov 3, 2017
Final sign-off
Apr 10, 2018

s.f.soft story retrofit program per sfbc ch 34b,vinstall steel moment frame & plywood shear panels. 2012 iebc appendix a-4.

Open the permit page

$34,800
Dec 29, 2016Completed
final sign-off Apr 2018
295 Buchanan StNieto Valle Constructions.f. soft story retrofit program sfbc ch 34b, install steel moment frame & plywood shear panels. 2012 iebc appendix a-4.
Details
Permit
201612296191
Permit issued
Nov 3, 2017
Final sign-off
Apr 10, 2018

s.f. soft story retrofit program sfbc ch 34b, install steel moment frame & plywood shear panels. 2012 iebc appendix a-4.

Open the permit page

$34,800
Jul 22, 2016Completed
final sign-off Feb 2017
1213 York StNieto Valle Constructionimplement voluntary engineered seismic retrofit to comply with the brace & bolt program
Details
Permit
201607223053
Permit issued
Jul 22, 2016
Final sign-off
Feb 7, 2017

implement voluntary engineered seismic retrofit to comply with the brace & bolt program

Open the permit page

$31,125
Feb 22, 2016Completed
final sign-off Aug 2016
1694 36th AvNieto Valle Constructionvoluntary strengthening at front of house. install a steel column and concrete grade beam in the garage slab floor as per engineering plans.
Details
Permit
201602220130
Permit issued
Feb 22, 2016
Final sign-off
Aug 22, 2016

voluntary strengthening at front of house. install a steel column and concrete grade beam in the garage slab floor as per engineering plans.

Open the permit page

$21,000
Oct 22, 2015Completed
final sign-off Jul 2016
648 Waller StNieto Valle Constructionsoft story retrofit per sfbc chapter 34b, 2012 iebc appendix a-4. strengthening of crawl space cripple walls, add new shear walls at crawl space.
Details
Permit
201510220502
Permit issued
Jan 20, 2016
Final sign-off
Jul 12, 2016

soft story retrofit per sfbc chapter 34b, 2012 iebc appendix a-4. strengthening of crawl space cripple walls, add new shear walls at crawl space.

Open the permit page

$50,000
Oct 9, 2015Completed
final sign-off Nov 2015
4404 17th StNieto Valle Constructionrepair of failed concrete slab on grade. work is confined to the east half of the garage, within the (e) perimeter footing
Details
Permit
201510099312
Permit issued
Oct 9, 2015
Final sign-off
Nov 18, 2015

repair of failed concrete slab on grade. work is confined to the east half of the garage, within the (e) perimeter footing

Open the permit page

$10,250
Mar 10, 2014Completed
final sign-off Aug 2014
4935 17th StNieto Valle Constructioncompliance with sfbc chapter 34c mandatory soft story seismic retrofit.
Details
Permit
201403100272
Permit issued
Apr 11, 2014
Final sign-off
Aug 21, 2014

compliance with sfbc chapter 34c mandatory soft story seismic retrofit.

Open the permit page

$5,000