On San Francisco permits
Dec 2004 to Jul 2025

14 permits since 2000 (engineer on 11 permits, architect on 3 permits): 6 completed, 7 in progress, 1 expired or cancelled.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. The discipline is read from the letters before the number, as the Board for Professional Engineers, Land Surveyors, and Geologists lists them (its license types, read Oct 16, 2026), and for a C number from whether the permits list the license as an architect or as an engineer. How to read these records

Worked with

Every other licensed party on the same permits, by the role the city lists them under, with how many of those permits each is on.

Contractors
Bcci Construction Company (3), Roebbelen Contracting Inc (2), Alternative Techs Cooperative Inc, Mai Construction Inc., Monterey Mechanical Co, Paragon Mechanical Inc, Park Place Contractors, Richlen Construction
Architects
Gary Semling (2), Joseph Gonzalez
Engineers
Wilson Lee (4), Andrew J. Strickland (2), Carl Crizer (2), Michael Murphy (2), Michael Murphy, Michael Murphy

Most recent permits

FiledOutcomeAddressContractorWork described on the permitDeclared cost
Jul 29, 2025In progress
issued Aug 2025
73 Erie Stnew generator and associated wiring to support the project operation during power outrage. work inches new 100kw standby back up generator.
Details
Permit
202507291887
Permit issued
Aug 22, 2025

new generator and associated wiring to support the project operation during power outrage. work inches new 100kw standby back up generator.

Open the permit page

$50,000
Jun 9, 2025In progress
issued Jul 2025
73 Erie StBcci Construction Companythe scope of work includes a proposed type v, 1 story pre-fabricated trailer by others- plan approval #mac-cm 10067 along with associated flatwork. flatwork improvements including grading of onsite concrete and asphalt areas surrounding the building & the accessible paths of travel from
Details
Permit
202506098250
Permit issued
Jul 1, 2025

the scope of work includes a proposed type v, 1 story pre-fabricated trailer by others- plan approval #mac-cm 10067 along with associated flatwork. flatwork improvements including grading of onsite concrete and asphalt areas surrounding the building & the accessible paths of travel from

Open the permit page

$70,000
May 5, 2025In progress
issued Jun 2025
140 14th StBcci Construction Companyrevision to permit 202210194657 and 202501299326. temporary light relocation to permanent location. update of electrical equipment locations and electrical yard. re-striping of stalls and drive aisles to provide new u-turn lane, fencing, gate updates. add lota devices.
Details
Permit
202505055760
Permit issued
Jun 16, 2025

revision to permit 202210194657 and 202501299326. temporary light relocation to permanent location. update of electrical equipment locations and electrical yard. re-striping of stalls and drive aisles to provide new u-turn lane, fencing, gate updates. add lota devices.

Open the permit page

May 5, 2025In progress
issued Jun 2025
55 Erie StBcci Construction Companyrevision to pa #2022-1019-4666 & 2025-0129-9327 update of electrical equipment. relocated guard shack. added lota devices
Details
Permit
202505055771
Permit issued
Jun 16, 2025

revision to pa #2022-1019-4666 & 2025-0129-9327 update of electrical equipment. relocated guard shack. added lota devices

Open the permit page

May 2, 2024In progress
issued Nov 2025
430 Bush StRoebbelen Contracting Incinstall (1) standby packaged 2mw 4160 volt diesel generator #3 (gen-3) & its associated after treatment system on the roof of 430 bush. provide & install fuel piping which transfer between the two buildings. provide & install piping for the equip. mentioned above. all misc. arch, mech, elec, & ...
Details
Permit
202405021307
Permit issued
Nov 19, 2025

install (1) standby packaged 2mw 4160 volt diesel generator #3 (gen-3) & its associated after treatment system on the roof of 430 bush. provide & install fuel piping which transfer between the two buildings. provide & install piping for the equip. mentioned above. all misc. arch, mech, elec, & ...

Open the permit page

$400,000
Nov 10, 2022In progress
issued Nov 2025
555 Pine StRoebbelen Contracting Incinstall 540 gal urea tank on the 1st floor of 555 pine. provide & install fuel piping & associated fuel pumps at 555 pine which transfer between the two buildings. provide & install piping for the equipment mentioned above. all misc. arch, mech, elec, & controls work required to complete the project
Details
Permit
202211106284
Permit issued
Nov 19, 2025

install 540 gal urea tank on the 1st floor of 555 pine. provide & install fuel piping & associated fuel pumps at 555 pine which transfer between the two buildings. provide & install piping for the equipment mentioned above. all misc. arch, mech, elec, & controls work required to complete the project

Open the permit page

$100,000
Oct 19, 2022In progress
issued Dec 2023
140 14th StRichlen Constructioninstall 20 ev chargers for 40 vehicles. convert from vehicle storage lot to fleet charging use.
Details
Permit
202210194657
Permit issued
Dec 29, 2023

install 20 ev chargers for 40 vehicles. convert from vehicle storage lot to fleet charging use.

Open the permit page

$500,000
May 4, 2016Completed
final sign-off Jan 2017
2495 Golden Gate AvMai Construction Inc.replacement of 2 existing 550 gallon lube oil storage tanks with 2 new 550 gallon double wall lube oil storage tanks in existing mechanical equipment pit. maher not req
Details
Permit
201605046571
Permit issued
Jun 23, 2016
Final sign-off
Jan 18, 2017

replacement of 2 existing 550 gallon lube oil storage tanks with 2 new 550 gallon double wall lube oil storage tanks in existing mechanical equipment pit. maher not req

Open the permit page

$20,000
Jun 6, 2013Completed
final sign-off Jun 2015
2445 Golden Gate AvMonterey Mechanical Coremoval of existing 75 kw standby generator in harney scence center mech room. new 230 kw standby diesel generator at the roof of the harney science center with piping and conduits routed to a new fuel storage tank at gr level
Details
Permit
201306068840
Permit issued
May 29, 2014
Final sign-off
Jun 4, 2015

removal of existing 75 kw standby generator in harney scence center mech room. new 230 kw standby diesel generator at the roof of the harney science center with piping and conduits routed to a new fuel storage tank at gr level

Open the permit page

$230,000
Feb 8, 2012Completed
final sign-off Sep 2012
2130 Fulton StParagon Mechanical Incinstallation of replacment chiller on roof of harney science center. removal of existing chiller and cooling tower in 1st floor of harney science center
Details
Permit
201202083799
Permit issued
Jun 1, 2012
Final sign-off
Sep 6, 2012

installation of replacment chiller on roof of harney science center. removal of existing chiller and cooling tower in 1st floor of harney science center

Open the permit page

$250,000
Aug 11, 2009Completed
final sign-off Oct 2009
1 South Van Ness AvAlternative Techs Cooperative Inc6th fl - seismic bracing of exiting raised access anchorage and overhead seismic racing of data center equipment and cabinets. installation of overhead cable ladder rack.
Details
Permit
200908114548
Permit issued
Aug 20, 2009
Final sign-off
Oct 27, 2009

6th fl - seismic bracing of exiting raised access anchorage and overhead seismic racing of data center equipment and cabinets. installation of overhead cable ladder rack.

Open the permit page

$46,500
Sep 23, 2008Completed
final sign-off Feb 2010
1930 Steiner Stvoluntary seismic upgrade, accessibility upgrade, minor plumbing, mechanical improvements, restroom upgrade. no facade work.
Details
Permit
200809232374
Permit issued
Dec 5, 2008
Final sign-off
Feb 2, 2010

voluntary seismic upgrade, accessibility upgrade, minor plumbing, mechanical improvements, restroom upgrade. no facade work.

Open the permit page

$2,500,000
Mar 7, 2005Expired or cancelled
expired Jul 2008
444 Presidio AvPark Place Contractorsas built revision to original pa# 2004/06/24/7284 per corrective action from notice of violation
Details
Permit
200503076866
Permit issued
Mar 7, 2005

as built revision to original pa# 2004/06/24/7284 per corrective action from notice of violation

Open the permit page

$10,000
Dec 28, 2004Completed
final sign-off Mar 2006
2191 Market Stinstall 3 panel antennas & 2 gps antennas on roof top railing.
Details
Permit
200412282229
Permit issued
Jun 27, 2005
Final sign-off
Mar 1, 2006

install 3 panel antennas & 2 gps antennas on roof top railing.

Open the permit page

$125,000