Aaron Hyland
- Listed as
- architect
- Firm
- Architectural Resources
- Based in
- San Francisco
- On San Francisco permits
- Aug 2011 to Feb 2013
5 permits since 2000 (architect on 5 permits): 4 completed, 1 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Feb 15, 2013 | Completed final sign-off May 2014 | 930 Chestnut St | Mc Cutcheon Construction Co. | remove siste wall at front property line and shrubs to allow equipment acccess pursuant to 201211134144 for foundation and seismic improvements. site wall and landscape will be either salvaged and reinstalled or replaced in kind at end of constructionDetails
remove siste wall at front property line and shrubs to allow equipment acccess pursuant to 201211134144 for foundation and seismic improvements. site wall and landscape will be either salvaged and reinstalled or replaced in kind at end of construction | $1,000 |
| Nov 13, 2012 | Completed final sign-off May 2014 | 930 Chestnut St | Ggd Inc. | seismic upgrade the basement. work inlcudles excavation of e crawl space by +/- 2' on east side and +/- 6' on west side. new retaining wall. new footings, new stem wal, new posts, new slab to be constructed. e wlevator to be enlargedDetails
seismic upgrade the basement. work inlcudles excavation of e crawl space by +/- 2' on east side and +/- 6' on west side. new retaining wall. new footings, new stem wal, new posts, new slab to be constructed. e wlevator to be enlarged | $275,000 |
| Apr 9, 2012 | Expired or cancelled cancelled Jan 2020 | 100 John F. Kennedy Dr | Grand Industries Inc | to erect 1 story, special events building.Details
to erect 1 story, special events building. | $50,000 |
| Nov 2, 2011 | Completed final sign-off Aug 2012 | 449 Powell St | tenant improvements on the 2nd, 3rd floors. roof penetrations and ducts will not be visible from street.4th floor under separate permit.new communicating stairs from 2nd to 3rd floors.new communicating stairs from 3rd to 4th floors.Details
tenant improvements on the 2nd, 3rd floors. roof penetrations and ducts will not be visible from street.4th floor under separate permit.new communicating stairs from 2nd to 3rd floors.new communicating stairs from 3rd to 4th floors. | $600,000 | |
| Aug 26, 2011 | Completed final sign-off Nov 2011 | 245 Linden St | Hathaway Dinwiddie Co. | revison to pa# 2011.07.29.1288 ( congregative living behind church) replacement of plaster wall along property lines/ replacement of mud sill and framing along ground floor level that was damaged due to water to the church building,Details
revison to pa# 2011.07.29.1288 ( congregative living behind church) replacement of plaster wall along property lines/ replacement of mud sill and framing along ground floor level that was damaged due to water to the church building, | $8,000 |