How long do kitchen remodel permits take in San Francisco's Mission neighborhood?

In the Mission neighborhood of San Francisco, of the 145 kitchen remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 1 day, the same as a year earlier. Of the 90 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 144 days of being issued, down from 217 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long kitchen remodel permits take in San Francisco'sMission neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/mission/kitchen · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026145 issued1144 issued1
Permit issued to final sign-offOctober 2023 through September 202490 finished144105 finished217

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 176 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q3433107752700too recent
2026-Q24438059161101480too recent
2026-Q14337174181041680too recent
2025-Q44339160271402900too recent
2025-Q34847077331443020too recent
2025-Q239373182192003390too recent
2025-Q1393704925912570too recent
2024-Q42523049151423540too recent
2024-Q33028298251413080yes
2024-Q23837175252454910yes
2024-Q12827152181263620yes
2023-Q43229073221393400yes
2023-Q3353201802114341611yes
2023-Q23333886272377715yes
2023-Q13633063261445925yes
2022-Q443416266312337168yes
2022-Q345400261352324823yes
2022-Q273685995219763810yes
2022-Q166600715021658811yes
2021-Q473722892451723918yes
2021-Q355530614119969210yes
2021-Q25857057471834837yes
2021-Q165580128512145005yes
2020-Q464600210501835929yes
2020-Q3433722276301915945yes
2020-Q22522785152357924yes
2020-Q1605801463924082415yes
2019-Q4645813434503361,1108yes
2019-Q359570923920583614yes
2019-Q248470104361684349yes
2019-Q15147066391853769yes
2018-Q462592674420852012yes
2018-Q3636041244522653912yes
2018-Q258551313724548517yes
2018-Q160551116361761,07016yes
2017-Q4646011034321067413yes
2017-Q3585573154019555310yes
2017-Q270640754611945516yes
2017-Q157550373441859478yes
2016-Q465560884223766113yes
2016-Q3696202574922972712yes
2016-Q2757111244718159920yes
2016-Q166530564118180711yes
2015-Q476710189601747357yes
2015-Q373650175542226838yes
2015-Q263570155431794979yes
2015-Q17367389532166678yes
2014-Q447470149391825146yes
2014-Q375700195318646519yes
2014-Q275690795218056414yes
2014-Q173680685417647412yes
2013-Q47270086562001,09612yes
2013-Q37170034591953639yes
2013-Q26260097541013615yes
2013-Q14947083612252210yes
2012-Q453521393923554712yes
2012-Q35250061421373607yes
2012-Q26462069491263829yes
2012-Q16060021501683077yes
2011-Q449481141421524174yes
2011-Q35452011461624205yes
2011-Q25048019431454913yes
2011-Q1242402021842561yes
2010-Q458571201441687177yes
2010-Q34139031331573553yes
2010-Q25754015491595104yes
2010-Q14139020281184648yes
2009-Q43934039291636253yes
2009-Q3343406291294382yes
2009-Q23737053251794097yes
2009-Q13333083242063228yes
2008-Q451460163012240811yes
2008-Q3545105351324555yes
2008-Q251500283112533311yes
2008-Q145410152281293003yes
2007-Q459550653314929211yes
2007-Q37369044014236016yes
2007-Q250490222813838610yes
2007-Q1303000151032558yes
2006-Q427270103111404667yes
2006-Q3515100331483195yes
2006-Q2333300181322185yes
2006-Q1434300261952915yes
2005-Q4353500232033438yes
2005-Q3494800221543979yes
2005-Q2454500231363847yes
2005-Q1474700372004665yes
2004-Q4282700131054233yes
2004-Q3302900141405456yes
2004-Q2383800231492765yes
2004-Q1292900121662198yes
2003-Q4363600231523513yes
2003-Q335350015652197yes
2003-Q2232207101682954yes
2003-Q1333300201083562yes
2002-Q44038025231313566yes
2002-Q3262600181092773yes
2002-Q22120017101543434yes
2002-Q134330016832101yes
2001-Q42525071121673612yes
2001-Q33029058161164321yes
2001-Q23333026132043190yes
2001-Q1292903221324750yes
2000-Q4191900121485910yes
2000-Q328280012932000yes
2000-Q24341044181454400yes
2000-Q1282700122504320yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

706 of the 5,121 kitchen remodel permits filed since 2000 (14%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Mission neighborhood

Shown apart, with their own page here: bathroom remodel (5,544 filed, 3,781 finished; contractors); kitchen remodel (5,121 filed, 3,441 finished; contractors); stairs (3,714 filed, 2,590 finished; contractors); deck (1,135 filed, 786 finished; contractors); roof deck (332 filed, 202 finished; contractors). Other types: 41,115 permits. All permits in San Francisco's Mission neighborhood

Nearby neighborhoods

Castro/Upper Market, Noe Valley, Potrero Hill; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.