Permit GraphShortlistSan Francisco building permits since 2000

How long do bathroom remodel permits take in San Francisco's Marina neighborhood?

In the Marina neighborhood of San Francisco, of the 167 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 1 day, up from 0 days a year earlier. Of the 131 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 168 days of being issued, down from 186 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sMarina neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002502017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/marina/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026167 issued1162 issued0
Permit issued to final sign-offOctober 2023 through September 2024131 finished168136 finished186

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q42100too recent
2026-Q3473403540too recent
2026-Q2474402414861230too recent
2026-Q14948338261061900too recent
2025-Q445413103241262820too recent
2025-Q34545031301192410too recent
2025-Q24746026341682910too recent
2025-Q13636036281623720too recent
2024-Q435350136241383630too recent
2024-Q34139050292144270yes
2024-Q23936499301423660yes
2024-Q14745088371263800yes
2023-Q44442181352025930yes
2023-Q342392101371685673yes
2023-Q238350143281946864yes
2023-Q14542027361978005yes
2022-Q44139188351786173yes
2022-Q36050052421524606yes
2022-Q24239138332105755yes
2022-Q15050025462183543yes
2021-Q451450123362186116yes
2021-Q36260064512095048yes
2021-Q26666066532416769yes
2021-Q1848202076620856810yes
2020-Q48379362045718553223yes
2020-Q3767261714919067118yes
2020-Q22524415201445471yes
2020-Q156530100462146008yes
2019-Q45149143401865609yes
2019-Q366650147521699127yes
2019-Q2605801194616670510yes
2019-Q14341020351486756yes
2018-Q459544994017684214yes
2018-Q35552270441403995yes
2018-Q25958259471697739yes
2018-Q144410127321343209yes
2017-Q456543406451781,02610yes
2017-Q3535202674018471010yes
2017-Q264644143531424836yes
2017-Q15956046491858423yes
2016-Q464600200491765968yes
2016-Q354490293411886247yes
2016-Q2625811284618055712yes
2016-Q165620202522387066yes
2015-Q436341408291838663yes
2015-Q341394439312026446yes
2015-Q2565524804318354011yes
2015-Q163611415120288210yes
2014-Q4494601243412560111yes
2014-Q34746090341404949yes
2014-Q259590234551608493yes
2014-Q14545041351183227yes
2013-Q44844682341924787yes
2013-Q3464602803420255810yes
2013-Q25149057401513845yes
2013-Q14848020391804412yes
2012-Q43432082292496232yes
2012-Q34343030381826844yes
2012-Q23835052231253348yes
2012-Q12828150261344172yes
2011-Q43734030301475404yes
2011-Q36160069361664586yes
2011-Q23535083262025423yes
2011-Q14745042381485193yes
2010-Q43534048261592965yes
2010-Q33737072331704582yes
2010-Q232310231281786832yes
2010-Q1494701039953304yes
2009-Q4424008331374243yes
2009-Q32726154221444352yes
2009-Q24644037381063603yes
2009-Q12928091251543570yes
2008-Q43635013241583172yes
2008-Q35957012461654721yes
2008-Q24646034241744072yes
2008-Q1333206221364052yes
2007-Q43533015241743722yes
2007-Q34644021281143352yes
2007-Q2515000321543311yes
2007-Q1504900321033202yes
2006-Q4373600311343121yes
2006-Q3363600241682982yes
2006-Q25756050412394413yes
2006-Q1363600261463490yes
2005-Q43838043221943961yes
2005-Q3424100261974702yes
2005-Q2353500201583631yes
2005-Q125250106161033860yes
2004-Q4242400201824040yes
2004-Q32727013231813820yes
2004-Q23030041211803370yes
2004-Q1242300171482581yes
2003-Q4252506191382520yes
2003-Q3353400231073320yes
2003-Q2242400161483480yes
2003-Q1242400171122500yes
2002-Q413120081024490yes
2002-Q32019029141603031yes
2002-Q23028049241423702yes
2002-Q11919050141221940yes
2001-Q4202003912741480yes
2001-Q31010011471182250yes
2001-Q226250163131474550yes
2001-Q13329027181103780yes
2000-Q422220227122833870yes
2000-Q332320164182665000yes
2000-Q227260105191364381yes
2000-Q1252306161924910yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

409 of the 4,620 bathroom remodel permits filed since 2000 (9%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Marina neighborhood

Shown apart, with their own page here: bathroom remodel (4,620 filed, 3,379 finished; contractors); kitchen remodel (4,226 filed, 3,107 finished; contractors); stairs (1,549 filed, 1,069 finished; contractors); deck (939 filed, 610 finished; contractors); roof deck (573 filed, 329 finished; contractors). Other types: 23,123 permits. All permits in San Francisco's Marina neighborhood

Nearby neighborhoods

Pacific Heights, Russian Hill, Japantown; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.