How long do kitchen remodel permits take in San Francisco's Lone Mountain/USF neighborhood?

In the Lone Mountain/USF neighborhood of San Francisco, of the 44 kitchen remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 1 day, down from 3 days a year earlier. Of the 29 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 198 days of being issued, up from 141 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long kitchen remodel permits take in San Francisco's LoneMountain/USF neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/lone-mountain-usf/kitchen · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202644 issued141 issued3
Permit issued to final sign-offOctober 2023 through September 202429 finished19835 finished141

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 176 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q3161102100too recent
2026-Q2131208040too recent
2026-Q1121072840too recent
2025-Q4111127051062150too recent
2025-Q386228840too recent
2025-Q216160127102132950too recent
2025-Q11212650112634190too recent
2024-Q4871417440too recent
2024-Q3111005383386360yes
2024-Q2171722154122165000yes
2024-Q13320yes
2023-Q4121049271223800yes
2023-Q316150189912884yes
2023-Q26603351125591yes
2023-Q11816033121542336yes
2022-Q41512211092313933yes
2022-Q31212511672105904yes
2022-Q212120136121955720yes
2022-Q11816778122165074yes
2021-Q41515081131834701yes
2021-Q3282514131181785627yes
2021-Q21515021151542670yes
2021-Q12320049193288411yes
2020-Q434320233292576202yes
2020-Q32322050201725721yes
2020-Q29843071975391yes
2020-Q116160148162097120yes
2019-Q421202442162445444yes
2019-Q32219034131746597yes
2019-Q22322223172634645yes
2019-Q12424028181963662yes
2018-Q415147190112116503yes
2018-Q319184146142284443yes
2018-Q222220169162165384yes
2018-Q120174340132531,0464yes
2017-Q416164105132323612yes
2017-Q326230471171798195yes
2017-Q2171671,416132507400yes
2017-Q12221047182104051yes
2016-Q4151527283132547972yes
2016-Q32118328131883965yes
2016-Q216168500142478750yes
2016-Q11614039131846661yes
2015-Q415150252132516531yes
2015-Q319150162121784103yes
2015-Q228281209231855924yes
2015-Q11313092111166382yes
2014-Q4141302881726264yes
2014-Q32020015191643461yes
2014-Q23030043251464745yes
2014-Q12323034211335051yes
2013-Q42019078171633731yes
2013-Q317160215131684791yes
2013-Q21515029131294252yes
2013-Q11212014102003042yes
2012-Q4109067974302yes
2012-Q314140612946612yes
2012-Q22929335261243312yes
2012-Q1141407101001493yes
2011-Q4101003771131672yes
2011-Q31413010111733141yes
2011-Q21818071161834061yes
2011-Q177095996181yes
2010-Q41313032121083121yes
2010-Q3141302111132663yes
2010-Q21615047131413412yes
2010-Q1101001051464704yes
2009-Q41313068101042162yes
2009-Q3151506131083562yes
2009-Q2101001481841,3931yes
2009-Q1171705141985460yes
2008-Q41313015011803552yes
2008-Q3171701111032093yes
2008-Q214140912942981yes
2008-Q116140011801713yes
2007-Q4161500121065401yes
2007-Q3222101141666562yes
2007-Q217170213893682yes
2007-Q1131300111263641yes
2006-Q414140072603963yes
2006-Q3171700131463060yes
2006-Q2161600131784221yes
2006-Q1202000141302491yes
2005-Q4141400111402101yes
2005-Q3202000141683821yes
2005-Q2232300172074000yes
2005-Q1181800141093622yes
2004-Q414130091542850yes
2004-Q311110072292,5642yes
2004-Q211110061904241yes
2004-Q113130081242422yes
2003-Q411110081121882yes
2003-Q310100061161801yes
2003-Q211110082182480yes
2003-Q1880051322051yes
2002-Q413130072874034yes
2002-Q315150081792594yes
2002-Q211110071001240yes
2002-Q111100971333960yes
2001-Q47703240yes
2001-Q355047230yes
2001-Q26601940yes
2001-Q1111102981532680yes
2000-Q411110071143560yes
2000-Q316160481623710yes
2000-Q2101004471863840yes
2000-Q1660054765800yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

180 of the 1,645 kitchen remodel permits filed since 2000 (11%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Lone Mountain/USF neighborhood

Shown apart, with their own page here: bathroom remodel (1,836 filed, 1,363 finished; contractors); kitchen remodel (1,645 filed, 1,201 finished; contractors); stairs (790 filed, 562 finished; contractors); deck (406 filed, 276 finished; contractors); roof deck (100 filed, 63 finished; contractors). Other types: 9,544 permits. All permits in San Francisco's Lone Mountain/USF neighborhood

Nearby neighborhoods

Haight Ashbury, Presidio Heights, Inner Richmond; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.