How long do stairs permits take in San Francisco's Hayes Valley neighborhood?

In the Hayes Valley neighborhood of San Francisco, of the 17 stairs permits filed from October 2025 through September 2026 that have been issued, half were issued within 20 days, up from 19 days a year earlier. Of the 11 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 81 days of being issued, up from 73 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long stairs permits take in San Francisco's Hayes ValleyneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004005002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/hayes-valley/stairs · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202617 issued2021 issued19
Permit issued to final sign-offOctober 2023 through September 202411 finished8121 finished73

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 7 days to issue and 175 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q35110too recent
2026-Q27601440too recent
2026-Q1752613910too recent
2025-Q4554716300too recent
2025-Q31310202175972670too recent
2025-Q23310too recent
2025-Q16420too recent
2024-Q44420too recent
2024-Q35440yes
2024-Q2664805671640yes
2024-Q16410yes
2023-Q42210yes
2023-Q3101034798531271yes
2023-Q25512615291030yes
2023-Q14440yes
2022-Q44440yes
2022-Q35331yes
2022-Q24440yes
2022-Q166237453628601yes
2021-Q45413yes
2021-Q3886820072887210yes
2021-Q277109143yes
2021-Q17645463451774371yes
2020-Q44421yes
2020-Q33320yes
2020-Q23330yes
2020-Q15441yes
2019-Q4870942yes
2019-Q311111027492337791yes
2019-Q26661251604300yes
2019-Q1762811263264180yes
2018-Q488433581767160yes
2018-Q3992767074327942yes
2018-Q2867457242yes
2018-Q155413641yes
2017-Q487028961206371yes
2017-Q366225061331,4180yes
2017-Q212120188111824990yes
2017-Q13312yes
2016-Q465638441yes
2016-Q3981690462284621yes
2016-Q21091447142yes
2016-Q11182215081588700yes
2015-Q4871727051472881yes
2015-Q313111817093589822yes
2015-Q21312015010563092yes
2015-Q1108231539901yes
2014-Q410102145071287360yes
2014-Q35430yes
2014-Q213131228081222964yes
2014-Q112121614494867891yes
2013-Q4882248703930yes
2013-Q3559238041yes
2013-Q216158295131163740yes
2013-Q11313385131383920yes
2012-Q455011241yes
2012-Q3161416309111243362yes
2012-Q2151301359372853yes
2012-Q1552845741yes
2011-Q46440yes
2011-Q34440yes
2011-Q28708561424160yes
2011-Q1770817772080yes
2010-Q488241272123780yes
2010-Q31212034101022381yes
2010-Q2101003382143781yes
2010-Q112112479652830yes
2009-Q4992109714200yes
2009-Q3141311913484100yes
2009-Q2101011689915250yes
2009-Q1181805418502310yes
2008-Q4212002516611951yes
2008-Q3252301316861572yes
2008-Q2212101015342643yes
2008-Q11414010213833390yes
2007-Q41312030161783373yes
2007-Q31616011214642001yes
2007-Q21414019010882461yes
2007-Q11818024911453573yes
2006-Q410902461273552yes
2006-Q3202004317921951yes
2006-Q2222203211481943yes
2006-Q11515012010731221yes
2005-Q41010019432yes
2005-Q31312012334yes
2005-Q2111109751653933yes
2005-Q17701,06843yes
2004-Q4151502018562742yes
2004-Q3660051342530yes
2004-Q2181701013341673yes
2004-Q110100315581242yes
2003-Q41312050631422yes
2003-Q315130011772313yes
2003-Q216150010302664yes
2003-Q118180013571123yes
2002-Q415150239691892yes
2002-Q325240015431585yes
2002-Q217170011542222yes
2002-Q11313051953881yes
2001-Q41212013871762710yes
2001-Q3660000yes
2001-Q2121106761711971yes
2001-Q1760041yes
2000-Q412125293101723610yes
2000-Q31414060101462910yes
2000-Q2131205101202800yes
2000-Q177019340yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

112 of the 1,075 stairs permits filed since 2000 (10%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Hayes Valley neighborhood

Shown apart, with their own page here: bathroom remodel (2,515 filed, 1,731 finished; contractors); kitchen remodel (2,377 filed, 1,703 finished; contractors); stairs (1,075 filed, 733 finished; contractors); deck (395 filed, 257 finished; contractors); roof deck (89 filed, 49 finished; contractors). Other types: 13,591 permits. All permits in San Francisco's Hayes Valley neighborhood

Nearby neighborhoods

Western Addition, Japantown, Castro/Upper Market; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.