How long do bathroom remodel permits take in San Francisco's Hayes Valley neighborhood?

In the Hayes Valley neighborhood of San Francisco, of the 62 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 55 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 156 days of being issued, down from 170 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sHayes Valley neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/hayes-valley/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202662 issued070 issued0
Permit issued to final sign-offOctober 2023 through September 202455 finished15659 finished170

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41000too recent
2026-Q33025015563760too recent
2026-Q21715039561170too recent
2026-Q11412039841440too recent
2025-Q4141004971462790too recent
2025-Q32119035111513360too recent
2025-Q22121030171282620too recent
2025-Q12119283151323960too recent
2024-Q414110681271840too recent
2024-Q32421051191443410yes
2024-Q21716110211902930yes
2024-Q11514073112084900yes
2023-Q41717061141573300yes
2023-Q32626035181462717yes
2023-Q22020436151445172yes
2023-Q11615010141303961yes
2022-Q41616696123646424yes
2022-Q320190119151836473yes
2022-Q22121027181644503yes
2022-Q12323011192265104yes
2021-Q42220026161823123yes
2021-Q33634036301746503yes
2021-Q24440074281844889yes
2021-Q1434001412818848212yes
2020-Q4656126862125851139yes
2020-Q341374792117529216yes
2020-Q21192215281396091yes
2020-Q12524054181864516yes
2019-Q45551133922816434117yes
2019-Q3514953343314840214yes
2019-Q2191802215821972yes
2019-Q14241040351313416yes
2018-Q441388118341826623yes
2018-Q32928551221663605yes
2018-Q24037339341403254yes
2018-Q139380322511346610yes
2017-Q425221216181244892yes
2017-Q33838037291274367yes
2017-Q240400190311835187yes
2017-Q125245976161384464yes
2016-Q437321863251675026yes
2016-Q33433985231438618yes
2016-Q228276121241658603yes
2016-Q13532047291165963yes
2015-Q43231150271183392yes
2015-Q333331169281407445yes
2015-Q25150132421603616yes
2015-Q15149054441363965yes
2014-Q44140034281252277yes
2014-Q352490283515338810yes
2014-Q21716032131053823yes
2014-Q12826067171305248yes
2013-Q42727534221184171yes
2013-Q33332025241765495yes
2013-Q23028015212365876yes
2013-Q1272601423923811yes
2012-Q42625055222466012yes
2012-Q32321023191343732yes
2012-Q2191801171474141yes
2012-Q12321034161034213yes
2011-Q4760042yes
2011-Q32323013181044202yes
2011-Q21414070121254320yes
2011-Q1151504121142321yes
2010-Q4121202911853041yes
2010-Q31818034151823661yes
2010-Q21818111151133100yes
2010-Q11717062151294811yes
2009-Q41512440111654632yes
2009-Q313134104112474171yes
2009-Q21413116121096301yes
2009-Q123220515633473yes
2008-Q4181808141142890yes
2008-Q3303001191221923yes
2008-Q2202003131552674yes
2008-Q12928027191463275yes
2007-Q43535011221283614yes
2007-Q3343402201142724yes
2007-Q2323200221474763yes
2007-Q12625028161812873yes
2006-Q4313001182115235yes
2006-Q3222200131793662yes
2006-Q2242400121317875yes
2006-Q1222200111653013yes
2005-Q4222200141573823yes
2005-Q314130081422360yes
2005-Q2242400141202292yes
2005-Q111110071052901yes
2004-Q411110061562502yes
2004-Q310100051622571yes
2004-Q217160091116282yes
2004-Q111100061223853yes
2003-Q49806551275921yes
2003-Q35430yes
2003-Q2770034yes
2003-Q177007792670yes
2002-Q44412yes
2002-Q398040832yes
2002-Q2990461322981yes
2002-Q155019731yes
2001-Q413130051611770yes
2001-Q3770010yes
2001-Q29902871945560yes
2001-Q110100351683160yes
2000-Q4770030yes
2000-Q310100271193460yes
2000-Q213120081644960yes
2000-Q113130293874870yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

362 of the 2,515 bathroom remodel permits filed since 2000 (14%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Hayes Valley neighborhood

Shown apart, with their own page here: bathroom remodel (2,515 filed, 1,731 finished; contractors); kitchen remodel (2,377 filed, 1,703 finished; contractors); stairs (1,075 filed, 733 finished; contractors); deck (395 filed, 257 finished; contractors); roof deck (89 filed, 49 finished; contractors). Other types: 13,591 permits. All permits in San Francisco's Hayes Valley neighborhood

Nearby neighborhoods

Western Addition, Japantown, Castro/Upper Market; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.