Truebeck Construction
- Based in
- San Mateo
- On San Francisco permits
- Jun 2008 to Sep 2026
- Last 24 months
- 40 permits filed
609 permits since 2000: 463 completed, 26 in progress, 79 never finaled, 41 expired or cancelled.
Of the 79 never-finaled permits, 3 are 3 to 5 years old, 31 are 5 to 10 years old, 45 are over 10 years old. 1 was filed but never issued.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for roof deck across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Roof deck permits
9 roof deck permits: 7 completed, 1 in progress, 1 never finaled. Typically 13 days from filing to permit and 298 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| May 27, 2026 | In progress issued May 2026 | 1 Harrison St | 6/fl- revisoin 202410173107 to include adding guardrail to 6th floor roof deck plan north parapet. in response to as built discovery that the parapet is less than 42" at roof deckDetails
6/fl- revisoin 202410173107 to include adding guardrail to 6th floor roof deck plan north parapet. in response to as built discovery that the parapet is less than 42" at roof deck | |
| Sep 17, 2020 | Completed final sign-off Apr 2021 | 1515 03rd St | revision to pa# 201508245062 s3. to update standpipe locations at occupied roof deck to match site addendum s8 for fire sprinklers.Details
revision to pa# 201508245062 s3. to update standpipe locations at occupied roof deck to match site addendum s8 for fire sprinklers. | |
| Sep 14, 2017 | Completed final sign-off Jun 2018 | 101 02nd St | demo curtain wall system and install nana wall system. new guardrail and wooden deck pavers on new occupiable roof deck and multipurpose room, (n) elevator lobby s-doors configuration and (n) panic hardware on exit stairs. mp room ref pa 201709138056 ** maher: n/a **Details
demo curtain wall system and install nana wall system. new guardrail and wooden deck pavers on new occupiable roof deck and multipurpose room, (n) elevator lobby s-doors configuration and (n) panic hardware on exit stairs. mp room ref pa 201709138056 ** maher: n/a ** | $120,450 |
| Sep 13, 2017 | Completed final sign-off Aug 2018 | 101 02nd St | 12th fl - demo partitions, new stairs, ramp, kitchenette tieing into existing meps for renovation. all new interior finishes. roof deck, curtain wall, fire alarm, and sprinklers on separate submittals.Details
12th fl - demo partitions, new stairs, ramp, kitchenette tieing into existing meps for renovation. all new interior finishes. roof deck, curtain wall, fire alarm, and sprinklers on separate submittals. | $425,050 |
| Jun 1, 2015 | Never finaled issued Jun 2015, no final | 555 Market St | 6th floor construction of (n) assembly spaces (a-3) for single tenant "uber" demo of partition & installation of new partitions, (n) doors, millwork, ceilings, finishes. new food service area (no range) & assembly roof deck. fire/life safety & mep under separate permit.Details
6th floor construction of (n) assembly spaces (a-3) for single tenant "uber" demo of partition & installation of new partitions, (n) doors, millwork, ceilings, finishes. new food service area (no range) & assembly roof deck. fire/life safety & mep under separate permit. | $1,600,000 |
| May 9, 2013 | Completed final sign-off Oct 2013 | 370 03rd St | add new temporary sun shade structure, 6 vertical poles with vertical fabric sun shades at existing roof deck. new support structural steel at 7th floor. fire alarm under sep. permitDetails
add new temporary sun shade structure, 6 vertical poles with vertical fabric sun shades at existing roof deck. new support structural steel at 7th floor. fire alarm under sep. permit | $35,000 |
| Feb 4, 2013 | Completed final sign-off Aug 2014 | 370 03rd St | refer to pa# 2012-0917-9869/r1-roof deck. m.e.p & landscape for new roof deckDetails
refer to pa# 2012-0917-9869/r1-roof deck. m.e.p & landscape for new roof deck | |
| Jul 16, 2012 | Completed final sign-off Sep 2013 | 275 Brannan St | core and shell renovation of existing office building. facade work and interior upgrades. new egress stairs to roof. new roof deck. sprinklers, standpipe, fire alarm permits separateDetails
core and shell renovation of existing office building. facade work and interior upgrades. new egress stairs to roof. new roof deck. sprinklers, standpipe, fire alarm permits separate | $2,500,000 |
| Apr 9, 2012 | Completed final sign-off Aug 2014 | 370 03rd St | structural upgrade for future roof deck - frp reinforcing of concrete beams.Details
structural upgrade for future roof deck - frp reinforcing of concrete beams. | $275,000 |