- 9 permits filed
14 permits since 2000: 8 completed, 5 in progress, 1 never finaled.
Of the 1 never-finaled permit, 1 is 3 to 5 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Sep 2, 2026 | In progress issued Sep 2026 | 600 07th St | units 731,729,728,726,725,724,722,723,623,523,423,323 & 223; 7/f hallway and staff lounge: install approx. 700 sqft of new 5/8" type x drywall & ~750sqft of r-19 insulation in 13 units at 2' high due to flood cuts. no stud replacement, drywall and insulation only. comply with nov #202658363 item 4.Details
units 731,729,728,726,725,724,722,723,623,523,423,323 & 223; 7/f hallway and staff lounge: install approx. 700 sqft of new 5/8" type x drywall & ~750sqft of r-19 insulation in 13 units at 2' high due to flood cuts. no stud replacement, drywall and insulation only. comply with nov #202658363 item 4. | $15,000 |
| Aug 14, 2026 | In progress issued Aug 2026 | 111 Jones St | performing selective demolition of non-structural walls sections of drywall in 7 floors in hallways & apaartments units - 8th floor units, 820, 819, 818, 816, 813 & hallway. 7th floor units 719, 716, 715, 713 & hallway.6th floor units 618, 615 & hallway. 5th floor units 507, 505. 4th floor units 407Details
performing selective demolition of non-structural walls sections of drywall in 7 floors in hallways & apaartments units - 8th floor units, 820, 819, 818, 816, 813 & hallway. 7th floor units 719, 716, 715, 713 & hallway.6th floor units 618, 615 & hallway. 5th floor units 507, 505. 4th floor units 407 | $35,000 |
| Jul 27, 2026 | In progress issued Jul 2026 | 600 07th St | 1-7/f: perform selective demo non-structural wall sections of drywall 7 floors, in hallways & apt units. 1/f -hallway. 2/f - unit# 221,223,224,226, hallway. 3/fl - #321, 323, hallway. 4/f - #421,423,424,426. 5/f - #525, hallwy. 6/f - #621,622,623,624. 7/f -#731,729,728,727,725,723,hallwy. total sf..Details
1-7/f: perform selective demo non-structural wall sections of drywall 7 floors, in hallways & apt units. 1/f -hallway. 2/f - unit# 221,223,224,226, hallway. 3/fl - #321, 323, hallway. 4/f - #421,423,424,426. 5/f - #525, hallwy. 6/f - #621,622,623,624. 7/f -#731,729,728,727,725,723,hallwy. total sf.. | $40,000 |
| Apr 17, 2026 | In progress issued Apr 2026 | 172 06th St | flrs 1-3 lobby areas: perform selective demolition on non structual walls sections of drywall, approx 80 sq ft, along with removal and repair of 30sq ft of flooring.Details
flrs 1-3 lobby areas: perform selective demolition on non structual walls sections of drywall, approx 80 sq ft, along with removal and repair of 30sq ft of flooring. | $3,000 |
| Apr 16, 2026 | In progress issued Apr 2026 | 480 Ellis St | units 442 500 sq ft, unit 342 300 sqft, unit 242 300 sq ft demolition of drywall due to water damage, and demo of drywall in flr 3 and flr 2 hallways, 70 sq ft.Details
units 442 500 sq ft, unit 342 300 sqft, unit 242 300 sq ft demolition of drywall due to water damage, and demo of drywall in flr 3 and flr 2 hallways, 70 sq ft. | $10,000 |
| Feb 17, 2026 | Completed final sign-off Feb 2026 | 455 Fell St | to comply with nov #202431422: install new dry wall in 5 units: 323, 322, 223, 222 & commercial area. no more than 3500 sf of total drywal replacement of type x 6yp board & nails w/5d coolers nails at 4" oc or equivalent. no stud replacement or relocation. replace r-19 insulation unfaced 6" thickDetails
to comply with nov #202431422: install new dry wall in 5 units: 323, 322, 223, 222 & commercial area. no more than 3500 sf of total drywal replacement of type x 6yp board & nails w/5d coolers nails at 4" oc or equivalent. no stud replacement or relocation. replace r-19 insulation unfaced 6" thick | $25,000 |
| Mar 11, 2025 | Completed final sign-off Jun 2025 | 833 Bryant St | drywall replacement no more than 600sf, in-kind replacement of drywall,insulation and flooring materials.no stud replacement or relocation,new drywall should be 5/8 type x gyp board-nails w/ sd cooler,Details
drywall replacement no more than 600sf, in-kind replacement of drywall,insulation and flooring materials.no stud replacement or relocation,new drywall should be 5/8 type x gyp board-nails w/ sd cooler, | $20,000 |
| Feb 21, 2025 | Completed final sign-off Jun 2025 | 833 Bryant St | comply w compl #202305844, replacement of drywall, insulation & flooring materials for residential units 602,607,608,503,504,505. no stud replacement & no relocation of interior wall. new drywall shall be 5/8" type x gyp. bd with 5d cooler nails at 4"o.c.Details
comply w compl #202305844, replacement of drywall, insulation & flooring materials for residential units 602,607,608,503,504,505. no stud replacement & no relocation of interior wall. new drywall shall be 5/8" type x gyp. bd with 5d cooler nails at 4"o.c. | $15,000 |
| Oct 31, 2024 | Completed final sign-off Jan 2025 | 350 Golden Gate Av | revision to pa# 202408138523: unit #410- replacement of approx. 2000sqft drywall w/ 5/8" type x sheetrock, insulation, and flooring.Details
revision to pa# 202408138523: unit #410- replacement of approx. 2000sqft drywall w/ 5/8" type x sheetrock, insulation, and flooring. | $5,000 |
| Aug 13, 2024 | Completed final sign-off Sep 2024 | 350 Golden Gate Av | replacement of drywall, insulation, and flooring materials in units# 203, 207, 210, 301, 307, no wall demolition or construction.Details
replacement of drywall, insulation, and flooring materials in units# 203, 207, 210, 301, 307, no wall demolition or construction. | $10,000 |
| Aug 13, 2024 | Completed final sign-off Jan 2025 | 350 Golden Gate Av | replacement of drywall, insulation, and flooring materials in units# 402, 404, 408, 304, 403, and 303. no wall demolition or construction.Details
replacement of drywall, insulation, and flooring materials in units# 402, 404, 408, 304, 403, and 303. no wall demolition or construction. | $10,000 |
| Aug 13, 2024 | Completed final sign-off Dec 2024 | 350 Golden Gate Av | replacement of drywall, insulation, and flooring materials in units# 407, 411, 310, 202, 209, 401. no wall demolition or construction.Details
replacement of drywall, insulation, and flooring materials in units# 407, 411, 310, 202, 209, 401. no wall demolition or construction. | $10,000 |
| Aug 7, 2024 | Completed final sign-off Sep 2024 | 350 Golden Gate Av | replacement of drywall, insulation and flooring materials in units 201,302,311 and 409. no wall demolition or construction.Details
replacement of drywall, insulation and flooring materials in units 201,302,311 and 409. no wall demolition or construction. | $10,000 |
| Sep 26, 2023 | Never finaled issued Sep 2023, no final | 20 Franklin St | remove and reapply culking on building windows and remove and replace water down spout. not visble from street.Details
remove and reapply culking on building windows and remove and replace water down spout. not visble from street. | $6,000 |