Block 5431A, lot 051
400 Paul Ave
- City’s use
- Industrial
- Built
- 1930
- Stories
- 3
- Rooms
- 11 bathrooms
- Building
- 143,920 sq ft
- Lot
- 317,510 sq ft
- Zoning
- PDR2
- Construction type
- C
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
21 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Apr 11, 2025 | In progress issued Apr 2025 | 400 Paul Av | to obtain final inspection for work approved under pa#: 202012311979 all work is complete.Details
to obtain final inspection for work approved under pa#: 202012311979 all work is complete. | ||
| Jul 26, 2023 | Completed final sign-off Aug 2023 | 400 Paul Av | Walsh Construction Company Ii Llc | revision to pa# 201603293329, updated plan layout, door removed from electrical room in basement. notes added for future scope and for door fire rating requirements.Details
revision to pa# 201603293329, updated plan layout, door removed from electrical room in basement. notes added for future scope and for door fire rating requirements. | |
| Dec 22, 2022 | Never finaled issued Jan 2023, no final | 400 Paul Av | Walsh Construction Company Ii Llc | to renew pa# 2018-0927-1576: pa# 2016-0329-3329: all work complete for t.c.oDetails
to renew pa# 2018-0927-1576: pa# 2016-0329-3329: all work complete for t.c.o | |
| Dec 21, 2022 | Completed final sign-off Aug 2023 | 400 Paul Av | Walsh Construction Company Ii Llc | bldg a and b: permit revision to document tco conditions. revisions include deferring bathrooms on level 2 and basement to tenant improvement phase. ref permits 201603293329 and 202009033417.Details
bldg a and b: permit revision to document tco conditions. revisions include deferring bathrooms on level 2 and basement to tenant improvement phase. ref permits 201603293329 and 202009033417. | |
| Oct 7, 2022 | Expired or cancelled cancelled Jan 2026 | 400 Paul Av | revision to pa#202009033417, 201603293329 to reovide fundation water proofing system in basement.Details
revision to pa#202009033417, 201603293329 to reovide fundation water proofing system in basement. | $20,000 | |
| Jun 8, 2022 | Completed final sign-off May 2023 | 400 Paul Av | Walsh Construction Company Ii Llc | revision to generator and fuel oil addendum revised generator pad design. ref to 2014 1117 1675 s8 & 202010277447.Details
revision to generator and fuel oil addendum revised generator pad design. ref to 2014 1117 1675 s8 & 202010277447. | |
| May 25, 2022 | Completed final sign-off Jul 2022 | 400 Paul Av | Seamless Fire Protection Llc | add 7 quick response concealed pendents for new interior walls and suspended ceiling on 1st flDetails
add 7 quick response concealed pendents for new interior walls and suspended ceiling on 1st fl | $10,000 |
| Aug 20, 2021 | Expired or cancelled withdrawn Nov 2021 | 400 Paul Av | building c: new t.i work for data center of about 90k sz ft. program includes data hall, elec rooms, support office & conference room, all on 30" raised fl with roof mech equip.work on l2 limited to pipe penetrations from roof to level 1. on site there is a new entry @ the north side of bldg.Details
building c: new t.i work for data center of about 90k sz ft. program includes data hall, elec rooms, support office & conference room, all on 30" raised fl with roof mech equip.work on l2 limited to pipe penetrations from roof to level 1. on site there is a new entry @ the north side of bldg. | $1,000,000 | |
| Aug 19, 2021 | Expired or cancelled withdrawn Nov 2021 | 400 Paul Av | bldg a & b - partial ti on level 1 to provide reception & office space. mep to serve limited area of this improvement. structural for (n) building canopy, stair opening, stair and roof equipment. exterior work includes replacements fo windows & new canopy over front doorDetails
bldg a & b - partial ti on level 1 to provide reception & office space. mep to serve limited area of this improvement. structural for (n) building canopy, stair opening, stair and roof equipment. exterior work includes replacements fo windows & new canopy over front door | $858,000 | |
| Dec 31, 2020 | Never finaled issued Mar 2021, no final | 400 Paul Av | Building Electronic Controls Inc. | bldg a/b: errcs for 2 stroy office building reference pa# 201603233329 & 202009033417. core and shell work only.Details
bldg a/b: errcs for 2 stroy office building reference pa# 201603233329 & 202009033417. core and shell work only. | $1,000 |
| Dec 31, 2020 | Never finaled issued Jan 2022, no final | 400 Paul Av | Building Electronic Controls Inc. | bldg a/b: fire alarm for 2 stroy office building reference pa# 201603233329 & 202009033417. core and shell work only.Details
bldg a/b: fire alarm for 2 stroy office building reference pa# 201603233329 & 202009033417. core and shell work only. | $1,000 |
| Nov 5, 2020 | Completed final sign-off May 2023 | 400 Paul Av | Cosco Fire Protection Inc. | two ductile iron stub-outs for fire supply & fdc, connection at 5 ft to building faceDetails
two ductile iron stub-outs for fire supply & fdc, connection at 5 ft to building face | $10,000 |
| Oct 27, 2020 | Never finaled issued Apr 2022, no final | 400 Paul Av | Walsh Construction Company Ii Llc | install ex generator to serve bldg# a/b (under this permit) & bldg# c (under separate permit). reference permit for bldg a/b pa# 201603293329 & pa# 202009033417. total 6 generators.Details
install ex generator to serve bldg# a/b (under this permit) & bldg# c (under separate permit). reference permit for bldg a/b pa# 201603293329 & pa# 202009033417. total 6 generators. | $50,000 |
| Sep 3, 2020 | Never finaled issued Aug 2021, no final | 400 Paul Av | Walsh Construction Company Ii Llc | revision to pa 201603293329: 1.relocate main entry on level 1, add elevator control room, add point of entry rooms to basement level of bldg b, and add architectural details. (see individual sheets for additional comments)Details
revision to pa 201603293329: 1.relocate main entry on level 1, add elevator control room, add point of entry rooms to basement level of bldg b, and add architectural details. (see individual sheets for additional comments) | |
| Sep 1, 2020 | Never finaled issued Aug 2021, no final | 400 Paul Av | Walsh Construction Company Ii Llc | revision to pa 201905069798: 1. change spacing of column grid, added brace frames2. modifies floor loading 3. revised elevations to reflect new column grid, openings on exterior facade, & new elevator shaft height. 4. added fire pump/domestic water pump rooms. 5. other {Details
revision to pa 201905069798: 1. change spacing of column grid, added brace frames2. modifies floor loading 3. revised elevations to reflect new column grid, openings on exterior facade, & new elevator shaft height. 4. added fire pump/domestic water pump rooms. 5. other { | |
| Aug 25, 2020 | Completed final sign-off May 2023 | 400 Paul Av | Cosco Fire Protection Inc. | fire sprinklers. install in accordance w/ nfpa 13: 69 sprinkler heads in the basement, 88 heads on level 1 and 231 heads on level 2. refer to pa 201603293329Details
fire sprinklers. install in accordance w/ nfpa 13: 69 sprinkler heads in the basement, 88 heads on level 1 and 231 heads on level 2. refer to pa 201603293329 | $90,000 |
| Jul 21, 2020 | Completed final sign-off Sep 2021 | 400 Paul Av | Cosco Fire Protection Inc. | the underground installation of the fire sprinkler system for new bldgDetails
the underground installation of the fire sprinkler system for new bldg | $60,000 |
| May 23, 2019 | Never finaled issued Jun 2019, no final | 400 Paul Av | Nova Corp Dba Nova Cm Corp, Walsh Construction Company Ii Llc | fire service for new bldDetails
fire service for new bld | $15,000 |
| Dec 3, 2018 | Expired or cancelled withdrawn Jan 2023 | 400 Paul Av | A & M Lath & Plastering Inc. **Check Id* | revision to 201603293329 new steel brace frame to reinforce building structurallyDetails
revision to 201603293329 new steel brace frame to reinforce building structurally | $10,000 |
| Sep 27, 2018 | Expired or cancelled expired Aug 2023 | 400 Paul Av | A & B Construction, Walsh Construction Company Ii Llc | plumbing system for 400 paul avenue including strom water management. ref pa# 2014/117/17/1675-s1. ** maher: n/a **Details
plumbing system for 400 paul avenue including strom water management. ref pa# 2014/117/17/1675-s1. ** maher: n/a ** | |
| Mar 29, 2016 | Expired or cancelled expired Aug 2023 | 400 Paul Av | Dpr Construction Inc, Nova Corp Dba Nova Cm Corp, Walsh Construction Company Ii Llc | remodel (e) building with new offices, new ceilings, new interior walls.Details
remodel (e) building with new offices, new ceilings, new interior walls. |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Walsh Construction Company Ii Llc (10), Cosco Fire Protection Inc. (3), Building Electronic Controls Inc. (2), Nova Corp Dba Nova Cm Corp (2), A & B Construction, A & M Lath & Plastering Inc. **Check Id*, Dpr Construction Inc, Seamless Fire Protection Llc
- Architects
- Theodore Mahl (7)
- Engineers
- Mark Koenigs (4), Jason Scott Petermann, Jason White, Joseph Young, Mark Rogers, Ronald Wilson, Tony H Shakouri
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.