Permit GraphShortlistSan Francisco building permits since 2000

Theodore Mahl

License
C18946
Look the license up with the state
Listed as
architect, authorized agent-others
Firm
Cac Architects
Based in
San Francisco
On San Francisco permits
Feb 2005 to Jul 2023

11 permits since 2000 (architect on 10 permits, authorized agent-others on 1 permit): 4 completed, 4 never finaled, 3 expired or cancelled.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records

Most recent permits

FiledOutcomeAddressContractorWork described on the permitDeclared cost
Jul 26, 2023Completed
final sign-off Aug 2023
400 Paul AvWalsh Construction Company Ii Llcrevision to pa# 201603293329, updated plan layout, door removed from electrical room in basement. notes added for future scope and for door fire rating requirements.
Details
Permit
202307263010
Status
complete
Filed
Jul 26, 2023
Permit issued
Jul 27, 2023
Final sign-off
Aug 15, 2023
Address
400 Paul Av

revision to pa# 201603293329, updated plan layout, door removed from electrical room in basement. notes added for future scope and for door fire rating requirements.

Open the permit page

Dec 21, 2022Completed
final sign-off Aug 2023
400 Paul AvWalsh Construction Company Ii Llcbldg a and b: permit revision to document tco conditions. revisions include deferring bathrooms on level 2 and basement to tenant improvement phase. ref permits 201603293329 and 202009033417.
Details
Permit
202212218854
Status
complete
Filed
Dec 21, 2022
Permit issued
Jan 6, 2023
Final sign-off
Aug 15, 2023
Address
400 Paul Av

bldg a and b: permit revision to document tco conditions. revisions include deferring bathrooms on level 2 and basement to tenant improvement phase. ref permits 201603293329 and 202009033417.

Open the permit page

Aug 20, 2021Expired or cancelled
withdrawn Nov 2021
400 Paul Avbuilding c: new t.i work for data center of about 90k sz ft. program includes data hall, elec rooms, support office & conference room, all on 30" raised fl with roof mech equip.work on l2 limited to pipe penetrations from roof to level 1. on site there is a new entry @ the north side of bldg.
Details
Permit
202108206844
Status
withdrawn
Filed
Aug 20, 2021
Declared cost
$1,000,000
Address
400 Paul Av

building c: new t.i work for data center of about 90k sz ft. program includes data hall, elec rooms, support office & conference room, all on 30" raised fl with roof mech equip.work on l2 limited to pipe penetrations from roof to level 1. on site there is a new entry @ the north side of bldg.

Open the permit page

$1,000,000
Oct 27, 2020Never finaled
issued Apr 2022, no final
400 Paul AvWalsh Construction Company Ii Llcinstall ex generator to serve bldg# a/b (under this permit) & bldg# c (under separate permit). reference permit for bldg a/b pa# 201603293329 & pa# 202009033417. total 6 generators.
Details
Permit
202010277447
Status
issued
Filed
Oct 27, 2020
Permit issued
Apr 8, 2022
Declared cost
$50,000
Address
400 Paul Av

install ex generator to serve bldg# a/b (under this permit) & bldg# c (under separate permit). reference permit for bldg a/b pa# 201603293329 & pa# 202009033417. total 6 generators.

Open the permit page

$50,000
Sep 3, 2020Never finaled
issued Aug 2021, no final
400 Paul AvWalsh Construction Company Ii Llcrevision to pa 201603293329: 1.relocate main entry on level 1, add elevator control room, add point of entry rooms to basement level of bldg b, and add architectural details. (see individual sheets for additional comments)
Details
Permit
202009033417
Status
issued
Filed
Sep 3, 2020
Permit issued
Aug 11, 2021
Address
400 Paul Av

revision to pa 201603293329: 1.relocate main entry on level 1, add elevator control room, add point of entry rooms to basement level of bldg b, and add architectural details. (see individual sheets for additional comments)

Open the permit page

Sep 1, 2020Never finaled
issued Aug 2021, no final
400 Paul AvWalsh Construction Company Ii Llcrevision to pa 201905069798: 1. change spacing of column grid, added brace frames2. modifies floor loading 3. revised elevations to reflect new column grid, openings on exterior facade, & new elevator shaft height. 4. added fire pump/domestic water pump rooms. 5. other {
Details
Permit
202009013071
Status
issued
Filed
Sep 1, 2020
Permit issued
Aug 11, 2021
Address
400 Paul Av

revision to pa 201905069798: 1. change spacing of column grid, added brace frames2. modifies floor loading 3. revised elevations to reflect new column grid, openings on exterior facade, & new elevator shaft height. 4. added fire pump/domestic water pump rooms. 5. other {

Open the permit page

May 6, 2019Completed
final sign-off May 2023
400 Paul AvWalsh Construction Company Ii Llcrevision to #201411171675-(s1) bldg c. superstrucrue, architectural, mep. foundation filed under #201901241163(s1)
Details
Permit
201905069798
Status
complete
Filed
May 6, 2019
Permit issued
Nov 26, 2019
Final sign-off
May 17, 2023
Address
400 Paul Av

revision to #201411171675-(s1) bldg c. superstrucrue, architectural, mep. foundation filed under #201901241163(s1)

Open the permit page

Mar 29, 2016Expired or cancelled
expired Aug 2023
400 Paul AvDpr Construction Inc, Nova Corp Dba Nova Cm Corp, Walsh Construction Company Ii Llcremodel (e) building with new offices, new ceilings, new interior walls.
Details
Permit
201603293329
Status
expired
Filed
Mar 29, 2016
Permit issued
Jul 25, 2016
Address
400 Paul Av

remodel (e) building with new offices, new ceilings, new interior walls.

Open the permit page

Nov 17, 2014Completed
final sign-off Aug 2016
400 Paul AvDpr Construction Incdemolish one story manafacturing center. ** maher: compliance with ordinance no# 155-13 required; route to dph **
Details
Permit
201411171680
Status
complete
Filed
Nov 17, 2014
Permit issued
Oct 20, 2015
Final sign-off
Aug 23, 2016
Declared cost
$20,000
Address
400 Paul Av

demolish one story manafacturing center. ** maher: compliance with ordinance no# 155-13 required; route to dph **

Open the permit page

$20,000
Nov 17, 2014Never finaled
issued Oct 2015, no final
400 Paul AvDpr Construction Inc, Nova Corp Dba Nova Cm Corp, Walsh Construction Company Ii Llcto erect 2 stories, no basement, data center building. ** maher: compliance with ordinance no# 155-13 not required
Details
Permit
201411171675
Status
issued
Filed
Nov 17, 2014
Permit issued
Oct 20, 2015
Declared cost
$300,000
Address
400 Paul Av

to erect 2 stories, no basement, data center building. ** maher: compliance with ordinance no# 155-13 not required

Open the permit page

$300,000
Feb 10, 2005Expired or cancelled
expired Jun 2006
1314 Polk Strenew 200404068109 & 200405275006.
Details
Permit
200502105299
Status
expired
Filed
Feb 10, 2005
Permit issued
Feb 10, 2005
Address
1314 Polk St

renew 200404068109 & 200405275006.

Open the permit page