Permits filed here
33 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jul 29, 2026 | In progress issued Aug 2026 | 150 Hooper St | Errc Systems Inc (Former Dishnet Direct) | provide design to upgrade bda & bbu for erces systems.Details
provide design to upgrade bda & bbu for erces systems. | $35,000 |
| Jan 15, 2025 | In progress issued Apr 2025 | 150 Hooper St | Stc Netcom Inc. | installation of an unmanned telecomm facility, consisting of a rooftop design with anennaes concealed by frp screening. related supporting equipment included.Details
installation of an unmanned telecomm facility, consisting of a rooftop design with anennaes concealed by frp screening. related supporting equipment included. | $195,000 |
| Dec 23, 2021 | Completed final sign-off Aug 2022 | 150 Hooper St | Cochran Inc Dba Cochran Electric Co Inc | fire only: revision to pa# 201410239755. errcs upgrade.Details
fire only: revision to pa# 201410239755. errcs upgrade. | $5,000 |
| Jan 13, 2020 | Never finaled issued Jan 2020, no final | 150 Hooper St | Bcci Construction Company | to obtain a final inspection for work approved under previous permits 201807104093 & 201811065091. all work is complete.Details
to obtain a final inspection for work approved under previous permits 201807104093 & 201811065091. all work is complete. | $10 |
| Jul 9, 2019 | Completed final sign-off May 2021 | 150 Hooper St | Siemens Industry, Inc. | fire alarm work the linamar remodel on floor 2, additions are 3 duct detectors, 1 horn/strobe, 1 strobe ref 201905080084Details
fire alarm work the linamar remodel on floor 2, additions are 3 duct detectors, 1 horn/strobe, 1 strobe ref 201905080084 | $5,935 |
| Jun 3, 2019 | Completed final sign-off Jan 2020 | 150 Hooper St | Gci, Inc | 212 & 214 - mechanical - install 3 fan coil units & duct workDetails
212 & 214 - mechanical - install 3 fan coil units & duct work | $88,000 |
| May 8, 2019 | Completed final sign-off Sep 2020 | 150 Hooper St | Gci, Inc | ti - unit 212 & 214 on 2nd flr. partition & door for conference room, a sound-rated door btwn units, relocattion of plumbing for utility sink & misc finishesDetails
ti - unit 212 & 214 on 2nd flr. partition & door for conference room, a sound-rated door btwn units, relocattion of plumbing for utility sink & misc finishes | $300,000 |
| Feb 26, 2019 | Never finaled issued Mar 2019, no final | 150 Hooper St | Acrat Plumbing & Heating | suite # 211: interior t.i. for r&d tenant wtth new non-structural partitons and finishes , fire life safety & sprinkler under separate permit.Details
suite # 211: interior t.i. for r&d tenant wtth new non-structural partitons and finishes , fire life safety & sprinkler under separate permit. | $100,000 |
| Jan 10, 2019 | Completed final sign-off Jan 2019 | 150 Hooper St | Siemens Industry, Inc. | 4th flr - fire alarm - add 2 smk dets, 4 duct dets, 4 horn/strobes and 1 strobe. for "human made" ref 201809180668Details
4th flr - fire alarm - add 2 smk dets, 4 duct dets, 4 horn/strobes and 1 strobe. for "human made" ref 201809180668 | $10,690 |
| Jan 9, 2019 | Expired or cancelled cancelled Jan 2026 | 150 Hooper St | construction of partition wall, 29'long and 18' 1/4" tall with one door and three windows.Details
construction of partition wall, 29'long and 18' 1/4" tall with one door and three windows. | $20,000 | |
| Dec 28, 2018 | Completed final sign-off Jul 2020 | 150 Hooper St | Bcci Construction Company | 4th floor: revision to app#201809180668: to change to rating on wall. n/a for maherDetails
4th floor: revision to app#201809180668: to change to rating on wall. n/a for maher | $1,000 |
| Nov 16, 2018 | Never finaled issued Nov 2018, no final | 150 Hooper St | 2nd fl - new sink and casework in existing breakroom. existing electrical and rough in plumbingDetails
2nd fl - new sink and casework in existing breakroom. existing electrical and rough in plumbing | $5,000 | |
| Nov 13, 2018 | Never finaled issued Jan 2019, no final | 150 Hooper St | Bcci Construction Company | 4th fl: mech to support appproved arch for office/workshop project. new fsds. ref pa #201809180668.Details
4th fl: mech to support appproved arch for office/workshop project. new fsds. ref pa #201809180668. | $75,000 |
| Nov 6, 2018 | Expired or cancelled expired Jul 2020 | 150 Hooper St | Bcci Construction Company | unit 211. add a demising wall in order to create unit 215Details
unit 211. add a demising wall in order to create unit 215 | $5,000 |
| Nov 1, 2018 | Completed final sign-off Dec 2018 | 150 Hooper St | R L H Fire Protection Inc | fire sprinkler add 12 and delete 1 upright sprinkler on the 4th fl ref 201809180668Details
fire sprinkler add 12 and delete 1 upright sprinkler on the 4th fl ref 201809180668 | $6,500 |
| Oct 3, 2018 | Completed final sign-off Nov 2018 | 150 Hooper St | John A Lehman Dba Lehman Construction | t.i. new interior partitionDetails
t.i. new interior partition | $728 |
| Sep 26, 2018 | Completed final sign-off Oct 2018 | 150 Hooper St | Bcci Construction Company | 3rd fl: architectural drawings of construction of demising wall in unit 3a to create unit 3g. mep submittals deferred.Details
3rd fl: architectural drawings of construction of demising wall in unit 3a to create unit 3g. mep submittals deferred. | $15,000 |
| Sep 18, 2018 | Completed final sign-off Jul 2020 | 150 Hooper St | Bcci Construction Company | tenant build out of 4th fl suite for manufacturing studio including machine shop, wood shop, office and conference space, breakroom. no changes to e lighting, defered mep, sprinkler, alarmDetails
tenant build out of 4th fl suite for manufacturing studio including machine shop, wood shop, office and conference space, breakroom. no changes to e lighting, defered mep, sprinkler, alarm | $600,000 |
| Aug 2, 2018 | Completed final sign-off Aug 2018 | 150 Hooper St | Siemens Industry, Inc. | 2nd flr - fire alarm work "placemade" add 3 duct det, 16 horn/strobes and 5 strobes ref 201803163925Details
2nd flr - fire alarm work "placemade" add 3 duct det, 16 horn/strobes and 5 strobes ref 201803163925 | $17,660 |
| Aug 2, 2018 | Completed final sign-off Aug 2018 | 150 Hooper St | Siemens Industry, Inc. | 1st fl. f/a. alarm work for the "placemade". additions are 1 duct det, 1 horn/strobe power supply & 8 horn/strobes. ref#201803163916. n/a for maher.Details
1st fl. f/a. alarm work for the "placemade". additions are 1 duct det, 1 horn/strobe power supply & 8 horn/strobes. ref#201803163916. n/a for maher. | $8,250 |
| Aug 2, 2018 | Completed final sign-off Aug 2018 | 150 Hooper St | Siemens Industry, Inc. | 4th flr - fire alarm work "placemade" add 10 duct det, 7 horn/strobes and 3 strobes ref 201803163921Details
4th flr - fire alarm work "placemade" add 10 duct det, 7 horn/strobes and 3 strobes ref 201803163921 | $21,940 |
| Aug 2, 2018 | Completed final sign-off Aug 2018 | 150 Hooper St | Siemens Industry, Inc. | 3rd flr - fire alarm work "placemade" add 1 duct det, 1 horn/strobe power supply, 14 horn/strobes and 3 strobes ref 201803163914. n/a for maher.Details
3rd flr - fire alarm work "placemade" add 1 duct det, 1 horn/strobe power supply, 14 horn/strobes and 3 strobes ref 201803163914. n/a for maher. | $13,700 |
| Jul 10, 2018 | Expired or cancelled expired Jul 2020 | 150 Hooper St | Bcci Construction Company | rev to pa# 201803163925; to omit door at non-rated corridor & break rm.Details
rev to pa# 201803163925; to omit door at non-rated corridor & break rm. | |
| Jun 26, 2018 | Completed final sign-off Aug 2018 | 150 Hooper St | R L H Fire Protection Inc | 1st flr - fire sprinkler - relocate 1, add 1 penden.t ti# 201803163921 maher naDetails
1st flr - fire sprinkler - relocate 1, add 1 penden.t ti# 201803163921 maher na | $1,000 |
| Jun 26, 2018 | Completed final sign-off May 2025 | 150 Hooper St | R L H Fire Protection Inc | 3rd flr - fire sprinkler - add 15 uprights. ti #201803163916 maher naDetails
3rd flr - fire sprinkler - add 15 uprights. ti #201803163916 maher na | $8,000 |
| Jun 26, 2018 | Completed final sign-off Jun 2025 | 150 Hooper St | R L H Fire Protection Inc | 2nd flr - fire sprinkler - relocate 23 and delete 8 uprights ti # 201803163914 maher naDetails
2nd flr - fire sprinkler - relocate 23 and delete 8 uprights ti # 201803163914 maher na | $12,500 |
| Mar 16, 2018 | Never finaled issued Apr 2018, no final | 150 Hooper St | Bcci Construction Company | t.i. to 1 suite (full floor) om 4th level in new building. work includes, power, lighting, plumbing & hvac systems. 12785 sf. maher naDetails
t.i. to 1 suite (full floor) om 4th level in new building. work includes, power, lighting, plumbing & hvac systems. 12785 sf. maher na | $882,000 |
| Mar 16, 2018 | Never finaled issued Apr 2018, no final | 150 Hooper St | Bcci Construction Company | ti to 3 ground level suites in new building. work includes partitions, lighting, plumbing & exhaust system. 8430 sfDetails
ti to 3 ground level suites in new building. work includes partitions, lighting, plumbing & exhaust system. 8430 sf | $707,000 |
| Mar 16, 2018 | Never finaled issued Apr 2018, no final | 150 Hooper St | Bcci Construction Company | ti to create 4 light industrial workshop suites on 3rd level in new building. work includes pratitions, lighting, plumbing & ventilation system. 12785 sf, fire alarm and sprinklers under separate permits.Details
ti to create 4 light industrial workshop suites on 3rd level in new building. work includes pratitions, lighting, plumbing & ventilation system. 12785 sf, fire alarm and sprinklers under separate permits. | $747,500 |
| Mar 16, 2018 | Never finaled issued Apr 2018, no final | 150 Hooper St | Bcci Construction Company | t.i. to 4 suite on 2nd fl in new building. work includes partitions, lighting, plumbing & ventilation systems. 12775 sf. maher na sprinkler nad fire alarm separte permitDetails
t.i. to 4 suite on 2nd fl in new building. work includes partitions, lighting, plumbing & ventilation systems. 12775 sf. maher na sprinkler nad fire alarm separte permit | $853,000 |
| Nov 6, 2017 | Completed final sign-off Oct 2018 | 150 Hooper St | Dpr Construction Inc | all floors: evacuation signage for 150 hooper fire permit only. n/a for maherDetails
all floors: evacuation signage for 150 hooper fire permit only. n/a for maher | $2,000 |
| Oct 25, 2017 | Completed final sign-off Jun 2020 | 150 Hooper St | Dpr Construction | revision to 201410239755 s3 add outdoor rated access panel at elevator penthouseDetails
revision to 201410239755 s3 add outdoor rated access panel at elevator penthouse | $1,000 |
| Aug 18, 2017 | Completed final sign-off Jun 2020 | 150 Hooper St | Dpr Construction | rev to superstructure addendum pa#201410239755-s2: changes to roof p1 slab for new mep equipment changes. changes to misc details. add elevator guardrail support & roof top davitts.Details
rev to superstructure addendum pa#201410239755-s2: changes to roof p1 slab for new mep equipment changes. changes to misc details. add elevator guardrail support & roof top davitts. | $10,000 |
Find contractors for work like this