Permit GraphShortlistSan Francisco building permits since 2000

Block 0738, lot 019

939 Ellis St

City’s use
Commercial Office
Built
1961
Stories
7
Rooms
12 bathrooms
Building
116,000 sq ft
Lot
16,500 sq ft
Zoning
RC4
Construction type
S

From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map

Permits filed here

55 permits filed for this property since 2000.

CompletedIn progressNever finaledExpired or cancelled
FiledOutcomeAddressContractorWork described on the permitDeclared cost
Jan 2, 2025In progress
issued Feb 2025
939 Ellis StConvergint Technologies Llcfire alarm t.i. voluntary upgrade. new celluar diater in main elec rm, new monitoring point for dialer
Details
Permit
202501027611
Permit issued
Feb 4, 2025

fire alarm t.i. voluntary upgrade. new celluar diater in main elec rm, new monitoring point for dialer

Open the permit page

$1,000
Jan 14, 2022Completed
final sign-off Oct 2022
939 Ellis StKaiser Foundation Health Plan Incproject involves replacement of door hardware found not to be in compliance as part of sffd annual inspection work inclues: replacement of door hardware at conference room 7103 (noted as conference room #7 on report), stair 1 door, stiar 2 door and stair vestibule at level 7.
Details
Permit
202201146011
Permit issued
Mar 11, 2022
Final sign-off
Oct 4, 2022

project involves replacement of door hardware found not to be in compliance as part of sffd annual inspection work inclues: replacement of door hardware at conference room 7103 (noted as conference room #7 on report), stair 1 door, stiar 2 door and stair vestibule at level 7.

Open the permit page

$15,000
May 27, 2021Completed
final sign-off Mar 2022
939 Ellis Sterrcs upgrade - revision to pa #2017-0605-8424 1. reprogram frequencies per ccsf dt 2. replace rooftop yagi antenna with a panel antenna 3. re-test errcs per ab #2.04 2019 4. coordinate inspections w/ccsf dt & sffd
Details
Permit
202105271232
Permit issued
Jul 20, 2021
Final sign-off
Mar 29, 2022

errcs upgrade - revision to pa #2017-0605-8424 1. reprogram frequencies per ccsf dt 2. replace rooftop yagi antenna with a panel antenna 3. re-test errcs per ab #2.04 2019 4. coordinate inspections w/ccsf dt & sffd

Open the permit page

Jun 11, 2020Never finaled
filed Jun 2020, never issued
939 Ellis Ststreet space
Details
Permit
M1209527

street space

Open the permit page

Jan 9, 2020Completed
final sign-off Aug 2020
939 Ellis StConvergint Technologies Llcadd 3 control modules, 2 emr smoke relays, 1 general alarm relay for securty.
Details
Permit
202001091508
Permit issued
Jan 9, 2020
Final sign-off
Aug 27, 2020

add 3 control modules, 2 emr smoke relays, 1 general alarm relay for securty.

Open the permit page

$1,584
Jun 28, 2019Never finaled
issued Jun 2019, no final
939 Ellis StConvergint Technologies Llcfira alarm ti buildout on 7th fl: 2 control relays, 2 smoke detectors, 7 duct detectors, 20 horn/strobes, 39 strobes. ref pa #201903195583
Details
Permit
201906284647
Permit issued
Jun 28, 2019

fira alarm ti buildout on 7th fl: 2 control relays, 2 smoke detectors, 7 duct detectors, 20 horn/strobes, 39 strobes. ref pa #201903195583

Open the permit page

$22,000
Jun 28, 2019Never finaled
issued Jun 2019, no final
939 Ellis StConvergint Technologies Llcfira alarm ti buildout on 6th fl: 2 control relays, 2 smoke detectors, 7 duct detectors, 20 horn/strobes, 35 strobes. ref pa #201903114897
Details
Permit
201906284645
Permit issued
Jun 28, 2019

fira alarm ti buildout on 6th fl: 2 control relays, 2 smoke detectors, 7 duct detectors, 20 horn/strobes, 35 strobes. ref pa #201903114897

Open the permit page

$22,000
Jun 28, 2019Never finaled
issued Jun 2019, no final
939 Ellis StConvergint Technologies Llcfira alarm ti buildout on 5th fl: 3 control relays, 5 smoke detectors, 3 duct detectors, 24 horn/strobes, 31 strobes. ref pa #201903195584
Details
Permit
201906284644
Permit issued
Jun 28, 2019

fira alarm ti buildout on 5th fl: 3 control relays, 5 smoke detectors, 3 duct detectors, 24 horn/strobes, 31 strobes. ref pa #201903195584

Open the permit page

$22,000
Jun 25, 2019Never finaled
filed Jun 2019, never issued
939 Ellis Ststreet space
Details
Permit
M1100627

street space

Open the permit page

Jun 25, 2019Never finaled
issued Jul 2019, no final
939 Ellis Ststreet space
Details
Permit
M1100607
Permit issued
Jul 2, 2019

street space

Open the permit page

Jun 7, 2019Never finaled
issued Jun 2019, no final
939 Ellis StEco Fire Sprinklers Incfloors 5/6/7: add 307 pendent sprinklers in area of ti. ref t.i. 201903195584/201903195583/201903114897. maher n/a.
Details
Permit
201906072822
Permit issued
Jun 7, 2019

floors 5/6/7: add 307 pendent sprinklers in area of ti. ref t.i. 201903195584/201903195583/201903114897. maher n/a.

Open the permit page

$45,000
May 20, 2019Never finaled
filed May 2019, never issued
939 Ellis Ststreet space
Details
Permit
M1082427

street space

Open the permit page

Apr 26, 2019Completed
final sign-off Feb 2020
939 Ellis StGidel & Kocal Construction Co Incall levels; barrier removal.
Details
Permit
201904269125
Permit issued
May 14, 2019
Final sign-off
Feb 6, 2020

all levels; barrier removal.

Open the permit page

$105,000
Apr 26, 2019Completed
final sign-off Nov 2019
939 Ellis StAqualine Piping Inc.interior waste line upgrades, 3 floor penetrations at entry level to the roof. total of 7 levels.
Details
Permit
201904269121
Permit issued
May 10, 2019
Final sign-off
Nov 20, 2019

interior waste line upgrades, 3 floor penetrations at entry level to the roof. total of 7 levels.

Open the permit page

$85,000
Apr 15, 2019Completed
final sign-off Jul 2021
939 Ellis StWebcor Construction Lp, Granite Excavation & Demolition Incinstall temporary shoring & underpinning along property lines to allow excavation for new development at 830 eddy. tie backs from northern row of soldier beams will enchroach onto 939 ellis st.**maher n/a**
Details
Permit
201904157973
Permit issued
Sep 6, 2019
Final sign-off
Jul 27, 2021

install temporary shoring & underpinning along property lines to allow excavation for new development at 830 eddy. tie backs from northern row of soldier beams will enchroach onto 939 ellis st.**maher n/a**

Open the permit page

$100,000
Apr 4, 2019Completed
final sign-off Jan 2020
939 Ellis StXl Construction, Corporation7th fl - mep for tenant improvement ref pa 2019-0319-5583
Details
Permit
201904047074
Permit issued
May 23, 2019
Final sign-off
Jan 31, 2020

7th fl - mep for tenant improvement ref pa 2019-0319-5583

Open the permit page

$500,000
Apr 4, 2019Completed
final sign-off Jan 2020
939 Ellis StXl Construction, Corporation5th fl - mep for tenant improvement ref pa 2019-0319-5584
Details
Permit
201904047075
Permit issued
May 23, 2019
Final sign-off
Jan 31, 2020

5th fl - mep for tenant improvement ref pa 2019-0319-5584

Open the permit page

$500,000
Mar 19, 2019Completed
final sign-off Jan 2020
939 Ellis StXl Construction, Corporation5th fl project consist of buildout of 1 floor of leased warm shell space. program includes counselor offices, group therapy rooms, reception and staff support spaces mep deferred maher not req
Details
Permit
201903195584
Permit issued
Apr 24, 2019
Final sign-off
Jan 31, 2020

5th fl project consist of buildout of 1 floor of leased warm shell space. program includes counselor offices, group therapy rooms, reception and staff support spaces mep deferred maher not req

Open the permit page

$883,000
Mar 19, 2019Completed
final sign-off Jan 2020
939 Ellis StXl Construction, Corporation7th fl build out of 1 floor leased warm shell space. program includes counselor offices, group therapy rooms, reception and staff support spaces. mep defered non osh facility
Details
Permit
201903195583
Permit issued
May 9, 2019
Final sign-off
Jan 31, 2020

7th fl build out of 1 floor leased warm shell space. program includes counselor offices, group therapy rooms, reception and staff support spaces. mep defered non osh facility

Open the permit page

$883,000
Mar 13, 2019Completed
final sign-off Jan 2020
939 Ellis StXl Construction, Corporation6th floor: mechanical, electrical and plumbing for 201903114897
Details
Permit
201903135077
Permit issued
May 23, 2019
Final sign-off
Jan 31, 2020

6th floor: mechanical, electrical and plumbing for 201903114897

Open the permit page

$567,000
Mar 11, 2019Completed
final sign-off Jan 2020
939 Ellis StXl Construction, Corporation6th flr - this project consist of buildout of one floor of leased warm shell space. program includes councilor offices; therapy room, reception area and staff support spaces. mep
Details
Permit
201903114897
Permit issued
May 9, 2019
Final sign-off
Jan 31, 2020

6th flr - this project consist of buildout of one floor of leased warm shell space. program includes councilor offices; therapy room, reception area and staff support spaces. mep

Open the permit page

$883,000
Dec 3, 2018Completed
final sign-off Nov 2019
939 Ellis StAcco Engineered Systems Inc. Dba Acco Enremove and replace extg boiler like for like and provide new piping connections. n/a for maher
Details
Permit
201812037284
Permit issued
Jan 28, 2019
Final sign-off
Nov 8, 2019

remove and replace extg boiler like for like and provide new piping connections. n/a for maher

Open the permit page

$247,000
Jul 24, 2017Completed
final sign-off Jul 2017
939 Ellis StPlant Construction Co, Lpadministrative correction to existing pa 2015-0518-6561 to correct special inspections
Details
Permit
201707242746
Permit issued
Jul 24, 2017
Final sign-off
Jul 25, 2017

administrative correction to existing pa 2015-0518-6561 to correct special inspections

Open the permit page

Jul 5, 2017Completed
final sign-off Dec 2020
939 Ellis StConvergint Technologies Llcfire alarm as built drawing for relocated emergency generator. ref pa 2016-1121-3180. maher na
Details
Permit
201707050999
Permit issued
Jul 6, 2017
Final sign-off
Dec 31, 2020

fire alarm as built drawing for relocated emergency generator. ref pa 2016-1121-3180. maher na

Open the permit page

Jun 13, 2017Completed
final sign-off Jul 2017
939 Ellis StPlant Construction Co, Lprevision to pa 2017-0309-1114 relocation of fuel port to exterior wall per district inspector's request addition of code required shut off
Details
Permit
201706139192
Permit issued
Jun 23, 2017
Final sign-off
Jul 14, 2017

revision to pa 2017-0309-1114 relocation of fuel port to exterior wall per district inspector's request addition of code required shut off

Open the permit page

Jun 5, 2017Completed
final sign-off Jul 2017
939 Ellis StE. J. Weber Elect.Co Incg/f- emergency responder radio coverage system. n/a ordinance #155-13
Details
Permit
201706058424
Permit issued
Jun 7, 2017
Final sign-off
Jul 10, 2017

g/f- emergency responder radio coverage system. n/a ordinance #155-13

Open the permit page

$35,000
May 31, 2017Completed
final sign-off Jul 2017
939 Ellis StAllied Fire Protectionmodify sprinker system to accomodate relocation of an (e) non conforming generator to a new bldg. code compliant room enclosure, ref pa 201703091114, design density to 0.4
Details
Permit
201705317995
Permit issued
May 31, 2017
Final sign-off
Jul 19, 2017

modify sprinker system to accomodate relocation of an (e) non conforming generator to a new bldg. code compliant room enclosure, ref pa 201703091114, design density to 0.4

Open the permit page

$3,500
Mar 9, 2017Completed
final sign-off Jul 2017
939 Ellis StPlant Construction Co, Lprelocation of an (e) non conforming generator to a new building code complaint room/enclosure with a 2 hr fire separation from (e) structure. maher na
Details
Permit
201703091114
Permit issued
Apr 10, 2017
Final sign-off
Jul 14, 2017

relocation of an (e) non conforming generator to a new building code complaint room/enclosure with a 2 hr fire separation from (e) structure. maher na

Open the permit page

$35,000
Jan 23, 2017Completed
final sign-off Jul 2017
939 Ellis StPriority Architectural Graphics Dba Prio19 evaucation maps to be reviewed by sffd only (all floors) floors b, 1, 2, 3, 4, 5, 6, 7, roof. n/a maher ordinance
Details
Permit
201701237632
Permit issued
Jan 23, 2017
Final sign-off
Jul 19, 2017

19 evaucation maps to be reviewed by sffd only (all floors) floors b, 1, 2, 3, 4, 5, 6, 7, roof. n/a maher ordinance

Open the permit page

$4,700
Dec 21, 2016Completed
final sign-off Jan 2017
939 Ellis StPlant Construction Co, Lpbasement: scope is to add elevator equipment room in basement elevator #3 only. revision to 201511193144 maher na
Details
Permit
201612215572
Permit issued
Jan 4, 2017
Final sign-off
Jan 23, 2017

basement: scope is to add elevator equipment room in basement elevator #3 only. revision to 201511193144 maher na

Open the permit page

$35,000
Nov 21, 2016Completed
final sign-off Jul 2017
939 Ellis StConvergint Technologies Llcfire alarm ti for appl #2015-1119-3144 r1, #2016-0613-9802. including 1 pullstation, 14 input modules, 2 booster power supplies, 8 sync modules, 14 smoke detectors, 93 hornstrobes, 16 relays and 13 duct detectors.
Details
Permit
201611213180
Permit issued
Dec 27, 2016
Final sign-off
Jul 19, 2017

fire alarm ti for appl #2015-1119-3144 r1, #2016-0613-9802. including 1 pullstation, 14 input modules, 2 booster power supplies, 8 sync modules, 14 smoke detectors, 93 hornstrobes, 16 relays and 13 duct detectors.

Open the permit page

$35,000
Oct 4, 2016Completed
final sign-off Jul 2017
939 Ellis StE. J. Weber Elect.Co Incmaintain circuitry to(e)garage,stor rm&closets.safe off&demo bldg core&tenant litg/recp.minor abandon data sys-clean(e) dnbros&feeders-torque terminator.install led litg&pwr in elev lobbies&rr, t-24 ctrls,pwr to new hvac&plumbing eqp-prov pwr to 1 renovated elevr. bldg permit 2015-11-19-3144.
Details
Permit
201610049496
Permit issued
Jan 5, 2017
Final sign-off
Jul 14, 2017

maintain circuitry to(e)garage,stor rm&closets.safe off&demo bldg core&tenant litg/recp.minor abandon data sys-clean(e) dnbros&feeders-torque terminator.install led litg&pwr in elev lobbies&rr, t-24 ctrls,pwr to new hvac&plumbing eqp-prov pwr to 1 renovated elevr. bldg permit 2015-11-19-3144.

Open the permit page

$559,000
Jun 14, 2016Never finaled
issued Jun 2016, no final
939 Ellis Ststreet space
Details
Permit
M697887
Permit issued
Jun 14, 2016

street space

Open the permit page

Jun 13, 2016Completed
final sign-off Jul 2017
939 Ellis StBay City Mechanical Incdemolition of extg hvac equipment. refurbish extg air handling unit and boiler. provide co monitoring of garage. install 6 package uints and new vrv system with 12 fan coils, 5 condensing units with controls.provide 6 new exhaust fans. n/a for maher.
Details
Permit
201606139802
Permit issued
Jul 5, 2016
Final sign-off
Jul 14, 2017

demolition of extg hvac equipment. refurbish extg air handling unit and boiler. provide co monitoring of garage. install 6 package uints and new vrv system with 12 fan coils, 5 condensing units with controls.provide 6 new exhaust fans. n/a for maher.

Open the permit page

$850,000
Jun 9, 2016Completed
final sign-off Jan 2017
939 Ellis StPlant Construction Co, Lpadministrative permit to correct official story-count from 7 to 8. previous parking stories were labeled basement. no construction.n/a for maher.
Details
Permit
201606099586
Permit issued
Nov 14, 2016
Final sign-off
Jan 31, 2017

administrative permit to correct official story-count from 7 to 8. previous parking stories were labeled basement. no construction.n/a for maher.

Open the permit page

May 25, 2016Completed
final sign-off Jan 2017
939 Ellis StAllied Fire Protectionfully sprinkler existing building to nfpa 13 per ab-005 exit constraints. seismic upgrade existing partial wet pipe systems. after completion of installation & final insp well remove class 2 standpipe fire hose rack assembily. hose value optional to remain. ** maher: n/a **
Details
Permit
201605258399
Permit issued
Sep 12, 2016
Final sign-off
Jan 13, 2017

fully sprinkler existing building to nfpa 13 per ab-005 exit constraints. seismic upgrade existing partial wet pipe systems. after completion of installation & final insp well remove class 2 standpipe fire hose rack assembily. hose value optional to remain. ** maher: n/a **

Open the permit page

$374,310
Nov 19, 2015Completed
final sign-off Jul 2017
939 Ellis StPlant Construction Co, Lpinterior core for full building including (n) ada bathrooms, (n) elevators, updated rooftop. mep, sprinklers and fire alarm separate permit. office ti separate permit. ** maher: n/a **
Details
Permit
201511193144
Permit issued
May 6, 2016
Final sign-off
Jul 14, 2017

interior core for full building including (n) ada bathrooms, (n) elevators, updated rooftop. mep, sprinklers and fire alarm separate permit. office ti separate permit. ** maher: n/a **

Open the permit page

$3,000,000
May 18, 2015Completed
final sign-off Jan 2017
939 Ellis StBalfour Beatty Construction Llc, Plant Construction Co, Lpfacde renovate w/ new cladding on building, and the rooftop will be updated to provide private roof-top space for tenants. maher ordinance ext is not required.
Details
Permit
201505186561
Permit issued
May 6, 2016
Final sign-off
Jan 23, 2017

facde renovate w/ new cladding on building, and the rooftop will be updated to provide private roof-top space for tenants. maher ordinance ext is not required.

Open the permit page

$5,670,128
Aug 30, 2011Completed
final sign-off Feb 2012
939 Ellis StAcco Engineered Systems Inc. Dba Acco En3rd floor - reconfigure existing zone to serve office, add new (1) vav & serve single office, not going through any walls, no new ductwork.
Details
Permit
201108303532
Permit issued
Aug 30, 2011
Final sign-off
Feb 13, 2012

3rd floor - reconfigure existing zone to serve office, add new (1) vav & serve single office, not going through any walls, no new ductwork.

Open the permit page

$9,500
May 17, 2011Completed
final sign-off Jul 2011
939 Ellis StBcci Construction Companyto obtain final inspection for work approved under pa 200906231114; all work is complete
Details
Permit
201105176190
Permit issued
May 17, 2011
Final sign-off
Jul 6, 2011

to obtain final inspection for work approved under pa 200906231114; all work is complete

Open the permit page

Feb 22, 2011Completed
final sign-off Jul 2011
939 Ellis StAccel Air Systems Inc.replace small unit ( split system unit) ac and outdoor unit. install dehumidification unit
Details
Permit
201102220708
Permit issued
Mar 10, 2011
Final sign-off
Jul 6, 2011

replace small unit ( split system unit) ac and outdoor unit. install dehumidification unit

Open the permit page

$50,000
Jul 22, 2010Never finaled
issued Jul 2010, no final
939 Ellis StBcci Construction Companyrevision to pa# 2009-0623-1114-strengthening of (e) concrete joists, fire alarm, sprinkler, mechanical under seperate permits
Details
Permit
201007227260
Permit issued
Jul 23, 2010

revision to pa# 2009-0623-1114-strengthening of (e) concrete joists, fire alarm, sprinkler, mechanical under seperate permits

Open the permit page

$12,000
May 18, 2010Completed
final sign-off Jul 2011
939 Ellis StDiversified Fire Productsfire alarm ti for 6th fl. add 1 monitor module, 1 smoke detector, 2 control relays, 1 duct detector
Details
Permit
201005182649
Permit issued
May 18, 2010
Final sign-off
Jul 6, 2011

fire alarm ti for 6th fl. add 1 monitor module, 1 smoke detector, 2 control relays, 1 duct detector

Open the permit page

$12,980
Mar 26, 2010Expired or cancelled
expired May 2013
939 Ellis StBcci Construction Company6th floor-mechanical, electrical work associated with approved pa# 2010-0316-8311 including new ac untis, 2 new fsd & lighting
Details
Permit
201003269052
Permit issued
Mar 26, 2010

6th floor-mechanical, electrical work associated with approved pa# 2010-0316-8311 including new ac untis, 2 new fsd & lighting

Open the permit page

$58,500
Mar 16, 2010Completed
final sign-off Jul 2011
939 Ellis StBcci Construction Company6th floor-minor tenant improvement & server rm. mech. & electrical under separate permit.
Details
Permit
201003168311
Permit issued
Mar 26, 2010
Final sign-off
Jul 6, 2011

6th floor-minor tenant improvement & server rm. mech. & electrical under separate permit.

Open the permit page

$45,000
Nov 17, 2009Completed
final sign-off Jan 2010
939 Ellis StDiversified Fire Productsfire alarm t.i. for 5th. flr.; relocation (e) strobes & horn/strobes.
Details
Permit
200911171358
Permit issued
Nov 17, 2009
Final sign-off
Jan 5, 2010

fire alarm t.i. for 5th. flr.; relocation (e) strobes & horn/strobes.

Open the permit page

$4,700
Nov 5, 2009Completed
final sign-off Jan 2010
939 Ellis StCommercial Interior Builders Inc5th floor -demolition of non-load bearing partitions, install new light fixtures & switches, new gyp bd., ceiling, new drinking fountain & new finishes. minor mechanical modification, elec work under separate permit.
Details
Permit
200911050613
Permit issued
Nov 9, 2009
Final sign-off
Jan 5, 2010

5th floor -demolition of non-load bearing partitions, install new light fixtures & switches, new gyp bd., ceiling, new drinking fountain & new finishes. minor mechanical modification, elec work under separate permit.

Open the permit page

$24,300
Sep 10, 2009Completed
final sign-off Jun 2010
939 Ellis StCommercial Interior Builders Inctitle 24 calculations for lighting. reference application 200908195190
Details
Permit
200909106474
Permit issued
Sep 10, 2009
Final sign-off
Jun 7, 2010

title 24 calculations for lighting. reference application 200908195190

Open the permit page

$3,500
Sep 10, 2009Completed
final sign-off Nov 2009
939 Ellis StDiversified Fire Products7th floor-fire alarm t.i for "conference room"-add 1 horn/strobe
Details
Permit
200909106477
Permit issued
Sep 10, 2009
Final sign-off
Nov 23, 2009

7th floor-fire alarm t.i for "conference room"-add 1 horn/strobe

Open the permit page

$3,780
Aug 19, 2009Completed
final sign-off Jun 2010
939 Ellis StCommercial Interior Builders Incremoval and construction of non-load bearing partitions. new acoustical ceilings and new light fixtures. new office doors and finishes. new striping for accessible parking in garage. mechanical and electrical work to be done under separate permit.
Details
Permit
200908195190
Permit issued
Aug 24, 2009
Final sign-off
Jun 7, 2010

removal and construction of non-load bearing partitions. new acoustical ceilings and new light fixtures. new office doors and finishes. new striping for accessible parking in garage. mechanical and electrical work to be done under separate permit.

Open the permit page

$25,000
Jul 23, 2009Expired or cancelled
cancelled Jan 2026
939 Ellis Stdemolition and construction of non-load bearing partitions, relocate light fixtures and repair gyp. bd. ceiling at affected area; new office doors and new finishes.
Details
Permit
200907233331

demolition and construction of non-load bearing partitions, relocate light fixtures and repair gyp. bd. ceiling at affected area; new office doors and new finishes.

Open the permit page

$25,000
Jun 23, 2009Expired or cancelled
expired Jan 2011
939 Ellis St6th floor-modification to (e) 6th floor. work includes demolition & construction of non-bearing partitions, new ceiling grid & tiles to align with (e). relocate light fixtures, new office doors, new millwork & new finishes. m.e.p under seperate permit
Details
Permit
200906231114
Permit issued
Jun 30, 2009

6th floor-modification to (e) 6th floor. work includes demolition & construction of non-bearing partitions, new ceiling grid & tiles to align with (e). relocate light fixtures, new office doors, new millwork & new finishes. m.e.p under seperate permit

Open the permit page

$33,000
Jun 17, 2008Expired or cancelled
expired Jan 2012
939 Ellis StAccel Air Systems Inc.add 2 - 2 ton split system air conditiones, for computer server room on 6th floor.
Details
Permit
200806174659
Permit issued
Jul 10, 2008

add 2 - 2 ton split system air conditiones, for computer server room on 6th floor.

Open the permit page

$25,070
Apr 14, 2004Expired or cancelled
withdrawn Jun 2004
939 Ellis StBenjamin Gilmore Bollesupgrade life safety system; newfire alarm system
Details
Permit
200404141302

upgrade life safety system; newfire alarm system

Open the permit page

$250,000
Oct 31, 2003Completed
final sign-off Jun 2004
939 Ellis StThe Lawson Roofing Co Inc.reroofing
Details
Permit
200310319108
Permit issued
Oct 31, 2003
Final sign-off
Jun 11, 2004

reroofing

Open the permit page

$353,387

Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

Contractors
Convergint Technologies Llc (7), Plant Construction Co, Lp (7), Xl Construction, Corporation (6), Bcci Construction Company (4), Commercial Interior Builders Inc (3), Diversified Fire Products (3), Accel Air Systems Inc. (2), Acco Engineered Systems Inc. Dba Acco En (2), Allied Fire Protection (2), E. J. Weber Elect.Co Inc (2), Aqualine Piping Inc., Balfour Beatty Construction Llc, Bay City Mechanical Inc, Benjamin Gilmore Bolles, Eco Fire Sprinklers Inc, Gidel & Kocal Construction Co Inc, Granite Excavation & Demolition Inc, Kaiser Foundation Health Plan Inc, Priority Architectural Graphics Dba Prio, The Lawson Roofing Co Inc., Webcor Construction Lp
Architects
Sujendra Mishra (5), Daniel Roach (3), Scott B. Peterson (2), Michael Moores
Engineers
Jason Lau (3), Craig Ristow (2), Eunice Yoon (2), Erwin O'toole, Eunice Yoon
Designers
Keith Lattin
Pmt consultant/expediters
Southwest Sign Co.

Find contractors for work like this

Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.