Block 0165, lot 022
717 Battery St
- City’s use
- Commercial Office
- Built
- 1907
- Stories
- 3
- Units
- 4
- Rooms
- 8 bathrooms
- Building
- 32,667 sq ft
- Lot
- 16,718 sq ft
- Zoning
- C2
- Construction type
- C
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
77 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Mar 11, 2025 | Completed final sign-off Aug 2025 | 717 Battery St | Terra Nova Industries | remodel (e) dining room bar at the ground floor. no mechanical/hvac workDetails
remodel (e) dining room bar at the ground floor. no mechanical/hvac work | $200,000 |
| Aug 25, 2023 | Never finaled issued Aug 2023, no final | 717 Battery St | Battalion One Fire Protection | replace existing communication deviceDetails
replace existing communication device | $9,600 |
| Dec 27, 2022 | Expired or cancelled withdrawn Mar 2025 | 717 Battery St | int courtyard alterations. project proposes to construct a retractable canopy that will partially cover the (e) ground floor courtyard. no change to any of the (e) uses. mep deferredDetails
int courtyard alterations. project proposes to construct a retractable canopy that will partially cover the (e) ground floor courtyard. no change to any of the (e) uses. mep deferred | $1,670,000 | |
| Dec 14, 2021 | Never finaled issued Mar 2022, no final | 717 Battery St | carbon dioxide operation permit only: installation of safety features and/or confirmation of the insallation of safety features for locations where compressed gas containers are used and stored within the buiding reqd by sffc2019.Details
carbon dioxide operation permit only: installation of safety features and/or confirmation of the insallation of safety features for locations where compressed gas containers are used and stored within the buiding reqd by sffc2019. | ||
| Jun 15, 2021 | Completed final sign-off Nov 2021 | 717 Battery St | Aaa Restaurant Fire Control/Dba Aaa Fire | cut pipe and reroute for under duct work re-install (2) sprinkler heads at same locationDetails
cut pipe and reroute for under duct work re-install (2) sprinkler heads at same location | $2,000 |
| May 24, 2021 | Completed final sign-off Oct 2021 | 717 Battery St | Terra Nova Industries | ti: this project consist of a newbar within the existing event/banquet room on the 2nd fl, near the se corner of the building. includes new finishes, appliances, plumbing and lighting associated with the area of the new bar. no change to structure, floor levels, occupancies, occupied load exitDetails
ti: this project consist of a newbar within the existing event/banquet room on the 2nd fl, near the se corner of the building. includes new finishes, appliances, plumbing and lighting associated with the area of the new bar. no change to structure, floor levels, occupancies, occupied load exit | $150,000 |
| Apr 21, 2021 | Never finaled issued May 2021, no final | 717 Battery St | Terra Nova Industries | 1st flr: new glass and steel partition at (e) bar in (e) restaurant dining room, n.w corner of building. new double acting door, new built in seating and new floor finishes within enclosed area. no change to bar, bar equipment, flor levels, occupancies, occupant loads or exist paths.Details
1st flr: new glass and steel partition at (e) bar in (e) restaurant dining room, n.w corner of building. new double acting door, new built in seating and new floor finishes within enclosed area. no change to bar, bar equipment, flor levels, occupancies, occupant loads or exist paths. | $120,000 |
| Jun 12, 2019 | Completed final sign-off Aug 2020 | 717 Battery St | Terra Nova Industries | t.i. new bar service and built in booth at extg library room. n/a for maherDetails
t.i. new bar service and built in booth at extg library room. n/a for maher | $150,000 |
| Aug 8, 2018 | Completed final sign-off Nov 2018 | 717 Battery St | Pyro-Comm Systems, Inc. | fire alarm ti - adding 1 audio.visual device ref 201803062958Details
fire alarm ti - adding 1 audio.visual device ref 201803062958 | $600 |
| Jul 12, 2018 | Never finaled issued Jul 2018, no final | 717 Battery St | Anderson, Rowe & Buckley, Inc. | existing fire sprinkler system ti 3 added sprinklers ref pa 2018-0306-2958Details
existing fire sprinkler system ti 3 added sprinklers ref pa 2018-0306-2958 | $1,500 |
| Mar 6, 2018 | Completed final sign-off Nov 2018 | 717 Battery St | Gci, Inc | construct and install glass wall and door. ceiling mounted exercise bar. all work in (e) fitness center. deferred mep maher naDetails
construct and install glass wall and door. ceiling mounted exercise bar. all work in (e) fitness center. deferred mep maher na | $65,000 |
| Dec 3, 2015 | Completed final sign-off Jan 2016 | 717 Battery St | Terra Nova Industries | revision to 201406259491 related to coffee bar on 1st fl. this shows correction of dimensions (as built condition) in front of coffee barDetails
revision to 201406259491 related to coffee bar on 1st fl. this shows correction of dimensions (as built condition) in front of coffee bar | |
| May 28, 2015 | Completed final sign-off Jul 2015 | 717 Battery St | Pyro-Comm Systems, Inc. | fire alarm- replace 2 existing elevator lobby smoke detectors with 2 new multi criteria, smoke detectors on an existing fire alarm system in an existing building. basement, 1st fl for elevator 2 lobbyDetails
fire alarm- replace 2 existing elevator lobby smoke detectors with 2 new multi criteria, smoke detectors on an existing fire alarm system in an existing building. basement, 1st fl for elevator 2 lobby | $2,000 |
| Nov 7, 2014 | Completed final sign-off Nov 2014 | 717 Battery St | Cisco Fire Sprinklers, Inc. | relocate 2 sprinklers. ref. t.i. appl. 201406259491. n/a ordinance #155-13Details
relocate 2 sprinklers. ref. t.i. appl. 201406259491. n/a ordinance #155-13 | $2,000 |
| Oct 29, 2014 | Never finaled issued Oct 2014, no final | 717 Battery St | street space w/mtaDetails
street space w/mta | ||
| Jun 25, 2014 | Completed final sign-off Nov 2014 | 717 Battery St | Terra Nova Industries | add new architecture counters, casework, flooring. n/a maher ordinanceDetails
add new architecture counters, casework, flooring. n/a maher ordinance | $80,000 |
| May 8, 2014 | Never finaled issued May 2014, no final | 340 Pacific Av | street space & mta permitDetails
street space & mta permit | ||
| Oct 31, 2013 | Completed final sign-off May 2014 | 717 Battery St | Bcci Construction Company | revision 201310038424. fan for elevator #1 pressurization is to be increased in sizeDetails
revision 201310038424. fan for elevator #1 pressurization is to be increased in size | $15,000 |
| Oct 3, 2013 | Completed final sign-off May 2014 | 717 Battery St | Bcci Construction Company | deactivate 2 dampers not needed for fire protection. revision to pa# 201303011257.increase the size of elevator shaft fan.Details
deactivate 2 dampers not needed for fire protection. revision to pa# 201303011257.increase the size of elevator shaft fan. | $25,000 |
| Sep 11, 2013 | Never finaled issued Sep 2013, no final | 340 Pacific Av | add address to block 0165, lot 022 (parking lot) as; 340 pacific ave.Details
add address to block 0165, lot 022 (parking lot) as; 340 pacific ave. | ||
| Sep 5, 2013 | Completed final sign-off May 2014 | 717 Battery St | Bcci Construction Company | revision to app#201012217091s for sffd assembly occupancy permit.Details
revision to app#201012217091s for sffd assembly occupancy permit. | |
| Aug 23, 2013 | Completed final sign-off May 2014 | 717 Battery St | Bcci Construction Company | emergency generator fuel tank, filling piping & related work associated with approved pa# 201012217091sDetails
emergency generator fuel tank, filling piping & related work associated with approved pa# 201012217091s | |
| Jul 30, 2013 | Never finaled issued Jul 2013, no final | 717 Battery St | street spaceDetails
street space | ||
| Jul 30, 2013 | Never finaled issued Jul 2013, no final | 717 Battery St | street space & parking meterDetails
street space & parking meter | ||
| Jul 30, 2013 | Never finaled issued Jul 2013, no final | 717 Battery St | street space & parking meterDetails
street space & parking meter | ||
| May 6, 2013 | Never finaled issued May 2013, no final | 717 Battery St | street space and mta parkingDetails
street space and mta parking | ||
| Mar 12, 2013 | Completed final sign-off Jan 2016 | 717 Battery St | Bcci Construction Company | revision to approved pa# 201012217091s addendum 7 to eliminate sprinkler at the glass bridge.Details
revision to approved pa# 201012217091s addendum 7 to eliminate sprinkler at the glass bridge. | |
| Mar 1, 2013 | Completed final sign-off May 2014 | 717 Battery St | Bcci Construction Company | hvac modification to provide pressurization fans for 2 "full floor" elevator pressurization with emergency back up power. revision to app#201012217094Details
hvac modification to provide pressurization fans for 2 "full floor" elevator pressurization with emergency back up power. revision to app#201012217094 | $30,000 |
| Feb 25, 2013 | Never finaled issued Feb 2013, no final | 717 Battery St | street space & mta parking meterDetails
street space & mta parking meter | ||
| Feb 14, 2013 | Completed final sign-off Sep 2013 | 717 Battery St | Bcci Construction Company | revision to site permit 201012217091s addenda 2 to provide water proofing & gutter as requested by the field inspectorDetails
revision to site permit 201012217091s addenda 2 to provide water proofing & gutter as requested by the field inspector | $4,800 |
| Feb 7, 2013 | Completed final sign-off Sep 2013 | 717 Battery St | Bcci Construction Company | revision to approved site pa#201012217091s. addenda #2 & #5 to reclassify the basement level from "a" occupancy to "b" occupancy. sprinkler still comply with "a" occupancy in accordance with code sec. 508.3.1Details
revision to approved site pa#201012217091s. addenda #2 & #5 to reclassify the basement level from "a" occupancy to "b" occupancy. sprinkler still comply with "a" occupancy in accordance with code sec. 508.3.1 | |
| Jan 17, 2013 | Completed final sign-off May 2014 | 717 Battery St | Pyro-Comm Systems, Inc. | new fire alarm submittal per nfpa 72 per 2007 code per pre-application letter. sprinkler monitoring, elevator recally ansul system & hvac controls. reference mechanical drawing pa# 2010/12/21/7091. all work under 2007 codes(swi 8/26/13).Details
new fire alarm submittal per nfpa 72 per 2007 code per pre-application letter. sprinkler monitoring, elevator recally ansul system & hvac controls. reference mechanical drawing pa# 2010/12/21/7091. all work under 2007 codes(swi 8/26/13). | $35,000 |
| Jan 16, 2013 | Completed final sign-off Jun 2014 | 717 Battery St | Bcci Construction Company | 4th floor:revision to approved app#201012217091. change cieling type and support.Details
4th floor:revision to approved app#201012217091. change cieling type and support. | $5,000 |
| Dec 13, 2012 | Completed final sign-off May 2014 | 717 Battery St | Bcci Construction Company | revision to pa# 2010-1221-7091/s addendum #2-provide electrified hardware & emergency release per sffd bulletin 2.10 at doors 010 & 405. this is in lieu of full smoke detection.Details
revision to pa# 2010-1221-7091/s addendum #2-provide electrified hardware & emergency release per sffd bulletin 2.10 at doors 010 & 405. this is in lieu of full smoke detection. | $2,500 |
| Nov 26, 2012 | Never finaled issued Nov 2012, no final | 717 Battery St | street spaceDetails
street space | ||
| Nov 21, 2012 | Completed final sign-off Oct 2013 | 717 Battery St | Cisco Fire Sprinklers, Inc. | revision to pa #2010.12.21.7091-s7: add 2 sprinklers under exterior glass canopy over koi pond at the basement floor.Details
revision to pa #2010.12.21.7091-s7: add 2 sprinklers under exterior glass canopy over koi pond at the basement floor. | $300 |
| Nov 19, 2012 | Never finaled issued Nov 2012, no final | 717 Battery St | street space permit with metersDetails
street space permit with meters | ||
| Nov 9, 2012 | Never finaled issued Nov 2012, no final | 717 Battery St | street spaceDetails
street space | ||
| Nov 2, 2012 | Completed final sign-off Oct 2013 | 717 Battery St | Bcci Construction Company | remove fire sprinkler heads in elevator control room, remove all associated piping. ref. t.i. #201012107091Details
remove fire sprinkler heads in elevator control room, remove all associated piping. ref. t.i. #201012107091 | $3,500 |
| Oct 23, 2012 | Completed final sign-off May 2014 | 717 Battery St | Aaa Restaurant Fire Control/Dba Aaa Fire | installation of a new ansul hood & duct fire system. ti pa# 2012-1221-7091Details
installation of a new ansul hood & duct fire system. ti pa# 2012-1221-7091 | $10,175 |
| Jul 23, 2012 | Never finaled issued Jul 2012, no final | 717 Battery St | street space permitDetails
street space permit | ||
| Jun 21, 2012 | Completed final sign-off Jan 2015 | 717 Battery St | Bcci Construction Company | revision to approved pa# 201012217091s. add 6 to show revised 2nd floor acoustic isolation ceiling details.Details
revision to approved pa# 201012217091s. add 6 to show revised 2nd floor acoustic isolation ceiling details. | $5,000 |
| Jun 14, 2012 | Never finaled issued Jun 2012, no final | 717 Battery St | street spaceDetails
street space | ||
| Jun 14, 2012 | Never finaled issued Jun 2012, no final | 717 Battery St | street spaceDetails
street space | ||
| Jun 6, 2012 | Never finaled issued Jun 2012, no final | 717 Battery St | street space permit.Details
street space permit. | ||
| Jun 5, 2012 | Completed final sign-off Aug 2014 | 717 Battery St | Bcci Construction Company | revision to app#201012217091 to addendem 5 to revise partition details.Details
revision to app#201012217091 to addendem 5 to revise partition details. | |
| May 16, 2012 | Never finaled issued May 2012, no final | 717 Battery St | street space permitDetails
street space permit | ||
| Apr 20, 2012 | Expired or cancelled withdrawn May 2012 | 717 Battery St | Cisco Fire Sprinklers, Inc. | fire sprinklers for new building, and new 6" fire service. ref. pa #201012217091.Details
fire sprinklers for new building, and new 6" fire service. ref. pa #201012217091. | $300,000 |
| Apr 18, 2012 | Never finaled issued Apr 2012, no final | 717 Battery St | street spaceDetails
street space | ||
| Dec 15, 2011 | Never finaled issued Dec 2011, no final | 717 Battery St | street spaceDetails
street space | ||
| Dec 7, 2011 | Completed final sign-off Oct 2013 | 717 Battery St | Bcci Construction Company | shoring work associated with approved app 201110187021, install 7 tiebacksDetails
shoring work associated with approved app 201110187021, install 7 tiebacks | $8,000 |
| Oct 20, 2011 | Never finaled issued Oct 2011, no final | 717 Battery St | street spaceDetails
street space | ||
| Oct 18, 2011 | Completed final sign-off Oct 2013 | 717 Battery St | Bcci Construction Company | shoring work associated with approved pa# 2010/12/21/7091.Details
shoring work associated with approved pa# 2010/12/21/7091. | $40,000 |
| Sep 9, 2011 | Completed final sign-off Jan 2013 | 717 Battery St | Bcci Construction Company | revision to approved pa# 2010/05/06/1863 (revision designations on plans as delta 4, 5, 6, 7, 8, & 9)Details
revision to approved pa# 2010/05/06/1863 (revision designations on plans as delta 4, 5, 6, 7, 8, & 9) | $25,000 |
| Jul 26, 2011 | Never finaled issued Jul 2011, no final | 717 Battery St | street spaceDetails
street space | ||
| Jun 14, 2011 | Never finaled issued Jun 2011, no final | 717 Battery St | street spaceDetails
street space | ||
| Mar 21, 2011 | Completed final sign-off Jan 2016 | 717 Battery St | Bcci Construction Company | installation of structural shoring for umb construction. this work associated with umb pa# 2010/05/06/1863.Details
installation of structural shoring for umb construction. this work associated with umb pa# 2010/05/06/1863. | $105,000 |
| Feb 28, 2011 | Completed final sign-off Jan 2016 | 717 Battery St | Bcci Construction Company | revision to app#201009130719 r1. shoring permitDetails
revision to app#201009130719 r1. shoring permit | $200,000 |
| Dec 22, 2010 | Never finaled issued Dec 2010, no final | 717 Battery St | street space permitDetails
street space permit | ||
| Dec 21, 2010 | Completed final sign-off May 2014 | 717 Battery St | Bcci Construction Company | excavation of the raza to enlarge basement level. addition of a partial 4th floor & complete renovation of the building into a membership club.Details
excavation of the raza to enlarge basement level. addition of a partial 4th floor & complete renovation of the building into a membership club. | $15,468,000 |
| Sep 23, 2010 | Never finaled issued Sep 2010, no final | 717 Battery St | street spaceDetails
street space | ||
| Sep 13, 2010 | Completed final sign-off Jan 2013 | 717 Battery St | Bcci Construction Company | shoring & tieback work associated with pa #2010-0506-1863-r1.Details
shoring & tieback work associated with pa #2010-0506-1863-r1. | $700,000 |
| Aug 3, 2010 | Never finaled issued Aug 2010, no final | 717 Battery St | street space permit.Details
street space permit. | ||
| Jun 8, 2010 | Never finaled issued Jun 2010, no final | 717 Battery St | street spaceDetails
street space | ||
| Jun 8, 2010 | Never finaled issued Jun 2010, no final | 717 Battery St | mta parkingDetails
mta parking | ||
| May 6, 2010 | Completed final sign-off Jan 2013 | 717 Battery St | Bcci Construction Company | seimic upgrade to an (e) unreinforced masonry building. work includes structural, foundations, diaphrans & all associated umb upgrade work.Details
seimic upgrade to an (e) unreinforced masonry building. work includes structural, foundations, diaphrans & all associated umb upgrade work. | $6,000,000 |
| Mar 16, 2010 | Never finaled issued Mar 2010, no final | 717 Battery St | street space permitDetails
street space permit | ||
| Mar 16, 2010 | Never finaled issued Mar 2010, no final | 717 Battery St | street space permitDetails
street space permit | ||
| Feb 8, 2010 | Never finaled issued Feb 2010, no final | 717 Battery St | street space and mta parkingsDetails
street space and mta parkings | ||
| Sep 10, 2009 | Never finaled issued Sep 2009, no final | 717 Battery St | street space & mtaDetails
street space & mta | ||
| May 14, 2009 | Never finaled issued May 2009, no final | 717 Battery St | mta only.Details
mta only. | ||
| Apr 15, 2009 | Completed final sign-off Jan 2016 | 717 Battery St | Bcci Construction Company | the project consist of interior non-structural demolition and the temporary construction of a fence. no demo to building exterior or any historic content. under ab-017.Details
the project consist of interior non-structural demolition and the temporary construction of a fence. no demo to building exterior or any historic content. under ab-017. | $325,000 |
| Dec 1, 2008 | Expired or cancelled cancelled Jan 2020 | 717 Battery St | alternation to existing build, new 2 story vertical addition on the existing build, 3 story horizontal addition at court yard, ref pa #200810103878Details
alternation to existing build, new 2 story vertical addition on the existing build, 3 story horizontal addition at court yard, ref pa #200810103878 | $5,000,000 | |
| Oct 10, 2008 | Never finaled issued Oct 2008, no final | 717 Battery St | demolish all interior non load bearing partitions, ceilings, and floor finishesDetails
demolish all interior non load bearing partitions, ceilings, and floor finishes | $40,000 | |
| Apr 21, 2005 | Expired or cancelled cancelled Mar 2008 | 717 Battery St | bolt plus umb upgradeDetails
bolt plus umb upgrade | $60,000 | |
| Mar 21, 2005 | Expired or cancelled cancelled Sep 2008 | 717 Battery St | vertical addition of 2 stories change of use-convert existing office into 78 residential units.Details
vertical addition of 2 stories change of use-convert existing office into 78 residential units. | $3,000,000 | |
| Feb 12, 2003 | Completed final sign-off Jan 2013 | 717 Battery St | seismic improvements req by umb.abatement order & accessibility upgrades.Details
seismic improvements req by umb.abatement order & accessibility upgrades. | $1,200,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Bcci Construction Company (22), Terra Nova Industries (6), Cisco Fire Sprinklers, Inc. (3), Pyro-Comm Systems, Inc. (3), Aaa Restaurant Fire Control/Dba Aaa Fire (2), Anderson, Rowe & Buckley, Inc., Battalion One Fire Protection, Gci, Inc
- Architects
- Babac Doane (4), Aston Pereira, David Steinberg, John Ike
- Engineers
- Ben Au, David Murphy, Holmes Culley, Ken Linsteadt, Paul Littler, Ryan Paul January
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.