Maureen Joyce
- Listed as
- engineer
- Firm
- Rjsd
- Based in
- Sf
- On San Francisco permits
- Oct 2019 to Dec 2025
6 permits since 2000 (engineer on 6 permits): 3 completed, 2 in progress, 1 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Dec 19, 2025 | In progress filed Dec 2025, not yet issued | 833 Mission St | elevator modernization of 6 tration elevators &1-6. upgrade new machines, new microprocessor based controllers, digital landing equipment, new guide rolles, new equipment in elevator machine room, and new 2-way emergency vidio and text based communication system.Details
elevator modernization of 6 tration elevators &1-6. upgrade new machines, new microprocessor based controllers, digital landing equipment, new guide rolles, new equipment in elevator machine room, and new 2-way emergency vidio and text based communication system. | $1,985,000 | |
| Oct 22, 2025 | In progress filed Oct 2025, not yet issued | 433 Kearny St | elevator modernization of two traction elevator 1 & 2. refurbish hoistway machines, new door operator, new spring roller guides, new normal and terminal switches. new travel cables etc.Details
elevator modernization of two traction elevator 1 & 2. refurbish hoistway machines, new door operator, new spring roller guides, new normal and terminal switches. new travel cables etc. | $2,300,000 | |
| Aug 12, 2025 | Completed final sign-off Mar 2026 | 398 Eddy St | Urban West Construction Inc | level 1: phase (1) - new accessible opening between (2) spaces, includes new stair, new lift.Details
level 1: phase (1) - new accessible opening between (2) spaces, includes new stair, new lift. | $250,000 |
| Jun 30, 2022 | Completed final sign-off Jan 2025 | 750 Florida St | Dome Construction Corp | alteration to (e) structure including change of use from warehouse to occupancy b-animal care. sow includes: arch, mep & structural modifications not included under phase 1 bpa# 2022-0406-1682. dferred: fire protection, life safety. ** ~encrypt&yes **Details
alteration to (e) structure including change of use from warehouse to occupancy b-animal care. sow includes: arch, mep & structural modifications not included under phase 1 bpa# 2022-0406-1682. dferred: fire protection, life safety. ** ~encrypt&yes ** | $4,800,000 |
| Dec 7, 2020 | Completed final sign-off Apr 2021 | 1890 Sutter St | City Building Inc. | emergency permit to perform dry rot remediation at all corners and west side platform. install footings for new post at north cornersDetails
emergency permit to perform dry rot remediation at all corners and west side platform. install footings for new post at north corners | $20,000 |
| Oct 23, 2019 | Never finaled issued Jan 2020, no final | 582 Market St | City Building Inc. | elevator modernization. 13th fl elevator machine room demolished & reconstructed to align to 13th fl. (n) machine room walls and doors. new elevator equipment & controlsDetails
elevator modernization. 13th fl elevator machine room demolished & reconstructed to align to 13th fl. (n) machine room walls and doors. new elevator equipment & controls | $228,237 |