Ruben Adolfo Santana
- Listed as
- architect, authorized agent-others, contractor
- Firm
- Rubecon General Contracting Inc
- Based in
- San Francisco
- On San Francisco permits
- Apr 2003 to Feb 2026
40 permits since 2000 (contractor on 40 permits, authorized agent-others on 2 permits, architect on 1 permit): 29 completed, 6 never finaled, 5 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. Their ranked record as a contractor is on their contractor page. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Feb 5, 2026 | Completed final sign-off Feb 2026 | 900 Innes Av | Rubecon General Contracting Inc | to obtain final inspection for work approved under pa# 202101273434. all work is complete.Details
to obtain final inspection for work approved under pa# 202101273434. all work is complete. | |
| Feb 25, 2025 | Completed final sign-off Oct 2025 | 1117 Market St | Rubecon General Contracting Inc | storefront renovation. 2 (n) roll up doors 2 glass windows in (e) openings, replace 4 missing marble panels, cermic tile on floor of alcoves and paintDetails
storefront renovation. 2 (n) roll up doors 2 glass windows in (e) openings, replace 4 missing marble panels, cermic tile on floor of alcoves and paint | $278,000 |
| May 26, 2021 | Completed final sign-off Dec 2022 | 325 Teresita Bl | Rubecon General Contracting Inc | kitchen remodel. new cabinets, new countertops, new appliances and new tile floor. no changes to floor plan or walls. replacing old material. p-trap for new sink, new plugs and lightsDetails
kitchen remodel. new cabinets, new countertops, new appliances and new tile floor. no changes to floor plan or walls. replacing old material. p-trap for new sink, new plugs and lights | $50,000 |
| May 13, 2021 | Completed final sign-off May 2022 | 2789 25th St | Rubecon General Contracting Inc | to comply with nov # 202175305. repair damaged stucco at front of the bldg. 20 sq ft. replace damaged door (all work in kind).Details
to comply with nov # 202175305. repair damaged stucco at front of the bldg. 20 sq ft. replace damaged door (all work in kind). | $8,500 |
| Jan 29, 2021 | Completed final sign-off Feb 2023 | 404 Griffith St | Rubecon General Contracting Inc | tool shed - to demolish a one story, type 5, storage shed.Details
tool shed - to demolish a one story, type 5, storage shed. | $10,000 |
| Jan 29, 2021 | Completed final sign-off Feb 2023 | 901 Hudson Av | Rubecon General Contracting Inc | yard shop/storage - to demolish a one story, type 5, storage shed.Details
yard shop/storage - to demolish a one story, type 5, storage shed. | $10,000 |
| Jan 29, 2021 | Completed final sign-off Feb 2023 | 890 Hudson Av | Rubecon General Contracting Inc | to demolish a one story, type 5, storage shed.Details
to demolish a one story, type 5, storage shed. | $10,000 |
| Jan 29, 2021 | Completed final sign-off Feb 2023 | 901 Hudson Av | Rubecon General Contracting Inc | boatyard storage - to demolish a one story, type 5, storage shed.Details
boatyard storage - to demolish a one story, type 5, storage shed. | $20,000 |
| Jan 29, 2021 | Completed final sign-off Feb 2023 | 404 Griffith St | Rubecon General Contracting Inc | boat office - to demolish a one story, type 5, storage shed.Details
boat office - to demolish a one story, type 5, storage shed. | $5,000 |
| Jan 27, 2021 | Completed final sign-off Apr 2024 | 404 Griffith St | Rubecon General Contracting Inc | remove soil and backfill equivalent with clean material, compact.Details
remove soil and backfill equivalent with clean material, compact. | $10,500 |
| Jan 27, 2021 | Never finaled issued Jun 2021, no final | 890 Hudson Av | Rubecon General Contracting Inc | parcel complete submerged (water lot)Details
parcel complete submerged (water lot) | $30,000 |
| Jan 27, 2021 | Expired or cancelled expired Feb 2026 | 900 Innes Av | Rubecon General Contracting Inc | work to occur around structure/cottage. offset work 5-ft from structure/cottage; minimal grading work and fill proposed around offset perimeter.Details
work to occur around structure/cottage. offset work 5-ft from structure/cottage; minimal grading work and fill proposed around offset perimeter. | $7,500 |
| Jan 27, 2021 | Completed final sign-off Apr 2024 | 904 Innes Av | Rubecon General Contracting Inc | remove soil and backfill equivalen with clean material, compact.Details
remove soil and backfill equivalen with clean material, compact. | $21,000 |
| Jan 27, 2021 | Completed final sign-off Apr 2024 | 908 Innes Av | Rubecon General Contracting Inc | remove soil and backfill equivalen with clean material, compact.Details
remove soil and backfill equivalen with clean material, compact. | $22,500 |
| Jan 27, 2021 | Never finaled issued Jun 2021, no final | 901 Hudson Av | Rubecon General Contracting Inc | remove soil and backfill equivalen with clean material, compaction.Details
remove soil and backfill equivalen with clean material, compaction. | $120,000 |
| Jan 27, 2021 | Completed final sign-off Apr 2024 | 808 Innes Av | Rubecon General Contracting Inc | remove soil and backfill equivalen with clean material, compact.Details
remove soil and backfill equivalen with clean material, compact. | $10,000 |
| Jan 27, 2021 | Completed final sign-off Apr 2024 | 900 Hudson Av | Rubecon General Contracting Inc | remove soil and backfill equivalen with clean material to depth ranging from 2 ft - 4 ft- compaction to follow. remove sediment in submerged lots and backfill with equivalent material. compaction only required for areas outside of the submerged zone.Details
remove soil and backfill equivalen with clean material to depth ranging from 2 ft - 4 ft- compaction to follow. remove sediment in submerged lots and backfill with equivalent material. compaction only required for areas outside of the submerged zone. | $105,000 |
| Aug 11, 2020 | Completed final sign-off Dec 2021 | 2789 25th St | Rubecon General Contracting Inc | structure support for hvac units on roof. install hvac units on roof under separate permit.Details
structure support for hvac units on roof. install hvac units on roof under separate permit. | $120,000 |
| Mar 28, 2019 | Completed final sign-off May 2019 | 544 Golden Gate Av | Rubecon General Contracting Inc | installation of 3 doors w/ d-20 fire rated glass at (e) 20 min rated doorsDetails
installation of 3 doors w/ d-20 fire rated glass at (e) 20 min rated doors | $5,000 |
| Dec 26, 2018 | Completed final sign-off Jul 2019 | 375 Laguna Honda Bl | Rubecon General Contracting Inc | revision to bpa#201609087093Details
revision to bpa#201609087093 | $423,000 |
| May 10, 2012 | Never finaled issued May 2012, no final | 1001 Potrero Av | Rubecon General Contracting Inc | providing revised battery spill containment and fuel oil containment from previously approved document. sffd approval only. oshpd juristriction revision 201003037463Details
providing revised battery spill containment and fuel oil containment from previously approved document. sffd approval only. oshpd juristriction revision 201003037463 | |
| Mar 12, 2012 | Completed final sign-off Oct 2013 | 475 Brannan St | Rubecon General Contracting Inc | voluntary seismic mitigation at entry canopy.Details
voluntary seismic mitigation at entry canopy. | $14,000 |
| Sep 30, 2010 | Expired or cancelled cancelled Jul 2012 | 475 Brannan St | Rubecon General Contracting Inc | 4th floor #430 - demolish & remove approx 250 lf of non-structural, non-rated sheetrock partitions. safe off electrical, patch & paint. relocation of sprinklers under separate permit if required.Details
4th floor #430 - demolish & remove approx 250 lf of non-structural, non-rated sheetrock partitions. safe off electrical, patch & paint. relocation of sprinklers under separate permit if required. | $15,000 |
| Sep 30, 2010 | Completed final sign-off Jun 2012 | 475 Brannan St | Rubecon General Contracting Inc | 4th floor #420 -demolish & remove approx 80ft of non-structural, non-rated sheetrock partitions, safe off electrical patch & paint. reclocation of sprinklers if required under separate permit.Details
4th floor #420 -demolish & remove approx 80ft of non-structural, non-rated sheetrock partitions, safe off electrical patch & paint. reclocation of sprinklers if required under separate permit. | $10,000 |
| Mar 3, 2010 | Never finaled issued May 2012, no final | 1001 Potrero Av | Rubecon General Contracting Inc | new emergency power system, 5 generator sets, walls & other 2-hr. construction enclosure 5 radiators,fuel oil system, hvac system, steam boilers, dearator tank, gas piping, 380 gallon fuel-oil day tankDetails
new emergency power system, 5 generator sets, walls & other 2-hr. construction enclosure 5 radiators,fuel oil system, hvac system, steam boilers, dearator tank, gas piping, 380 gallon fuel-oil day tank | $3,885 |
| Apr 1, 2009 | Never finaled issued Apr 2009, no final | 330 Ellis St | Rubecon General Contracting Inc | renew pa# 2005/10/07/5118 to complete work & obtain final inspection.Details
renew pa# 2005/10/07/5118 to complete work & obtain final inspection. | $6,000 |
| Jan 15, 2009 | Completed final sign-off Jun 2009 | 35 Lillian St | Rubecon General Contracting Inc | reduced scop0e of work to previous approved pa# 2007/08/07/0611. work to include only new siding repair & replacement. replacement of (e) windows to match size of (e) opening & accessibility per 20% rule. new interior patition walls for new offices. no square footage added.Details
reduced scop0e of work to previous approved pa# 2007/08/07/0611. work to include only new siding repair & replacement. replacement of (e) windows to match size of (e) opening & accessibility per 20% rule. new interior patition walls for new offices. no square footage added. | $105,000 |
| Dec 6, 2006 | Completed final sign-off Mar 2007 | 475 Brannan St | Rubecon General Contracting Inc | create new 1 hr. rate partition in an existing suite to make 2 suites. work on 3/f. sprinkler, hvac, electrical and life safety on seperate permit.Details
create new 1 hr. rate partition in an existing suite to make 2 suites. work on 3/f. sprinkler, hvac, electrical and life safety on seperate permit. | $35,000 |
| Oct 4, 2006 | Completed final sign-off Nov 2006 | 330 Ellis St | Rubecon General Contracting Inc | revision to remove review comment of submit sprinklers items on seperate appl#200510075118. revision to code information on sheet a0.2: change "fire protection" description and eliminate "engineering" completelyDetails
revision to remove review comment of submit sprinklers items on seperate appl#200510075118. revision to code information on sheet a0.2: change "fire protection" description and eliminate "engineering" completely | |
| Aug 14, 2006 | Completed final sign-off Oct 2006 | 200 Brannan St | Rubecon General Contracting Inc | repalce iitchen exhaust system in unit 506Details
repalce iitchen exhaust system in unit 506 | $35,000 |
| Dec 1, 2005 | Expired or cancelled cancelled Dec 2008 | 1886 Mission St | Rubecon General Contracting Inc | demolish 2 stories of printing/lithographyDetails
demolish 2 stories of printing/lithography | |
| Dec 28, 2004 | Completed final sign-off Jul 2005 | 475 Brannan St | Rubecon General Contracting Inc | wood beam repairs inject epoxy grout in 2 crack beams/install 1 pair 8' bolted stich plates onDetails
wood beam repairs inject epoxy grout in 2 crack beams/install 1 pair 8' bolted stich plates on | $3,000 |
| Aug 10, 2004 | Completed final sign-off Jan 2005 | 2102 Union St | Rubecon General Contracting Inc | add non-load bearing partitions, relocate (e) toilet and comply with ada requirementsDetails
add non-load bearing partitions, relocate (e) toilet and comply with ada requirements | $120,000 |
| Jun 28, 2004 | Never finaled issued Jul 2004, no final | 3254 19th St | Rubecon General Contracting Inc | revert back to last legal use of story count. comply nov 200120655 ced.remove (e)unwarranted 3/f,Details
revert back to last legal use of story count. comply nov 200120655 ced.remove (e)unwarranted 3/f, | $30,000 |
| Jun 22, 2004 | Expired or cancelled expired Jul 2006 | 71 Stevenson St | Rubecon General Contracting Inc | oti-1 revision 21st fl el,me,lsDetails
oti-1 revision 21st fl el,me,ls | $20,000 |
| Mar 31, 2004 | Expired or cancelled expired Jul 2006 | 71 Stevenson St | Rubecon General Contracting Inc | oti-1 21/f el me ls spDetails
oti-1 21/f el me ls sp | $491,000 |
| Jul 31, 2003 | Completed final sign-off Feb 2004 | 220 Montgomery St | Rubecon General Contracting Inc | revision to pa#2003/05/02/3656 - deletion of structural bracing detail and special insp. requirementDetails
revision to pa#2003/05/02/3656 - deletion of structural bracing detail and special insp. requirement | |
| Jul 22, 2003 | Completed final sign-off Feb 2004 | 220 Montgomery St | Rubecon General Contracting Inc | add lite fixtures, oti-3, lst fl. elDetails
add lite fixtures, oti-3, lst fl. el | $2,500 |
| Jul 15, 2003 | Completed final sign-off Feb 2004 | 220 Montgomery St | Rubecon General Contracting Inc | oti-2 1st fl. ls,spDetails
oti-2 1st fl. ls,sp | $10,000 |
| Apr 11, 2003 | Completed final sign-off May 2003 | 221 07th Av | Rubecon General Contracting Inc | comply w/ nov #200229914Details
comply w/ nov #200229914 | $15,000 |