- Jul 2014 to Jul 2026
51 permits since 2000 (architect on 46 permits, designer on 3 permits, authorized agent-others on 2 permits): 28 completed, 14 in progress, 5 never finaled, 4 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jul 20, 2026 | In progress issued Jul 2026 | 1896 Pacific Av | Santos Construction | unit 202: revision to bpa: 202606012236: remodel/ reconfigure: (e) kitchen, primary bath and (e) bath.Details
unit 202: revision to bpa: 202606012236: remodel/ reconfigure: (e) kitchen, primary bath and (e) bath. | $10,000 |
| Jun 4, 2026 | In progress issued Sep 2026 | 372 Quintara St | replace and widen (e) window at 2nd fl. bedroom, no other alterations to (e) interior areas. add (n) property line window at second floor bedroomDetails
replace and widen (e) window at 2nd fl. bedroom, no other alterations to (e) interior areas. add (n) property line window at second floor bedroom | $15,000 | |
| May 6, 2026 | In progress filed May 2026, not yet issued | 2401 23rd St | lower unit: remodel (e) bathroom onlyDetails
lower unit: remodel (e) bathroom only | $25,000 | |
| Apr 16, 2026 | In progress issued Sep 2026 | 769 Clayton St | Gil Construction & Assoc Inc. | 1. remodel (e) garden apartment. 2. reconfigure/rebuild (e) ground floor deck. 3. reconfigure (e) ground floor garage and utility area to provide dedicated shared laundry. 4. voluntary replacement of portion of (e) perimeter foundation. 5. no work at (e) primary dwelling (second and third floor).Details
1. remodel (e) garden apartment. 2. reconfigure/rebuild (e) ground floor deck. 3. reconfigure (e) ground floor garage and utility area to provide dedicated shared laundry. 4. voluntary replacement of portion of (e) perimeter foundation. 5. no work at (e) primary dwelling (second and third floor). | $150,000 |
| Jan 20, 2026 | In progress issued Apr 2026 | 2465 Harrison St | Gb Construction Company | replace (e) rear yard deck/landings and exterior stairs with (n) deck and rear yard access stairs including a pre-fabricated steel, spiral staircase, and construction of new, shallow isolated pad footings.Details
replace (e) rear yard deck/landings and exterior stairs with (n) deck and rear yard access stairs including a pre-fabricated steel, spiral staircase, and construction of new, shallow isolated pad footings. | $20,000 |
| Dec 22, 2025 | In progress filed Dec 2025, not yet issued | 78 Eastwood Dr | convert portion of (e) unfinished first fl garage to (n) habitble area consisting of (n) family room, (n) bath, and (n) bedroom. excavate portion of (e) slab to provide required ceiling height.Details
convert portion of (e) unfinished first fl garage to (n) habitble area consisting of (n) family room, (n) bath, and (n) bedroom. excavate portion of (e) slab to provide required ceiling height. | $150,000 | |
| Dec 18, 2025 | In progress issued Sep 2026 | 284 Liberty St | Brendan J Uniacke Construction | add new ensuite full bath and walk in closet. relocate washer and dryer.Details
add new ensuite full bath and walk in closet. relocate washer and dryer. | $40,000 |
| Nov 19, 2025 | In progress issued Dec 2025 | 2467 Harrison St | Gb Construction Company | remodel and reconfigure existing kitchen, dining, and laundry at 2nd floor.Details
remodel and reconfigure existing kitchen, dining, and laundry at 2nd floor. | $75,000 |
| Nov 12, 2025 | Completed final sign-off Jun 2026 | 970 Bay St | Sewer Master | provide a personal residential pneumatic vaccum elevator between the first floor vestibule and 4th floor apt unit 9Details
provide a personal residential pneumatic vaccum elevator between the first floor vestibule and 4th floor apt unit 9 | $20,000 |
| Jun 26, 2025 | In progress issued Aug 2025 | 1948 Sutter St | Silver Lining Design Build Co | revision to pa 202406245064 including minor interior floor plan changes; addition of 1 skylight; any other minor changes including some changes to window sizes, add 4 gas fireplaces, remove 1 bathroom renovation. no change to fixture countDetails
revision to pa 202406245064 including minor interior floor plan changes; addition of 1 skylight; any other minor changes including some changes to window sizes, add 4 gas fireplaces, remove 1 bathroom renovation. no change to fixture count | $1,000 |
| Feb 27, 2025 | Completed final sign-off Mar 2026 | 3545 Washington St | Gil Construction & Assoc Inc. | remodel/reconfigure and expand (e) kitchen; remodel 2 full baths and 1 powder room; replace (e) windows & rear bedroom with (n) patio doorsDetails
remodel/reconfigure and expand (e) kitchen; remodel 2 full baths and 1 powder room; replace (e) windows & rear bedroom with (n) patio doors | $180,000 |
| Feb 25, 2025 | In progress issued Apr 2026 | 78 Eastwood Dr | Brothers Collins Woodworking Inc | remodel/reconfigure (e) kitchen, remodel /reconfigure (e) full bath. add second full bath. reconfigure (e) stairs down to (e) garageDetails
remodel/reconfigure (e) kitchen, remodel /reconfigure (e) full bath. add second full bath. reconfigure (e) stairs down to (e) garage | $90,000 |
| Jan 30, 2025 | Completed final sign-off Mar 2026 | 1958 Vallejo St | Santos Construction | unit 7; remodel kitchen reconfig layout, moving sink, stove, oven, and cabinets. reconfig (2)full baths, remodel (1)powder, change(1) full to powder, bedrooms, and(4) bathrooms, remove/configure (e) non structural partitions, (3) replace (e) windows aluminum clad wood, double hung at front facade.Details
unit 7; remodel kitchen reconfig layout, moving sink, stove, oven, and cabinets. reconfig (2)full baths, remodel (1)powder, change(1) full to powder, bedrooms, and(4) bathrooms, remove/configure (e) non structural partitions, (3) replace (e) windows aluminum clad wood, double hung at front facade. | $350,000 |
| Sep 5, 2024 | In progress issued Nov 2025 | 80 Crown Tr | Ot Bay Builders Inc. | 1) remodel kitchen in kind. 2) remodel (2) existing baths. 3) replace (4) windows in-kindDetails
1) remodel kitchen in kind. 2) remodel (2) existing baths. 3) replace (4) windows in-kind | $60,000 |
| Aug 22, 2024 | Completed final sign-off Feb 2025 | 847 Fillmore St | new 500 sf roofdeck with acess via (e) stair penthouse.Details
new 500 sf roofdeck with acess via (e) stair penthouse. | $50,000 | |
| Apr 25, 2024 | In progress issued May 2024 | 2964 Jackson St | O'shaughnessy Construction | unit 1- remodel/ relocate (e) kitchen and removing wall to expand into living/dining room. addition (n) powder room. convert (3) (e) windows into (n) rear door opening.Details
unit 1- remodel/ relocate (e) kitchen and removing wall to expand into living/dining room. addition (n) powder room. convert (3) (e) windows into (n) rear door opening. | $75,000 |
| Apr 4, 2024 | Completed final sign-off Oct 2025 | 230 Ashbury St | interior remodel of e) kitchen, convert e) powder to full bath. convert e)bedroom to n) ensuite bathroom & laundryDetails
interior remodel of e) kitchen, convert e) powder to full bath. convert e)bedroom to n) ensuite bathroom & laundry | $80,000 | |
| Feb 20, 2024 | Completed final sign-off Mar 2025 | 170 Everson St | Brendan J Uniacke Construction | 1) remodel extg kitchen and 3rd floor bedroom. 2)remodel/reconfigure 3 extg bathrooms. 3)replace extg windows throughout.Details
1) remodel extg kitchen and 3rd floor bedroom. 2)remodel/reconfigure 3 extg bathrooms. 3)replace extg windows throughout. | $150,000 |
| Dec 8, 2023 | Completed final sign-off Apr 2024 | 2231 34th Av | Iz & J Construction Llc | remodel (e) kitchen. remodel (e) full bath.Details
remodel (e) kitchen. remodel (e) full bath. | $55,000 |
| Nov 20, 2023 | Completed final sign-off Jul 2024 | 2111 14th Av | Blue Sky Wallace Construction | remodel e kitchen and dining room, including removal of bearing wall/beam. replace lighting in e living rm new washer dryer in closetDetails
remodel e kitchen and dining room, including removal of bearing wall/beam. replace lighting in e living rm new washer dryer in closet | $50,000 |
| Nov 7, 2023 | Completed final sign-off Nov 2024 | 85 Eastwood Dr | Pallari Construction General Contracting | remodel (e) kitchen, remodel/reconfigure (e) bath to create new ensuite bath & walk-in closet, remodel/reconfigure (e) hall closet to create new full bath.Details
remodel (e) kitchen, remodel/reconfigure (e) bath to create new ensuite bath & walk-in closet, remodel/reconfigure (e) hall closet to create new full bath. | $85,000 |
| Sep 26, 2023 | In progress issued May 2024 | 55 Southwood Dr | Brendan J Uniacke Construction | interior remodel of (e) kitchen. alteration to (e) garage to create mudroom and half bath. convert (e) second floor sunroom to new ensuite bathroom. 1 street visible window replacement.Details
interior remodel of (e) kitchen. alteration to (e) garage to create mudroom and half bath. convert (e) second floor sunroom to new ensuite bathroom. 1 street visible window replacement. | $95,000 |
| Sep 11, 2023 | Never finaled issued Sep 2023, no final | 100 Teresita Bl | Brendan J Uniacke Construction | convert portion of (e) 2 car garage to (n) bedroom/office; new full bath and new laundry; replace (e) stairs to provide open connection between main floor and new; convert (e) window to patio door w/landingDetails
convert portion of (e) 2 car garage to (n) bedroom/office; new full bath and new laundry; replace (e) stairs to provide open connection between main floor and new; convert (e) window to patio door w/landing | $70,000 |
| Jul 7, 2023 | Never finaled issued Aug 2023, no final | 524 Lake St | Brendan J Uniacke Construction | remodel (e) hall bath, replace fixtures in-kind, countertops @ (e) kitchen, convert (e) laundry room to new full bath, replace lighting throughout flat.Details
remodel (e) hall bath, replace fixtures in-kind, countertops @ (e) kitchen, convert (e) laundry room to new full bath, replace lighting throughout flat. | $30,000 |
| May 25, 2023 | Completed final sign-off Jul 2024 | 2700 43rd Av | O'shaughnessy Construction | replace/modify (e) interior stairs, add new stair to access roof via low profile roof, add new roof deck (approx 300 sq.ft.)Details
replace/modify (e) interior stairs, add new stair to access roof via low profile roof, add new roof deck (approx 300 sq.ft.) | $30,000 |
| Apr 12, 2023 | Completed final sign-off Feb 2024 | 644 25th Av | revision to bpa#202212208737, (e) beam @ living room to remain (support w/new posts per original permit), revise kitchen layout, shear wall revisions to coordinate w/(e) conditionsDetails
revision to bpa#202212208737, (e) beam @ living room to remain (support w/new posts per original permit), revise kitchen layout, shear wall revisions to coordinate w/(e) conditions | ||
| Dec 29, 2022 | Completed final sign-off Jun 2026 | 318 Detroit St | Tong Construction Inc | 2/f: remove/reconfigure (e) kitchen and dining and living room. remodel 2 (e) full baths. add a new half bath. remodel 2 (e) bedrooms and provide laundry closet. remove (e) ext. stair access to (e) deck, infill opening to match deck.Details
2/f: remove/reconfigure (e) kitchen and dining and living room. remodel 2 (e) full baths. add a new half bath. remodel 2 (e) bedrooms and provide laundry closet. remove (e) ext. stair access to (e) deck, infill opening to match deck. | $80,000 |
| Dec 20, 2022 | Completed final sign-off Feb 2024 | 644 25th Av | interior remodel of existing 2nd fl flat. remodel reconfigure kitchen and 2 full baths. add 1/2 bath and laundry closet. no work to gr floor. common area or upper flatDetails
interior remodel of existing 2nd fl flat. remodel reconfigure kitchen and 2 full baths. add 1/2 bath and laundry closet. no work to gr floor. common area or upper flat | $50,000 | |
| Oct 27, 2022 | Completed final sign-off Jul 2024 | 2700 43rd Av | O'shaughnessy Construction | replace/replace fire damaged roof, roof framing, and finishes at 2nd floor. interior remodel of extg kitchen and bath. remodel/reconfigure extg bedroom, half bath and garage to create a den, primary suite, and one car garage.Details
replace/replace fire damaged roof, roof framing, and finishes at 2nd floor. interior remodel of extg kitchen and bath. remodel/reconfigure extg bedroom, half bath and garage to create a den, primary suite, and one car garage. | $110,000 |
| Dec 21, 2021 | Never finaled filed Dec 2021, never issued | 463 Ulloa St | remodel & horizontal addition to an existing 2-story single family residence & a vertical addition to provide a 3rd fl plus roof deck.Details
remodel & horizontal addition to an existing 2-story single family residence & a vertical addition to provide a 3rd fl plus roof deck. | $600,000 | |
| Nov 30, 2021 | In progress issued May 2024 | 3329 Cesar Chavez St | soft story improvements at the (e) ground fl garage as required due to the proposed addition of an accessory dwelling unit under separate permit (permit application #201803022769)Details
soft story improvements at the (e) ground fl garage as required due to the proposed addition of an accessory dwelling unit under separate permit (permit application #201803022769) | $45,000 | |
| Nov 29, 2021 | Completed final sign-off Feb 2026 | 1947 31st Av | Winwin Construction Inc | voluntary soft story seismic retrofit per ab094, 2019 cebc appendix 4a. two floor horizontal addition. 2nd fl add 245 sqft, remodel 2 (n) bathroom, living room, kitchen, add 2 bathroom. relocate living room, dining, kitchen. ground fl add 418 sqft rear storage room. ground floor add 451 sqft.Details
voluntary soft story seismic retrofit per ab094, 2019 cebc appendix 4a. two floor horizontal addition. 2nd fl add 245 sqft, remodel 2 (n) bathroom, living room, kitchen, add 2 bathroom. relocate living room, dining, kitchen. ground fl add 418 sqft rear storage room. ground floor add 451 sqft. | $100,000 |
| Apr 16, 2021 | Never finaled issued Apr 2022, no final | 2700 43rd Av | B. Uniacke Construction | 11/4/21: reduced scope: interior remodel of (e) kitchen and hall bath; raise kitchen ceiling by 12"; remove (e) chainlink fence at front yardDetails
11/4/21: reduced scope: interior remodel of (e) kitchen and hall bath; raise kitchen ceiling by 12"; remove (e) chainlink fence at front yard | $50,000 |
| Mar 10, 2020 | Expired or cancelled withdrawn Feb 2022 | 959 Rutland St | convert existing ground floor garage to 2 bed/1 bathroom adu. minor related interior work @ primary unit and additin of rear deck to provide access to required open space.Details
convert existing ground floor garage to 2 bed/1 bathroom adu. minor related interior work @ primary unit and additin of rear deck to provide access to required open space. | $100,000 | |
| Feb 4, 2020 | Completed final sign-off Feb 2020 | 715 Sargent St | rev to pa# 201804267502; omit sliding glass door replace (e) windows, revise interior closet, omit enrty deckDetails
rev to pa# 201804267502; omit sliding glass door replace (e) windows, revise interior closet, omit enrty deck | ||
| Feb 4, 2020 | Completed final sign-off Feb 2020 | 715 Sargent St | rev to pa# 201804267500; construction revision to reflect field changes, revise/reconfigure entry steps,/landing, revise interior closts, remodel/ reconfigure legalized bath, relocate/reconfigure legalized kitchenDetails
rev to pa# 201804267500; construction revision to reflect field changes, revise/reconfigure entry steps,/landing, revise interior closts, remodel/ reconfigure legalized bath, relocate/reconfigure legalized kitchen | $10,000 | |
| Dec 6, 2019 | Completed final sign-off Jul 2020 | 1666 Golden Gate Av | Partee Construction Co | to comply w/nov #201966581 fire damage repair. interior fire rebuild (replace all affected surfaces). minor non-structural wall alterations to reconfigure closets, provide 2 full baths, and remodel kitchen.Details
to comply w/nov #201966581 fire damage repair. interior fire rebuild (replace all affected surfaces). minor non-structural wall alterations to reconfigure closets, provide 2 full baths, and remodel kitchen. | $300,000 |
| Dec 6, 2019 | Completed final sign-off Jun 2020 | 1666 Golden Gate Av | Partee Construction Co | work to comply with nov.201966581 fire damage repair replace 18 windows, wood windows to match (e) (ogee lugs, frame, operation ) within e opening (in kind) match unit below (166 golden gate)Details
work to comply with nov.201966581 fire damage repair replace 18 windows, wood windows to match (e) (ogee lugs, frame, operation ) within e opening (in kind) match unit below (166 golden gate) | $20,000 |
| Dec 6, 2019 | Completed final sign-off Jan 2022 | 1363 28th Av | Simply Building Inc | interior remodel of kitchen and reconfigure interior walls (less than 75% demolition) to provide 2 beds 2.5 baths upstair. convert portion of unfinished garage to additional 1 bed/ bath, family room, and laundry ( rooms down) replace existing windows with wood windows (e) opening/(e)operation @frontDetails
interior remodel of kitchen and reconfigure interior walls (less than 75% demolition) to provide 2 beds 2.5 baths upstair. convert portion of unfinished garage to additional 1 bed/ bath, family room, and laundry ( rooms down) replace existing windows with wood windows (e) opening/(e)operation @front | $400,000 |
| Apr 3, 2019 | Completed final sign-off Oct 2019 | 4426 19th St | Partee Construction Co | demo (e) interior wall btw kitchen and family rm and replace with new post and beamDetails
demo (e) interior wall btw kitchen and family rm and replace with new post and beam | $3,500 |
| Nov 1, 2018 | Expired or cancelled suspend Apr 2019 | 2027 20th Av | rev to pa# 200804048918; revise extant of demo work at (e) ground floor bungalow to match site conditions, no change to proposed layoutDetails
rev to pa# 200804048918; revise extant of demo work at (e) ground floor bungalow to match site conditions, no change to proposed layout | $3,000 | |
| Jul 25, 2018 | Completed final sign-off Dec 2019 | 709 Central Av | All Construction Services | interior remodel and minor reconfiguration of walls to create 3 bed and 1.5 baths. remodel/reconfiguration kitchen. window replacment throughout unitDetails
interior remodel and minor reconfiguration of walls to create 3 bed and 1.5 baths. remodel/reconfiguration kitchen. window replacment throughout unit | $100,000 |
| Jul 25, 2018 | Expired or cancelled expired Oct 2021 | 711 Central Av | All Construction Services | interior remodel and minor reconfiguration of walls to create 3 bed and 1.5 baths. remodel/reconfiguration kitchen. window replacment throughout unitDetails
interior remodel and minor reconfiguration of walls to create 3 bed and 1.5 baths. remodel/reconfiguration kitchen. window replacment throughout unit | $100,000 |
| Jun 8, 2018 | Completed final sign-off Aug 2023 | 2371 17th Av | Ze Sheng Liao | to comply with nov# 201614111. remove existing concrete pavement in front of property. provide 20% landscaping with 50% permeable surface. install new front balcony to match original.Details
to comply with nov# 201614111. remove existing concrete pavement in front of property. provide 20% landscaping with 50% permeable surface. install new front balcony to match original. | $5,000 |
| Apr 26, 2018 | Completed final sign-off Feb 2020 | 715 Sargent St | Ket Construction Inc., Spotlight Construction Groups Inc | legalize (e) unauthorized dwelling unit, including (n) entry & skylight for light & ventilation. update entry stair for code conformance & legalize unpermitted shower & kitchen fixtures. legalization per ordinance 43-14.Details
legalize (e) unauthorized dwelling unit, including (n) entry & skylight for light & ventilation. update entry stair for code conformance & legalize unpermitted shower & kitchen fixtures. legalization per ordinance 43-14. | $15,000 |
| Apr 26, 2018 | Completed final sign-off Feb 2020 | 715 Sargent St | Ket Construction Inc., Spotlight Construction Groups Inc | convert portion of remaining garage space to 3rd bedroom. (ground floor unit legalized under separate permit #2018-0426-7500 s) extend entry landing to create entry porch.Details
convert portion of remaining garage space to 3rd bedroom. (ground floor unit legalized under separate permit #2018-0426-7500 s) extend entry landing to create entry porch. | $15,000 |
| Mar 2, 2018 | Never finaled issued Jul 2019, no final | 3329 Cesar Chavez St | convert portion of (e) 4-car garage into a 2-bedroom/1.5 bath adu. 2-car parking remains. no scope of work @ (e) 4-units to remain per ordinance 162-16.Details
convert portion of (e) 4-car garage into a 2-bedroom/1.5 bath adu. 2-car parking remains. no scope of work @ (e) 4-units to remain per ordinance 162-16. | $77,000 | |
| Nov 3, 2017 | Expired or cancelled cancelled Jan 2026 | 444 43rd Av | Emery Pacific Construction | replace (e) driveway & planters in front yard per s.f. planning code section 132.Details
replace (e) driveway & planters in front yard per s.f. planning code section 132. | $1,500 |
| Dec 13, 2016 | Completed final sign-off May 2017 | 1132 Hampshire St | Partee Construction Co | relocate extg bedroom and kitchen in both units and open kitchen area to extg living room. fire remediation, including framing repair/replacement, finish repair/replacement, kitchen fixtures and work in bathroom area is under seperate permit.Details
relocate extg bedroom and kitchen in both units and open kitchen area to extg living room. fire remediation, including framing repair/replacement, finish repair/replacement, kitchen fixtures and work in bathroom area is under seperate permit. | $15,000 |
| Jun 19, 2015 | Completed final sign-off Sep 2016 | 8219 Geary Bl | Hua Da Construction | remodel of an extg full bath and reconfigure extg bedroom closet.Details
remodel of an extg full bath and reconfigure extg bedroom closet. | $9,000 |
| Jul 10, 2014 | Completed final sign-off Apr 2016 | 2371 17th Av | Millennium Construction Company, Success Construction ***See Notes*** | remodel (e) kitchen & bath, reconfigure (e) bedrooms upstairs & add to provide 3 beds/2 bath upstairs & 1 bed/1 family room/2 bath downstairs.horizontal additionDetails
remodel (e) kitchen & bath, reconfigure (e) bedrooms upstairs & add to provide 3 beds/2 bath upstairs & 1 bed/1 family room/2 bath downstairs.horizontal addition | $130,000 |