How long do stairs permits take in San Francisco's Western Addition neighborhood?

In the Western Addition neighborhood of San Francisco, of the 9 stairs permits filed from October 2025 through September 2026 that have been issued, half were issued within 7 days, down from 50 days a year earlier. Of the 10 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 290 days of being issued, up from 93 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long stairs permits take in San Francisco's WesternAddition neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004005006002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/western-addition/stairs · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 20269 issued717 issued50
Permit issued to final sign-offOctober 2023 through September 202410 finished2909 finished93

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 7 days to issue and 175 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41000too recent
2026-Q35410too recent
2026-Q22110too recent
2026-Q12220too recent
2025-Q42210too recent
2025-Q33330too recent
2025-Q299521118561710too recent
2025-Q13320too recent
2024-Q43210too recent
2024-Q3109363672933910yes
2024-Q23320yes
2023-Q43210yes
2023-Q33330yes
2023-Q25431yes
2023-Q14430yes
2022-Q33221yes
2022-Q24222yes
2022-Q1983251355436793yes
2021-Q45519147841yes
2021-Q32220yes
2021-Q21110yes
2021-Q11110yes
2020-Q43220yes
2020-Q33220yes
2020-Q21110yes
2020-Q15440yes
2019-Q4653505623061yes
2019-Q34421yes
2019-Q21110yes
2019-Q155018332yes
2018-Q42220yes
2018-Q33321yes
2018-Q21110yes
2018-Q17701805683041yes
2017-Q44430yes
2017-Q3760061266500yes
2017-Q23220yes
2017-Q11100yes
2016-Q42211yes
2016-Q33330yes
2016-Q22220yes
2016-Q13330yes
2015-Q4652731431yes
2015-Q365651,03351348830yes
2015-Q299411781244361yes
2015-Q13312yes
2014-Q44440yes
2014-Q39904298204350yes
2014-Q2870216451601yes
2014-Q13330yes
2013-Q4109215063106052yes
2013-Q377165343yes
2013-Q23330yes
2013-Q15440yes
2012-Q46605261044390yes
2012-Q388016473054531yes
2012-Q24404yes
2012-Q11110yes
2011-Q42220yes
2011-Q3662785564761yes
2011-Q26601855371091yes
2011-Q1881274124961yes
2010-Q48718641yes
2010-Q35440yes
2010-Q23330yes
2010-Q13211yes
2009-Q455049140yes
2009-Q376012862056380yes
2009-Q212110011502320yes
2009-Q1990661503003yes
2008-Q43330yes
2008-Q3650540yes
2008-Q210903922520yes
2008-Q1121017481305123yes
2007-Q49901717491621yes
2007-Q31817091131112783yes
2007-Q225252828231192761yes
2007-Q112123838112584040yes
2006-Q43310yes
2006-Q31010006281381yes
2006-Q255028021yes
2006-Q113120326852202yes
2005-Q46603640yes
2005-Q31010010633yes
2005-Q27702156882101yes
2004-Q42210yes
2004-Q33330yes
2004-Q24330yes
2004-Q13220yes
2003-Q43330yes
2003-Q34422yes
2003-Q25528832622yes
2003-Q12201yes
2002-Q4850012yes
2002-Q33311yes
2002-Q26609431yes
2002-Q13310yes
2001-Q4550030yes
2001-Q32220yes
2001-Q22210yes
2001-Q177032340yes
2000-Q42210yes
2000-Q3990556303010yes
2000-Q24430yes
2000-Q1550452604530yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

63 of the 546 stairs permits filed since 2000 (12%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Western Addition neighborhood

Shown apart, with their own page here: kitchen remodel (2,623 filed, 2,004 finished; contractors); bathroom remodel (2,344 filed, 1,806 finished; contractors); stairs (546 filed, 385 finished; contractors); deck (272 filed, 208 finished; contractors). Other types: 9,088 permits. All permits in San Francisco's Western Addition neighborhood

Nearby neighborhoods

Japantown, Hayes Valley, Pacific Heights; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.