How long do bathroom remodel permits take in San Francisco's Western Addition neighborhood?

In the Western Addition neighborhood of San Francisco, of the 74 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 70 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 93 days of being issued, down from 104 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sWestern Addition neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/western-addition/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202674 issued063 issued0
Permit issued to final sign-offOctober 2023 through September 202470 finished9384 finished104

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q42100too recent
2026-Q3201801330too recent
2026-Q2252401615801270too recent
2026-Q11615116121031460too recent
2025-Q41817033111031800too recent
2025-Q32020059161042360too recent
2025-Q217160014741560too recent
2025-Q1101001971055600too recent
2024-Q419170911821960too recent
2024-Q313110610901860yes
2024-Q229280725832930yes
2024-Q1151508151033410yes
2023-Q423230520961950yes
2023-Q32827016221041644yes
2023-Q2303001823982367yes
2023-Q127250423742253yes
2022-Q41918015161403911yes
2022-Q32121029181242242yes
2022-Q22625041201503205yes
2022-Q12727027221045063yes
2021-Q42725291201362854yes
2021-Q33232045271542733yes
2021-Q22323043191383284yes
2021-Q12525063191124725yes
2020-Q43131079251083596yes
2020-Q3252425119943554yes
2020-Q2151531415981400yes
2020-Q12321011121923717yes
2019-Q4494731638603026yes
2019-Q362620855363136yes
2019-Q2484502836622749yes
2019-Q1424102436642214yes
2018-Q4474703341752146yes
2018-Q3383701130952817yes
2018-Q2434331133771588yes
2018-Q1525202743591867yes
2017-Q45958115491111936yes
2017-Q35252023451062136yes
2017-Q2474705240552795yes
2017-Q146450439452566yes
2016-Q4353504229972024yes
2016-Q35450649357630712yes
2016-Q2413842333842214yes
2016-Q1302902425811904yes
2015-Q439390452411123515yes
2015-Q3434304635615106yes
2015-Q252491224431056447yes
2015-Q143420537482524yes
2014-Q4323102223691796yes
2014-Q34745041318325510yes
2014-Q2393901256213410yes
2014-Q1363401325593229yes
2013-Q42827047201092995yes
2013-Q3262508201153064yes
2013-Q218180148161212322yes
2013-Q1211909151335714yes
2012-Q4252501191183455yes
2012-Q32523012171233512yes
2012-Q22121020171633583yes
2012-Q117160213721560yes
2011-Q4171704315832292yes
2011-Q31313029111191681yes
2011-Q2131300101702042yes
2011-Q14440yes
2010-Q4131301481181633yes
2010-Q32020020152409131yes
2010-Q2202000121383073yes
2010-Q1880271306921yes
2009-Q41111077911601yes
2009-Q311110110988301yes
2009-Q21111028814951yes
2009-Q11615014121052611yes
2008-Q4660041yes
2008-Q3181808161242361yes
2008-Q2171700111092401yes
2008-Q1222103171003003yes
2007-Q418180115982651yes
2007-Q3171704111392064yes
2007-Q220200018902640yes
2007-Q1212100171182693yes
2006-Q4171700122103622yes
2006-Q36601241yes
2006-Q2171700121321792yes
2006-Q1151500111612380yes
2005-Q4161606392304261yes
2005-Q377006962540yes
2005-Q29905572235920yes
2005-Q17707340yes
2004-Q499007643441yes
2004-Q32210yes
2004-Q2650040yes
2004-Q13330yes
2003-Q42211yes
2003-Q32202yes
2003-Q23321yes
2003-Q12220yes
2002-Q43330yes
2002-Q37703162262330yes
2002-Q24430yes
2002-Q1111100111211840yes
2001-Q410100081924721yes
2001-Q34420yes
2001-Q24430yes
2001-Q14330yes
2000-Q46601251862920yes
2000-Q3550020yes
2000-Q23310yes
2000-Q11100yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

293 of the 2,344 bathroom remodel permits filed since 2000 (13%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Western Addition neighborhood

Shown apart, with their own page here: kitchen remodel (2,623 filed, 2,004 finished; contractors); bathroom remodel (2,344 filed, 1,806 finished; contractors); stairs (546 filed, 385 finished; contractors); deck (272 filed, 208 finished; contractors). Other types: 9,088 permits. All permits in San Francisco's Western Addition neighborhood

Nearby neighborhoods

Japantown, Hayes Valley, Pacific Heights; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.