How long do bathroom remodel permits take in San Francisco's Seacliff neighborhood?

In the Seacliff neighborhood of San Francisco, of the 22 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, down from 5 days a year earlier. Of the 31 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 283 days of being issued, down from 437 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sSeacliff neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge02004006008002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/seacliff/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202622 issued036 issued5
Permit issued to final sign-offOctober 2023 through September 202431 finished28314 finished437

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41000too recent
2026-Q37400too recent
2026-Q211110185701060too recent
2026-Q15400too recent
2025-Q44300too recent
2025-Q399011740too recent
2025-Q2121252061222100too recent
2025-Q19982940too recent
2024-Q46655230too recent
2024-Q316161125112243330yes
2024-Q21111155103434930yes
2024-Q1121202494166750yes
2023-Q44410yes
2023-Q3554621441yes
2023-Q297258344yes
2023-Q15432yes
2022-Q44331yes
2022-Q34321yes
2022-Q28614633yes
2022-Q177040656447391yes
2021-Q47708856577722yes
2021-Q3651777055921,3140yes
2021-Q2662615142yes
2021-Q16440yes
2020-Q44321yes
2020-Q34421yes
2020-Q1761675631yes
2019-Q477343863918460yes
2019-Q37733062045200yes
2019-Q28766664066721yes
2019-Q112121410582987363yes
2018-Q44440yes
2018-Q366023442yes
2018-Q26601823yes
2018-Q166105252222900yes
2017-Q48795333yes
2017-Q36636472856411,2130yes
2017-Q26606842yes
2017-Q199075761683362yes
2016-Q48807451906100yes
2016-Q313135228121862810yes
2016-Q2119913084085231yes
2016-Q177015052382731yes
2015-Q487214061044821yes
2015-Q311112602105658490yes
2015-Q29901972745322yes
2015-Q18801261715442yes
2014-Q4660165567690yes
2014-Q365823741yes
2014-Q2131312431103227681yes
2014-Q18818384106850yes
2013-Q455110630yes
2013-Q355211540yes
2013-Q2882461864411yes
2013-Q155115740yes
2012-Q49933272173252yes
2012-Q388021372971,7060yes
2012-Q288623662746822yes
2012-Q19916873555821yes
2011-Q4881038082946020yes
2011-Q399118762856342yes
2011-Q288222773237110yes
2011-Q155126553635590yes
2010-Q4111139893534310yes
2010-Q34330yes
2010-Q2551653504600yes
2010-Q1550352054070yes
2009-Q47711971554830yes
2009-Q3550331yes
2009-Q22210yes
2009-Q155813041yes
2008-Q477115763423931yes
2008-Q366024962243930yes
2008-Q211902072073281yes
2008-Q199043172164740yes
2007-Q45430yes
2007-Q39903461442780yes
2007-Q2101002181582490yes
2007-Q1770720yes
2006-Q411110081923850yes
2006-Q33330yes
2006-Q215150100112013430yes
2006-Q188019761403590yes
2005-Q41211026042yes
2005-Q31111028791333601yes
2005-Q266011540yes
2005-Q14440yes
2004-Q44420yes
2004-Q31110yes
2004-Q2990051591841yes
2004-Q1660030yes
2003-Q4660030yes
2003-Q3660021yes
2003-Q299050541yes
2002-Q455014920yes
2002-Q3870021yes
2002-Q277025041yes
2002-Q16606940yes
2001-Q43310yes
2001-Q34410yes
2001-Q211110061181780yes
2001-Q17701151602120yes
2000-Q465017610yes
2000-Q3880040yes
2000-Q26601020yes
2000-Q14420yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

65 of the 763 bathroom remodel permits filed since 2000 (9%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Seacliff neighborhood

Shown apart, with their own page here: bathroom remodel (763 filed, 503 finished; contractors); kitchen remodel (548 filed, 369 finished; contractors); stairs (345 filed, 210 finished; contractors); deck (289 filed, 181 finished; contractors); roof deck (79 filed, 44 finished; contractors). Other types: 3,420 permits. All permits in San Francisco's Seacliff neighborhood

Nearby neighborhoods

Outer Richmond, Lincoln Park, Inner Richmond; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.