How long do bathroom remodel permits take in San Francisco?

In San Francisco, of the 3,506 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, down from 1 day a year earlier. Of the 2,805 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 169 days of being issued, down from 176 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San FranciscoMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002502017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/san-francisco/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 20263,506 issued03,655 issued1
Permit issued to final sign-offOctober 2023 through September 20242,805 finished1692,900 finished176

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q452100100too recent
2026-Q31,0157550228341780too recent
2026-Q21,088972150324761290too recent
2026-Q1946863059458941820too recent
2025-Q499691611065521302660too recent
2025-Q31,0259760936361403020too recent
2025-Q21,0119661866761523420too recent
2025-Q19188761886351403580too recent
2024-Q488183701076211573640too recent
2024-Q39138661686741763990yes
2024-Q21,0721,0361758291915240yes
2024-Q18227830596681594890yes
2023-Q483378911146341544936yes
2023-Q3924872165705176529153yes
2023-Q2946901196744166557116yes
2023-Q1862801064650169538129yes
2022-Q41,0799933182801198537152yes
2022-Q31,0269580109797175537123yes
2022-Q21,1061,0431106854195672160yes
2022-Q11,2051,143179957192575154yes
2021-Q41,2111,1402101940204610147yes
2021-Q31,1991,154098944198626164yes
2021-Q21,3701,29901171,031194656221yes
2021-Q11,4071,31701981,030204679249yes
2020-Q41,4741,347262021,030201659297yes
2020-Q31,2671,1773170866190656260yes
2020-Q2414382711230615449055yes
2020-Q11,0139250259721214667167yes
2019-Q41,3931,28053621,007247749229yes
2019-Q31,3251,25821521,001195719209yes
2019-Q21,3371,2371122984182702238yes
2019-Q11,2231,1571110979177621142yes
2018-Q41,2421,1602161951196769175yes
2018-Q31,2341,1691133945178636170yes
2018-Q21,3271,24021441,031183607166yes
2018-Q11,3361,2481189973180613225yes
2017-Q41,2271,1723239932206658177yes
2017-Q31,2961,2391204994182659186yes
2017-Q21,3841,29012521,029185614202yes
2017-Q11,1111,0551158864164579137yes
2016-Q41,1781,1022215871177636157yes
2016-Q31,3261,25132131,004188595193yes
2016-Q21,2851,2071154969182612173yes
2016-Q11,3101,22201561,005170632166yes
2015-Q41,1671,1211152880192668175yes
2015-Q31,3351,27711981,022197661198yes
2015-Q21,4041,33011681,084186612178yes
2015-Q11,3151,25611031,029175586170yes
2014-Q41,2531,1961164947184708184yes
2014-Q31,3171,261183956184600234yes
2014-Q21,3301,29011141,037169623177yes
2014-Q11,1931,150062923145504170yes
2013-Q41,2561,2141135975176609171yes
2013-Q31,2681,217053978173533175yes
2013-Q21,2591,2240671,002152542152yes
2013-Q11,0601,038041852138527127yes
2012-Q4966932055748159537130yes
2012-Q31,0441,006037851155458122yes
2012-Q21,005968045818134409108yes
2012-Q187986205072914042788yes
2011-Q481579106867014545878yes
2011-Q398395003780513938076yes
2011-Q292089304976013944167yes
2011-Q182179403469513540854yes
2010-Q480477507366515547365yes
2010-Q384181017069315844260yes
2010-Q294692305878515543270yes
2010-Q177274803862114744871yes
2009-Q479876406561814648281yes
2009-Q382179703367315040066yes
2009-Q278675213762614042864yes
2009-Q169566805555915339057yes
2008-Q476172804557214938850yes
2008-Q31,0871,04802379015041796yes
2008-Q21,0971,06804578615138286yes
2008-Q11,023982038713146368109yes
2007-Q41,1611,110092761163424139yes
2007-Q31,2161,17706797149360151yes
2007-Q21,0771,06601751154376117yes
2007-Q11,0551,0350273115037086yes
2006-Q48888700157815339080yes
2006-Q39619460062416540183yes
2006-Q296495502766516040885yes
2006-Q18668600161815437556yes
2005-Q482581402454418141189yes
2005-Q387686301159215637889yes
2005-Q28428280157715536180yes
2005-Q16266180042516637565yes
2004-Q46396230042815038665yes
2004-Q372371101050714835771yes
2004-Q275374102749612736883yes
2004-Q16126030042114836375yes
2003-Q461560302443913335943yes
2003-Q364263003442615232869yes
2003-Q268066803747413636170yes
2003-Q154553805337913036558yes
2002-Q456054809337814435861yes
2002-Q359257205537816239059yes
2002-Q260759204139415334654yes
2002-Q148847609433613735921yes
2001-Q446546005831013331010yes
2001-Q34764650622851503887yes
2001-Q251549801033311523682yes
2001-Q15014870443301393525yes
2000-Q44734590862881523833yes
2000-Q34834700602821574272yes
2000-Q25134930583051553773yes
2000-Q14884640592701754707yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

11,095 of the 104,357 bathroom remodel permits filed since 2000 (11%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco

Shown apart, with their own page here: bathroom remodel (104,357 filed, 75,687 finished; contractors); kitchen remodel (88,742 filed, 63,705 finished; contractors); stairs (42,896 filed, 29,067 finished; contractors); deck (24,218 filed, 16,266 finished; contractors); roof deck (5,264 filed, 3,106 finished; contractors); pergola or trellis (645 filed, 372 finished; contractors). Other types: 613,041 permits. All permits in San Francisco

Every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.