Permit GraphShortlistSan Francisco building permits since 2000

How long do bathroom remodel permits take in San Francisco's Pacific Heights neighborhood?

In the Pacific Heights neighborhood of San Francisco, of the 157 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 1 day, up from 0 days a year earlier. Of the 123 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 158 days of being issued, up from 132 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sPacific Heights neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/pacific-heights/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026157 issued1170 issued0
Permit issued to final sign-offOctober 2023 through September 2024123 finished158121 finished132

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41000too recent
2026-Q3463313740too recent
2026-Q2534903113731150too recent
2026-Q13836073191011890too recent
2025-Q4433917248131543250too recent
2025-Q35047050291192170too recent
2025-Q24443299271543080too recent
2025-Q14544039301622990too recent
2024-Q43636060261443520too recent
2024-Q33838266241503290yes
2024-Q24444038381923870yes
2024-Q13534018301203920yes
2023-Q43939088311545280yes
2023-Q33331027272034105yes
2023-Q234342237271083843yes
2023-Q126250181211356574yes
2022-Q45855078461344008yes
2022-Q33232067271848062yes
2022-Q242421139373089125yes
2022-Q16060444541726856yes
2021-Q45755039462345924yes
2021-Q36060050511996559yes
2021-Q284810675919867317yes
2021-Q1878301286516955314yes
2020-Q47265191365320659813yes
2020-Q36259698471936837yes
2020-Q224245110182509153yes
2020-Q144370234321948356yes
2019-Q45550145372177249yes
2019-Q357561504326467011yes
2019-Q25552446431917799yes
2019-Q14242076391674342yes
2018-Q45956042451856769yes
2018-Q352510393918471410yes
2018-Q24843138371364655yes
2018-Q16158030511626667yes
2017-Q43737098272186445yes
2017-Q36256088482121,1306yes
2017-Q2615801214623467813yes
2017-Q15553038381322749yes
2016-Q444420181351401,1374yes
2016-Q339380112331844573yes
2016-Q24847026401865747yes
2016-Q15047029391124217yes
2015-Q44444041321426968yes
2015-Q36160094482085389yes
2015-Q261602101521805353yes
2015-Q163610188492385177yes
2014-Q45351043402447239yes
2014-Q367640264220958814yes
2014-Q256540109462087405yes
2014-Q15048021441243982yes
2013-Q468652167532129815yes
2013-Q35351069392458699yes
2013-Q25050022431824234yes
2013-Q16463017521503688yes
2012-Q44544016301425028yes
2012-Q34743020361243566yes
2012-Q26565010571735263yes
2012-Q14646093361054867yes
2011-Q430300125231894224yes
2011-Q35453063441393945yes
2011-Q24444052361444744yes
2011-Q14040026341934372yes
2010-Q43838179301925983yes
2010-Q336340179321714040yes
2010-Q2616109542099772yes
2010-Q14949038381744867yes
2009-Q43837063281304392yes
2009-Q33635243341664601yes
2009-Q22626010221437272yes
2009-Q14341014361363404yes
2008-Q4232306171563112yes
2008-Q34443015322064893yes
2008-Q2666407501393535yes
2008-Q15151014331093716yes
2007-Q450490163362103896yes
2007-Q3646402451263425yes
2007-Q27373016531454176yes
2007-Q1727200561503083yes
2006-Q4565602341513162yes
2006-Q36361003017244210yes
2006-Q2505003341864715yes
2006-Q1454500263624832yes
2005-Q4333300232164540yes
2005-Q33535034222503781yes
2005-Q2474600281643531yes
2005-Q1292900172394221yes
2004-Q4323100231402960yes
2004-Q3262600161462641yes
2004-Q24444038302013953yes
2004-Q1343400281763302yes
2003-Q4272700192253620yes
2003-Q32828023201703531yes
2003-Q2292900202115223yes
2003-Q12828028222146061yes
2002-Q4262605192134321yes
2002-Q3272600111854764yes
2002-Q2343401161923543yes
2002-Q12727023181873312yes
2001-Q41818051111533500yes
2001-Q317170121101804000yes
2001-Q22120057151277450yes
2001-Q12626041142584900yes
2000-Q4181700112424150yes
2000-Q3212001982404010yes
2000-Q2363500191834550yes
2000-Q12523017131693911yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

445 of the 4,845 bathroom remodel permits filed since 2000 (9%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Pacific Heights neighborhood

Shown apart, with their own page here: bathroom remodel (4,845 filed, 3,523 finished; contractors); kitchen remodel (4,365 filed, 3,192 finished; contractors); stairs (1,514 filed, 952 finished; contractors); deck (949 filed, 637 finished; contractors); roof deck (336 filed, 200 finished; contractors). Other types: 24,826 permits. All permits in San Francisco's Pacific Heights neighborhood

Nearby neighborhoods

Japantown, Marina, Western Addition; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.