How long do bathroom remodel permits take in San Francisco's Outer Richmond neighborhood?

In the Outer Richmond neighborhood of San Francisco, of the 214 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 1 day, down from 3 days a year earlier. Of the 157 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 197 days of being issued, down from 206 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sOuter Richmond neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/outer-richmond/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026214 issued1218 issued3
Permit issued to final sign-offOctober 2023 through September 2024157 finished197178 finished206

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q42000too recent
2026-Q36450024570840too recent
2026-Q265606561068930too recent
2026-Q14543090191041670too recent
2025-Q46561170331502820too recent
2025-Q36357079361663060too recent
2025-Q27167680461843870too recent
2025-Q150494119331823840too recent
2024-Q447453292331403710too recent
2024-Q33433032271673660yes
2024-Q26764259551894740yes
2024-Q15451149392084010yes
2023-Q450482176362324481yes
2023-Q36156476471955798yes
2023-Q2484711301371996928yes
2023-Q15049072392055136yes
2022-Q4776911305523461911yes
2022-Q34843085331575288yes
2022-Q248422229362536207yes
2022-Q16059169531924224yes
2021-Q4484610208322705309yes
2021-Q354535125462406187yes
2021-Q2736902235727882110yes
2021-Q179750213612146709yes
2020-Q48170412685732171810yes
2020-Q352520239402756729yes
2020-Q223231397182093474yes
2020-Q157512409392321,01311yes
2019-Q47065136954936069016yes
2019-Q36963164592247345yes
2019-Q275654905223857710yes
2019-Q16964791582335295yes
2018-Q4686462105121157913yes
2018-Q35451188432136626yes
2018-Q271670291582246826yes
2018-Q159520170442367634yes
2017-Q471697252582426718yes
2017-Q360570253502247505yes
2017-Q27168070622316593yes
2017-Q15753060461713857yes
2016-Q458560238431976919yes
2016-Q373671464532037059yes
2016-Q267642453521987493yes
2016-Q172666116561765299yes
2015-Q463612207502115049yes
2015-Q35554542472346103yes
2015-Q2897533805727063313yes
2015-Q16359032521534104yes
2014-Q44644286391673880yes
2014-Q361575200462107107yes
2014-Q27270671551834308yes
2014-Q15654246411794597yes
2013-Q478780102622285655yes
2013-Q35858231501885332yes
2013-Q25252071442506642yes
2013-Q15351055422106346yes
2012-Q44140054331624715yes
2012-Q35148025411164026yes
2012-Q24442029371103202yes
2012-Q14745030401283455yes
2011-Q437361112301292515yes
2011-Q349480178431073833yes
2011-Q262620111511393869yes
2011-Q140380121331354363yes
2010-Q42929052271314761yes
2010-Q34845040381412977yes
2010-Q23737115331403212yes
2010-Q12524030221743641yes
2009-Q455520198401416949yes
2009-Q3454208351132346yes
2009-Q24139120351212923yes
2009-Q13433027261884384yes
2008-Q4322901241363112yes
2008-Q3545309421412565yes
2008-Q26360084615433010yes
2008-Q16056013421343207yes
2007-Q465650215471813927yes
2007-Q35452073512032710yes
2007-Q2585802451523543yes
2007-Q1403900291362865yes
2006-Q4383700261283204yes
2006-Q3414100321162632yes
2006-Q2414100301463224yes
2006-Q1474700351562980yes
2005-Q4444400301643464yes
2005-Q3555400351833404yes
2005-Q2363600311302710yes
2005-Q1474600341523511yes
2004-Q43230068241484030yes
2004-Q343420258301533370yes
2004-Q234340103221483511yes
2004-Q13232017231413623yes
2003-Q4191900131352650yes
2003-Q3363600271492912yes
2003-Q238370146271282820yes
2003-Q124230179201163260yes
2002-Q43737014251462710yes
2002-Q326260160201331912yes
2002-Q2242400132183543yes
2002-Q12424079161363720yes
2001-Q4262600201792660yes
2001-Q32525013191323550yes
2001-Q2232200141954510yes
2001-Q128270617932220yes
2000-Q426260815931580yes
2000-Q33332094181643030yes
2000-Q22625043161602400yes
2000-Q126260136141432470yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

456 of the 5,388 bathroom remodel permits filed since 2000 (8%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Outer Richmond neighborhood

Shown apart, with their own page here: bathroom remodel (5,388 filed, 3,961 finished; contractors); kitchen remodel (4,536 filed, 3,308 finished; contractors); stairs (2,059 filed, 1,409 finished; contractors); deck (1,133 filed, 752 finished; contractors); roof deck (217 filed, 139 finished; contractors). Other types: 23,687 permits. All permits in San Francisco's Outer Richmond neighborhood

Nearby neighborhoods

Seacliff, Lincoln Park, Golden Gate Park; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.