How long do kitchen remodel permits take in San Francisco's Outer Mission neighborhood?

In the Outer Mission neighborhood of San Francisco, of the 38 kitchen remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 5 days, up from 2 days a year earlier. Of the 30 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 194 days of being issued, down from 219 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long kitchen remodel permits take in San Francisco's OuterMission neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004005002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/outer-mission/kitchen · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202638 issued547 issued2
Permit issued to final sign-offOctober 2023 through September 202430 finished19445 finished219

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 176 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q36501710too recent
2026-Q2141126630too recent
2026-Q12116115261962360too recent
2025-Q466817430too recent
2025-Q318161114111742240too recent
2025-Q2880216562180too recent
2025-Q1131112133111664350too recent
2024-Q41312946111822170too recent
2024-Q31717036122173070yes
2024-Q21818012411742940yes
2024-Q1971110053084340yes
2023-Q45504920yes
2023-Q310931382203952yes
2023-Q2109010572263151yes
2023-Q1141210425112383971yes
2022-Q4242346186191854754yes
2022-Q31313916793525234yes
2022-Q2161614302163119120yes
2022-Q1885133572784520yes
2021-Q42019093162405903yes
2021-Q31313017092074862yes
2021-Q2111009991515470yes
2021-Q120190178132977506yes
2020-Q41515101419122527923yes
2020-Q310106747981953641yes
2020-Q23330yes
2020-Q117156311132455072yes
2019-Q4171514455102235214yes
2019-Q31311720392637422yes
2019-Q21818070121958036yes
2019-Q117160171114018694yes
2018-Q414135558112073330yes
2018-Q31313011101193383yes
2018-Q218160293121165504yes
2018-Q115140196122441,7341yes
2017-Q4101001881363282yes
2017-Q31515024102204894yes
2017-Q22119012141642894yes
2017-Q116115196112797151yes
2016-Q4111014253025282yes
2016-Q320190455172246211yes
2016-Q2151410157122401,6002yes
2016-Q11614227121886872yes
2015-Q416165394162837020yes
2015-Q3109016071212612yes
2015-Q21817132142588751yes
2015-Q115140388121625312yes
2014-Q410100993617511yes
2014-Q31715440101964994yes
2014-Q21818021161663372yes
2014-Q1111115381612623yes
2013-Q4111124592034761yes
2013-Q377067351424932yes
2013-Q2141425391082063yes
2013-Q1171503713721771yes
2012-Q45501341yes
2012-Q310912391104401yes
2012-Q218180213751783yes
2012-Q1131301281062745yes
2011-Q4990792203900yes
2011-Q317160015603402yes
2011-Q2990661021351yes
2011-Q1191801517892040yes
2010-Q41515017121186452yes
2010-Q31212013111473231yes
2010-Q2109055491396210yes
2010-Q110100107644773yes
2009-Q41111011101063580yes
2009-Q315120195111682692yes
2009-Q212120181964002yes
2009-Q115150610673023yes
2008-Q415150481822306yes
2008-Q314120111831271yes
2008-Q2181800141102703yes
2008-Q1141402121422041yes
2007-Q4990261186051yes
2007-Q313120091501820yes
2007-Q213130212101463041yes
2007-Q1131309810944550yes
2006-Q4111100101282490yes
2006-Q39903681894170yes
2006-Q255005881850yes
2006-Q1101002971043290yes
2005-Q4101002091712610yes
2005-Q313130071956461yes
2005-Q288016361343140yes
2005-Q1990565744061yes
2004-Q48808340yes
2004-Q3990061082821yes
2004-Q23330yes
2004-Q187055551130yes
2003-Q41111008801961yes
2003-Q31211015881033601yes
2003-Q24421yes
2003-Q1101004444yes
2002-Q48806061203460yes
2002-Q3660285563480yes
2002-Q266038051192130yes
2002-Q1880461062240yes
2001-Q4101001471002340yes
2001-Q3660030yes
2001-Q2141401546682,8380yes
2001-Q188005251080yes
2000-Q47702251632150yes
2000-Q3990661924390yes
2000-Q299025152524110yes
2000-Q12210yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

142 of the 1,307 kitchen remodel permits filed since 2000 (11%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Outer Mission neighborhood

Shown apart, with their own page here: bathroom remodel (2,084 filed, 1,559 finished; contractors); kitchen remodel (1,307 filed, 942 finished; contractors); stairs (749 filed, 512 finished; contractors); deck (403 filed, 278 finished; contractors). Other types: 8,343 permits. All permits in San Francisco's Outer Mission neighborhood

Nearby neighborhoods

Excelsior, Oceanview/Merced/Ingleside, Glen Park; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.