How long do bathroom remodel permits take in San Francisco's Haight Ashbury neighborhood?

In the Haight Ashbury neighborhood of San Francisco, of the 81 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, down from 1 day a year earlier. Of the 74 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 193 days of being issued, up from 186 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sHaight Ashbury neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/haight-ashbury/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202681 issued090 issued1
Permit issued to final sign-offOctober 2023 through September 202474 finished19378 finished186

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q42000too recent
2026-Q3221801300too recent
2026-Q225210216531030too recent
2026-Q12423077151031650too recent
2025-Q424194100121982630too recent
2025-Q32828292181362520too recent
2025-Q23432067231212940too recent
2025-Q12119112815994120too recent
2024-Q4121111371133300too recent
2024-Q316166168131683420yes
2024-Q22929478242305100yes
2024-Q12523077161923710yes
2023-Q43230034211493971yes
2023-Q32929033261823762yes
2023-Q22019027161723612yes
2023-Q12828091722738910yes
2022-Q431290651916242110yes
2022-Q328250200211953835yes
2022-Q234332782326849811yes
2022-Q1484871333319352411yes
2021-Q42323195191955103yes
2021-Q334331106242367667yes
2021-Q235320211253409337yes
2021-Q138340231252309127yes
2020-Q45854381873719768612yes
2020-Q331290122212395943yes
2020-Q2131045671761,0202yes
2020-Q135342233272586195yes
2019-Q4443810417313069566yes
2019-Q332324152272005683yes
2019-Q23636054291423497yes
2019-Q127261120161785525yes
2018-Q43834262281825587yes
2018-Q34644111653019279311yes
2018-Q235330264271234405yes
2018-Q129271434221553784yes
2017-Q437352546263126228yes
2017-Q345440202331523759yes
2017-Q235332591261408125yes
2017-Q125252543191577424yes
2016-Q425230123152537265yes
2016-Q349445450352495957yes
2016-Q23129090241685114yes
2016-Q139391103341575374yes
2015-Q450481197361683817yes
2015-Q340371502819152410yes
2015-Q23028027252166632yes
2015-Q13532033281363313yes
2014-Q43634051252166326yes
2014-Q347454893114959912yes
2014-Q239390992819878810yes
2014-Q14040017311243745yes
2013-Q44745060361786307yes
2013-Q33331019261606355yes
2013-Q231300192261505003yes
2013-Q133330137281766223yes
2012-Q421210288181837193yes
2012-Q32928020221963495yes
2012-Q2272606231243472yes
2012-Q12222047181515352yes
2011-Q422220112201353352yes
2011-Q32221013211813300yes
2011-Q23635256301865573yes
2011-Q13131011272154680yes
2010-Q4272705221443731yes
2010-Q32323147211683502yes
2010-Q23131155272095792yes
2010-Q12524012191687464yes
2009-Q42725396231574302yes
2009-Q322224107201873591yes
2009-Q22020166171774252yes
2009-Q12624177171332046yes
2008-Q42928016252014180yes
2008-Q33533060221209585yes
2008-Q24141031291815015yes
2008-Q128270186211503984yes
2007-Q441400220281888879yes
2007-Q33836018242003527yes
2007-Q2313100211612745yes
2007-Q1353400231716492yes
2006-Q4323106141463405yes
2006-Q340400105251844764yes
2006-Q2242400201674211yes
2006-Q13232050221924374yes
2005-Q4292802162183342yes
2005-Q3272700191743640yes
2005-Q23535075181222584yes
2005-Q1191900131903221yes
2004-Q411100052534851yes
2004-Q3191800121823532yes
2004-Q2252500151582383yes
2004-Q115150071293836yes
2003-Q4990641yes
2003-Q3141307071153092yes
2003-Q2242300101081687yes
2003-Q1161600121342633yes
2002-Q412100671724403yes
2002-Q316150165111345053yes
2002-Q2202002991942893yes
2002-Q12525039121543541yes
2001-Q414130061241980yes
2001-Q312120061461940yes
2001-Q2151504132023010yes
2001-Q11616017172523341yes
2000-Q4202009151483300yes
2000-Q3131305962584750yes
2000-Q218170091723421yes
2000-Q1212103091023710yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

397 of the 3,075 bathroom remodel permits filed since 2000 (13%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Haight Ashbury neighborhood

Shown apart, with their own page here: bathroom remodel (3,075 filed, 2,147 finished; contractors); kitchen remodel (2,766 filed, 1,877 finished; contractors); stairs (1,550 filed, 1,064 finished; contractors); deck (751 filed, 494 finished; contractors); roof deck (170 filed, 96 finished; contractors). Other types: 15,744 permits. All permits in San Francisco's Haight Ashbury neighborhood

Nearby neighborhoods

Lone Mountain/USF, Castro/Upper Market, Hayes Valley; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.